Further Tracking Studies and March Trip Plan

Slides:



Advertisements
Similar presentations
1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Advertisements

ATF2: Status Update Glenn Christian (on behalf of FONT group) 10 th ATF Project Meeting.
N. BlaskovicFONT Meeting1 Preliminary resolution study results N. Blaskovic.
Coupling Correction in ATF2 EXT 7 th ATF2 Project Meeting, december 2008 C.Rimbault, LAL Orsay.
FONT Meeting1 Calibrations over IP LO power scan N. Blaskovic.
Emittance Measurement Simulations in the ATF Extraction Line Anthony Scarfe The Cockcroft Institute.
Analysis of ATF EXT/FF Orbit Jitter and extrapolation to IP (Data of ) ATF2 Project Meeting K. Kubo.
Progress towards nanometre-level beam stabilisation at ATF2 N. Blaskovic, D. R. Bett, P. N. Burrows, G. B. Christian, C. Perry John Adams Institute, University.
N. BlaskovicFONT Meeting1 ATF February-March 2014 shift plan N. Blaskovic.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis, Colin Perry.
Discussion on Milestone and schedule Toshiyuki Okugi ATF2 commissioning meeting 1 / 7 / 2009.
Ground Motion + Vibration Transfer Function for Final QD0/SD0 Cryomodule System at ILC Glen White, SLAC ALCPG11, Eugene March 21, 2011.
1 FONT Results 2010 Philip Burrows Robert Apsimon, Doug Bett, Glenn Christian Michael Davis, Colin Perry, Javier Resta Lopez John Adams Institute Oxford.
FJPPL-FKPPL Workshop on ATF21 FONT digitisation studies of IP BPMs D. Bett, N. Blaskovic, P. Burrows, G. Christian, M. Davis, Y. I. Kim, C. Perry John.
ATF2 Tuning Updates Glen White, SLAC Sept
Continuous Run in May K.Kubo. Final Focus Test Line IP; ~40 nm beam ATF Linac (1.3 GeV) ATF Damping Ring (140 m) Extraction Line Photo-cathode.
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
ILC BDS Static Beam-Based Alignment and Tuning Glen White SLAC 1.Aims. 2.Error parameters and other assumptions. 3.Overview of alignment and tuning procedure.
Development of a Low-latency, High-precision, Intra-train Beam Feedback System Based on Cavity Beam Position Monitors N. Blaskovic Kraljevic, D. R. Bett,
Mark Woodley, SLACATF2 Project March 20-21, Summary of Tuning, Corrections, and Commissioning.
IP BPM Shift Report FONT Meeting: 22 December 2014 Talitha Bromwich.
1 FONT R&D status Philip Burrows Douglas Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John Adams Institute Oxford University.
ATF2 Commissioning Toshiyuki Okugi 2008 / 7 /9 ATF2 beam commissioning meeting, KEK.
FONT Hardware Processing electronics and current beam tests Stephen Molloy Queen Mary, University of London.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
FONT Meeting1 Charge normalisation and IP LO power scan N. Blaskovic.
Analysis of Multipole and Position Tolerances for the ATF2 Final Focus Line James Jones ASTeC, Daresbury Laboratory.
N. BlaskovicFONT Meeting1 ATF October 2014 shift plan N. Blaskovic.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett*, Talitha Bromwich, Glenn Christian, Michael Davis, Colin Perry.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John.
Superfast BPM Processor Scheme and First Results Stephen Molloy, QMUL 2 nd Mini-Workshop for Nano-Project at ATF.
ATF2 Tuning Summary Nov & Dec 2010 Glen White, SLAC 11 th ATF2 Project Meeting, SLAC Jan
Task Lists of ATF2 commissioning Toshiyuki Okugi ATF2 Project Meeting 12 / 17 / 2008.
Simulations - Beam dynamics in low emittance transport (LET: From the exit of Damping Ring) K. Kubo
N. BlaskovicFONT Meeting1 ATF November 2013 shift plan N. Blaskovic.
Summary of Tuning, Corrections, and Commissioning ( Short summary of ATF2 meeting at SLAC in March 2007 ) and Hardware Issues for beam Tuning Toshiyuki.
NumberMikey Davis02 November 2012 Roundup of ATF Trip.
FONT GROUP MEETING ATF JUNE SUMMARY Neven & Talitha Talitha Bromwich - Friday, 26 June 2015.
1 Feedback On Nanosecond Timescales (FONT): Philip Burrows Neven Blaskovic, Douglas Bett, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John.
1 IP FB tests at ATF2 Philip Burrows Douglas Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Young Im Kim, Colin Perry John Adams Institute Oxford.
Status and plan of Beta-matching in Extraction line Kiyoshi Kubo.
Wakefield effect in ATF2 Kiyoshi Kubo
Overview of progress at FONT Neven Blaskovic TMD technologies CASE student John Adams Institute Oxford University.
1/33Mikey Davis24 January 2013 Review of 23 rd of January Shift.
1 FONT IP FB Philip Burrows Robert Apsimon, Doug Bett, Neven Blaskovic, Glenn Christian, Michael Davis, Colin Perry John Adams Institute Oxford University.
IP Tuning Task Updates Glen White, SLAC January
D. BettATF Operations Meeting - 15 June IP C. Perry G. Christian Y. Kim D. Bett N. Blaskovic Kraljevic.
N. Blaskovic, T. Bromwich, R. Ramjiawan
Roundup of Week at ATF Mikey Davis 19 April /26.
ILC BDS Alignment, Tuning and Feedback Studies
Expected hardware status and Priority of the commissioning task
Resolution Study T. Bromwich FONT 8 September 2017.
Emittance Diagnostics
Tolerances & Tuning of the ATF2 Final Focus Line
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Emittance Dilution and Preservation in the ILC RTML
Feedforward runs N. Blaskovic N. Blaskovic FONT Meeting.
Firmware Update 29/03/2017 Rebecca Ramjiawan.
Analysis of March ATF Run
ATF Shift Plans Rebecca, Talitha 08/09/2017 Friday, 08 September 2017
Coupling Correction at the Australian Synchrotron
ATF2 IP Tuning Task Simulation Updates
Accelerator Physics Technical System Group Review
March Trip Plan Mikey Davis 01 March /7.
Revised ATF Shift Plans
Beam Optics Set-Up at SLAC End Station A
Progress towards nanometre beam stabilisation at ATF2
Updates on IR and FF for super-B factory
Status of Phase Feedforward Tests
Extraction kicker scan & feedback results
Presentation transcript:

