PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Advertisements

1 Powering Tests and Safety Electrical Safety Hugues Thiesen Power Converter Group.
Challenges of a Harmonized Global Safety Regime Jacques Repussard Director General IRSN IAEA 2007 Scientific Forum.
October 2009 Klaus Grensemann, Division WS 23 St. Petersburg 1 Development and Implementation of an Overall E-Navigation Strategy.
Status Report for Critical Infrastructure Protection Advisory Group
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
HL-LHC Configuration Management Keywords : HW Baseline, Naming, Parameters, Layout DB, Change Control The HiLumi LHC Design Study (a sub-system of HL-LHC)
TS, Length of YETS EYETS LIU & CONS Project
Access zones and Training Steve Hutchins BE-ASR IEFC workshop 7/3/2012.
1 EARLY SAFETY MANAGEMENT OF PROJECTS AND EXPERIMENTS HSE UNIT PH DSO EDMS No
1 1. Some recent views ( ) 2 Linac tunnel
Samy Chemli – Configuration Management - S. Chemli EN-MEF – Contents Configuration Management Hardware Baseline Change Management.
LS2 Safety Thomas Otto, LS2 Safety Coordinator.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
19/11/2015 PSB and PS&TT2 Facilities YETS L. Kobzeva.
RSSO REPORT TE-MSC Andrea Musso – Virginia Prieto Hermosilla (RSSO’s) Acknowledgments - We wish to thanks: Michele Modena (Safety Link Person TE-MSC) for.
Last but not least : LS2 General Safety 1 Thomas Otto, LS2 Safety Coordinator for LHC Ana-Paula Bernardes, LS2 Safety Coordinator for Injectors.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Radiation Protection computing tools Gérald Dumont HSE/RP.
R2E Workshop Preparations RadWG Meeting March 25 th.
Evaluation Expert Committee 2nd meeting SYNTHESIS OF THE ANNUAL PROGRESS REPORTS FOR 2007 CONCERNING ONGOING EVALUATION Irina RAMNICEANU Helpdesk Evaluation.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Electrial Safety LS2 days November 2016 AP
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
Survey on “Chargés de Consignation” Status Update
Magnet activities in SPS during EYETS
LHC intervention scheduling with the Work Acceptance Tool
LIU and TE/VSC activities LIU-SPS aC coating & flange impedance reduction Paul Cruikshank LIU & TE/VSC activities, 23/6/2016 Paul Cruikshank.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
V4.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
East Area Renovation Project Team meeting # 2 – EDMS News
Target & Frontend Switch Yard & Collection Boxes Medicis Seminar, 2nd and 3rd March 2016 Stefano Marzari EN-STI & Vincent Barozier EN-ACE.
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
Update on the Critical Path of the PS Booster Schedule for the EYETS
LIU Consolidation project (INDICO ) E. Blanco BE/ICS
East Hall under construction
Forecasts for waste and radioactive material storage
Injector De-cabling Project
The revised Periodic Reporting Questionnaires: general features Alessandra Borchi Policy and Statutory Meetings Section UNESCO World Heritage Centre.
Safety in Construction and Upgrade Phases
LIU – EVM status and next steps
AD consolidation activities in LS2
Configuration Management and Layout Database ELENA Project
LIU–PLI report LIU PSB meeting.
News from EVM.
LINAC4 50 MeV phase BIS STATUS
EC Activities Status for the LIU
Buffer Zones - Status Report
EN 4946 – Refurbishment of Electrical Substations
De-cabling strategy during YETS
M.Jonker CTC MPO-WG status
Keeping LHC cold during LS periods Preliminary proposal
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
SPS Planning for the EYETS Meeting 8 (07/12/2016)
PSB lock-out test - Organisation AP. Bernardes, D. Hay, C
Survey on “Chargés de Consignation” Follow-up
SPS activities during LS2 TE-EPC (Power Converter Group)
Cryogenic Risk Assessment in LHC
GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (SMB/SE) Olivier Barrière.
YETS & LS2 Works EN-EL / Power distribution
Overview & baseline of LS2 and roadmap for CRG
East Hall under construction
GIS Portal Racks Project
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Activities of the UNECE-UNODC Task Force on Victimization Surveys
Exemptions and Disproportionate Costs
Implementation of RP training ranks in SPS and NA_target
Radiation Working Group RADWG
Presentation transcript:

PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K PSB Lock Out Test, Follow-Up AP.Bernardes-/EN-STI, K.Boonroy/HSE-SEE, D.Hay/EN-ACE, C.Mugnier/TE-EPC, S.Ugidos/EP-DT Acknowledgements: W.Andreazza/BE-BI, JP.Burnet/TE-EPC, L.Coralejo/TE-ABT, A.Day/HSE-RP, P.Demarest/TE-VSC, T.Dobers/EN-ACE, G.Dumont/HSE-RP, JA.Ferreira Somoza/TE-VSC, S.Fumet/EN-HE, JC.Guillaume/EN-EL, M.Haase/BE-RF, T.Masson/TE-ABT, V.Montabonnet/TE-EPC, A.Newborough/TE-MSC, H.Sabri/EN-CV, J.Tassan-Viol/BE-BI

Outline Introduction Status Proposal for PSB machine access Next steps Conclusion 30 June 2017 LS2 Committee

Machine oriented approach Transversal Activity approach Introduction Focus on the 2 first cases 3 cases with 3 different approaches are proposed for the “PSB tests”: Machine oriented approach PSB (machine) Access and electrical state of the machine (EYETS, YETS, TS, LS2)  Electrical hazard mapping, training, habilitation PSB Period approach Intervention on the PSB (machine) PERIOD 2 (EYETS, YETS, TS, LS2)  Lock-out procedure, definition of roles and responsibilities? Work package New Injection Region 1L1 (LS2)  Lock-out procedure, definition of roles and responsibilities? Transversal Activity approach 30 June 2017 LS2 Committee

Introduction Mission : Select 3 cases where electrical safety is critical and where the lock-out procedure needs to be clarified Define a pilot methodology and apply it to the 3 selected cases Identify the groups concerned, contact them and clarify with them the lock-out steps based on the electrical hazard assessment Write the operational procedures with the groups contribution If the procedures are approved they should be followed on field when applicable, feed-back should be collected from groups Present feed-back of the results and the procedure at the LS2 Committee of April 2017 30 June 2017 LS2 Committee

Outline Introduction Status Proposal for PSB machine access Next steps Conclusion 30 June 2017 LS2 Committee

Status Electrical Hazard assessment Done for the PSB (machine): Electrical equipment group owners for the PSB machine BE-BI BE-RF EN-EL TE-ABT TE-MSC TE-VSC Main PSB machine non electrical equipment contributors for YETS, EYETS, LS: EN-ACE EN-CV EN-HE HSE-RP 30 June 2017 LS2 Committee

Status Electrical Hazard assessment done with the equipment owner or the activity responsible: Inventory of the accessible live parts Inventory of the main activities taking place close to accessible live parts To be done: Check through EDMS of each hazard assessment presentation by the different groups  Summary to be presented at the LS2 committee 30 June 2017 LS2 Committee

Status Main Difficulty: No updated layout available. Each group has corrected/completed the layout No central data base for electrical network. Schematics are a mixture of EN-EL and TE-EPC data bases EN-EL TE-EPC Electrical hazard assessment and electrical schematics will not be valid anymore after significant changes on the PSB machine (After LS2) 30 June 2017 LS2 Committee

Status In an ideal world! Central data base for mechanical and electrical layout to contain verified and updated information required for lock-out purposes (as done today for the magnetic elements of the LHC and SPS-LHC transfer lines) Through this data base it could be possible to select an equipment or area and to identify which equipment should be lock-out before intervention What to do meanwhile? 30 June 2017 LS2 Committee