Further Tracking Studies and March Trip Plan Mikey Davis 01 March 2012 1/12

Further IP Simulations I wanted to see how moving the waist affected the constant that converts mover pos to beam pos at the IP I run a number of simulations which involved Move the waist Track particles using different QD0FF pos Move waist I think what I’ve found makes sense Mikey Davis 01 March 2013 2/12

Further IP Simulations Mikey Davis 01 March 2013 3/12

Further IP Simulations Mikey Davis 01 March 2013 4/12

Trip Plan I’ve planned with the idea that we should: Repeat some of the calibration studies we did in January Focus on beam conditions rather than correction Study correlations and how to improve them Young Im and Glenn have also suggested some tests we could do on the IP BPMs As we are concerned the BPM resolution could be part of our problem also worth studying Also there is some stuff we missed out last time I think we should redo Mikey Davis 01 March 2013 5/12

First Shift - Focus on IP BPMs LO Phase Scan Upstream Calibration (mover scan) Centre beam in IP BPMs IP Waist Scan IPBM Calibration Centre waist at BPM Go from -50 to 50 (microns) around centre – alter depending on atten Record EPICS and compare it, jitters should be the same Do this with a number of different attenuation settings, at least 20 dB and 30 dB – see if we can do 20dB without sat IP waist scan Tedious but quick, I’d like some more of these for cross checks Mikey Davis 01 March 2013 6/12

First Shift - IP BPMs Focus Switch around the second stage downmixer for IPA and IPB Take some jitter runs – maybe very coarse calibrations See if the switch has any effect Charge vs Jitter Scan at IP BPMs See if we’re limited by resolution IP Kicker Calibration Single bunch Lots of small steps Cross check EPICs and HONDA Upstream kicker calibrations Single Bunch Lots of very small steps Retest Jan Results Mikey Davis 01 March 2013 7/12

First Shift - IP BPMs Focus Switch to two bunch mode Recalibrate IP BPMs Measure the bunch to bunch correlations Check the new extraction kicker setup hasn’t changed anything Check the downstream bunch to bunch cor (IP feedback) Mikey Davis 01 March 2013 8/12

Second Shift – Correlations LO Phase Scan Upstream Calibration (mover scan) Centre beam in IP BPMs IP Waist Scan IPBM Calibration Centre waist at BPM Go from -50 to 50 (microns) around centre – alter depending on atten Record EPICS and compare it, jitters should be the same Do this with a number of different attenuation settings, at least 20 dB and 30 dB – see if we can do 20dB without sat IP waist scan Mikey Davis 01 March 2013 9/10

Second Shift – Correlations From Glen White: Switching off the QK skew quads when they are being used to correct incoming coupling will change the projected emittance. This will increase the vertical beam sizes everywhere up to a factor of 2. This by itself might give you more jitter correlation simply because there is going to be more jitter, but also improve jitter correlation because you don't couple y kick into the horizontal. Turning them off will also change the dispersion function downstream. Depending on the conditions before, the dispersion function at your measurement points will either get better or worse. Having a different dispersion function at your different measurement points will change the correlation you refer to. Turning the skew-quads off may also change the beta matching, effecting the relative beam sizes at the different locations a bit. The only thing you can really do to improve matters after switching off the QK's is to do a dispersion correction. You can also use the measured dispersion values and use the strengths of the QK's (if they are on) in a model to calculate exactly what you expect. Recently it was found that the QS skew-quads can be used to partially correct for the coupling which greatly reduces the required strength of the QK's. This may help you out quite a bit as I think both the QS magnets are upstream of you. Mikey Davis 01 March 2013 10/12

Second Shift – Correlations Measure the dispersion Do this in a number of places throughout the line Measure upstream downstream cor. Turn off skew quads Re measure dispersion Re measure cor. Dispersion correction See if you can achieve the level measured in 7 Attempt to redo coupling correction with skew sextuples I worry this might be a bit beyond us Redo dispersion correction Mikey Davis 01 March 2013 11/12

Final Thoughts We should probably have a go at measuring the emittance and beamsize whilst we are doing these tests Maybe switch shift two with shift one Should we instrument P1 or MQF15X? From Glenn X and Y? Damping ring? Mikey Davis 01 March 2013 12/12