Outline Introduction Status Proposal for PSB machine access Next steps Conclusion 30 June 2017 LS2 Committee

Proposal for PSB machine access To access the PSB (machine) – What? Define a network separation pre-requisite for “general access” and make sure it is approved by all the groups concerned (applicable (E)YETS, LS) Network separation of all equipment with accessible live parts Network separation of all equipment with non accessible live parts if groups already do it systematically Make clear which equipment remain switched OFF during (E)YETS, LS Machine oriented approach PSB Access and electrical state of the machine (EYETS, YETS, TS, LS2)  Electrical hazard mapping, training, habilitation Objective: Get the same minimal electrical state of the PSB at each EYETS, YETS, LS during general access --> Avoid confusion and human errors 30 June 2017 LS2 Committee

Proposal for PSB machine access Network separation is not a lock-out ! The absence of voltage is not checked and the equipment is not grounded. The PSB (machine) can not be considered in a safe state to perform electrical work or non electrical in the surroundings of accessible live parts! The groups remain responsible for requesting there lock-out before their intervention!  No work in the shadows of a network separation or a lock-out made for another activity! 30 June 2017 LS2 Committee

Proposal for PSB machine access To access the PSB (machine) – Who? The facility coordinator can request the Network separation pre-requesite for general access if a procedure is approved by all the groups (First step). The groups remain responsible for requesting their lock-out before the intervention! Network separation could be done at EN-EL level when possible (quicker procedure, less possibility of human errors) Network separation for access Objective: Clarify responsibilities and make official/optimize good practices 30 June 2017 LS2 Committee

Proposal for PSB machine access To access the PSB (machine) Advantages Disadvantages Electrical state for (E)YETS, LS of the machine is defined and approved by all groups concerned. The approach remains every time the same and is official Equipment owners can not power the equipment without the facility coordinators agreement (during general access only!) No more confusion about “Shut-down” and “YETS” Special cases need to be defined from the beginning (Example: BE-RF commissioning during LS2) No powering without planning  Improve electrical safety and planning Procedures need to be checked before (E)YETS and LS Electrical safety is introduced in the planning just like radiation protection. Facility coordinator knows the state of the machine 30 June 2017 LS2 Committee

Proposal for PSB machine access To access the PSB (machine) – How? The Facility coordinator of the PSB machine request a network separation request) based on procedure approved by the groups and keeps the paper until the end of the general access First-Line and EN-EL The facility coordinator of the PSB owns all the network separation requests sheets “General Access” can start Equipment owners or activity owners perform their own lock-out procedure before intervention at the equipment level as usual! 30 June 2017 LS2 Committee

Outline Introduction Status Proposal for PSB machine access Next steps Conclusion 30 June 2017 LS2 Committee

Machine oriented approach Transversal Activity approach Next steps Machine oriented approach PSB (machine) Access and electrical state of the machine (EYETS, YETS, TS, LS2)  Electrical hazard mapping, training, habilitation PSB Period approach Intervention on the PSB (machine) PERIOD 2 (EYETS, YETS, TS, LS2)  Lock-out procedure, definition of roles and responsibilities? Work package New Injection Region 1L1 (LS2)  Lock-out procedure, who is concerned, who does what? Transversal Activity approach Not started but very similar to case 2 Assessment done. Proposition to be discussed. Well advanced. Feed back from groups needed 30 June 2017 LS2 Committee

Outline Introduction Status Proposal for PSB machine access Next steps Conclusion 30 June 2017 LS2 Committee

Great collaboration from all the groups! Thank you very much!!! Conclusion Electrical Hazard assessment done (to be circulated in EDMS) The procedure was slow because of layout and data base issues Difficult to keep this information updated without a centrally maintained mechanical and electrical database as reliable source of information (as is existing today for LHC) Proposal for PSB machine access done. Please provide feed-back! Proposal for PSB machine electrical work still to be discussed Great collaboration from all the groups! Thank you very much!!! 30 June 2017 LS2 Committee