High-Beta cavity STATUS at DAREsbury laboratory

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
G. Olry for the IPN Orsay team 5 th SPL collaboration meeting, 25-26/11/2010, CERN.
G. Olry, H-M Gassot, S. Rousselot (IPN Orsay) EuCARD-SRF annual review 2011, 4-5 May, IPN, Orsay Unité mixte de recherche CNRS-IN2P3 Université Paris-Sud.
ESS cavities interfaces
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
WP : HIGH-BETA CAVITY DELIVERY A Wheelhouse ASTeC, STFC Daresbury Laboratory ESS SRF Elliptical Cavities Kick-Off Meeting CEA Saclay 15 th December.
ESS WP 12 Project Management & Capabilities Overview Neil Bliss Projects & Mechanical Engineering Group Leader ESS PDR, Lund, 10 th November 2015.
HIGH-BETA CAVITY DELIVERY P McIntosh ASTeC, STFC Daresbury Laboratory ESS Technical Advisory Committee Lund 1 – 2 April 2015.
FNAL efforts on LHC Crab Cavity R&D (Proposals for R&D sub-tasks, resources and schedule) Nikolay Solyak.
LASA Medium-β Cavity Progress Update Paolo Michelato 2 nd ESS Collaboration Meeting - SRF Elliptical Cavities 15 th December 2015.
Spoke test in vertical cryostat IPNO-UU Meeting on spoke test program, 2 nd -3 st October 2013 IPNO Team.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Medium Beta Cavities Paolo Michelato, Paolo Pierini, and Carlo Pagani INFN Milano - LASA.
Medium beta cavities Paolo Michelato, Paolo Pierini, Carlo Pagani INFN Milano - LASA.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Accelerator/WP High-Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April, 2016.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
7th SRF Materials Workshop FRIB SRF Cavities 7/16/12 Chris Compton.
Integration and Cold Testing of the CW ERL Cryomodule at Daresbury Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) On behalf of ERL Cryomodule.
Status of Vertical Test Stand at RRCAT P Shrivastava, P Mohania,D.Baxy, Vikas Rajput S C Joshi, S Raghavendra,S K Suhane RRCAT, Indore November 26, 2012.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
WP : HIGH-BETA CAVITY DELIVERY A Wheelhouse ASTeC, STFC Daresbury Laboratory ESS SRF Elliptical Cavities Kick-Off Meeting CEA Saclay 23 rd June 2015.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Developing the Collaboration P McIntosh STFC Daresbury Laboratory.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
H-ECCTD KICK-OFF DESCRIPTION AND CHALLENGES 16/03/2016 F. PEAUGER.
WP : High-Beta Cavity Delivery
H-ECCTD KICK-OFF DEVELOPMENT PLAN AND SCHEDULE 16/03/2016.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
WP High Beta Cavities Delivery
Status of the M-ECCTD F. Peauger - P. Bosland
S1G Experiment Schedule Plan
Field Emission Minimization for LCLS-II
Cryomodule test stand at ESS site
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
Status and plans for the 3.9 GHz section of XFEL
WP5 Elliptical cavities
ESS cavity procurement via in-kind contributions
at STFC Daresbury laboratory
Mark Pendleton – STFC Daresbury Laboratory
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Uppsala Commitment to ESS and FREIA Planning
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
WG-1 Session Cavity Performance Cryomodule Performance
HL-LHC-UK: UK contribution to HL-LHC Crab Cavities and evolution
Jiyuan Zhai ( IHEP ) TTC Meeting, JLAB, 6 Nov 2012
ESS RF Development at Uppsala University
UK RFD Pre-Series cryomodule
Horizontal Tests in a Vertical Cryostat
HIE-LINAC status report
SNS Cryoplant Commissioning Past Experiences
Cryomodules Challenges for PERLE
A. Bignami on behalf of LASA SRF Group
Prototype cryomodule development
Daresbury ESS In-Kind Contributions
ESS High Beta Cavities Quality Assurance and Control - Learning and Planning Workshops, CEA Saclay, 30 June - 1 July 2016 Mark Pendleton STFC, Daresbury.
SuRf Lab: (STFC) VTF Infrastructure and Process
Presentation transcript:

High-Beta cavity STATUS at DAREsbury laboratory A Wheelhouse on behalf of the STFC team ASTeC, STFC Daresbury Laboratory ESS Collaboration Meeting 13th - 14th June 2017

Outline High-β Cavity Programme Infrastructure Preparations ESS Requirements & Program Project Scope Project Schedule Infrastructure Preparations Cavity Qualification Preparation Procurement QA Future Plans Summary

High-β Cavity Programme

ESS Program STFC WP5 Programme is part of the UK IKC to ESS INFN 5 cells high beta (0.86) cavity 6-cells medium beta (0.67) cavity Cavities without HOM coupler INFN Production of 36 dressed medium-β cavities STFC Production of 84 (+ 4 spares) dressed high-β cavities CEA Saclay Design of medium and high-β cavities Design of cryomodules Prototypes Cryomodule integration Programme is part of the UK IKC to ESS

ESS Requirements WP5 Cavities without HOM coupler 5 cells high beta (0.86) cavity 6-cells medium beta (0.67) cavity Cavities without HOM coupler Medium-β High-β Geometrical β 0.67 0.86 Frequency (MHz) 704.42 No. of Cryomodules 9 21 Cavities /Cryomodule 4 No. of Cavities 36 84 Cryomodule length (m) 6.584 Nominal Accelerating gradient (MV/m) 16.7 19.9 Nominal Accelerating Voltage (MV) 14.3 18.2 Q0 at nominal gradient > 5 x 109 Similar to CEBAF/SNS cryomodule concept with 4 cavities per cryomodule Common cryomodule design for medium and high beta cavities

Scope Manage Eddy Current Scanning (DESY) STFC In-Kind Contribution: Niobium procurement Manage Eddy Current Scanning (DESY) Validation of treatment processes (esp. BCP) in industry using ‘pre-series’ cavities Cavity fabrication of 84 high beta cavities in industry 2K RF qualification of cavities to 22.9MV/m, Q0 ≥ 5 x 109 Transport to Saclay

High-β Cavity Schedule KEY Critical path STFC or industry Industry task STFC or external STFC task

High-β Cavity Schedule Critical Path: Nb tender process & Nb lead time Pre-series fabrication & test Series final assembly Qualification testing KEY Critical path STFC or industry Industry task STFC or external STFC task

High-β Cavity Schedule Near-critical path (limited float): Fabrication tender Tooling & preparations KEY Critical path STFC or industry Industry task STFC or external STFC task

High-β Cavity Schedule VTF Preparations & Plans Final deliveries due mid summer Assembly & commissioning of subsystems independently Integration & controls development in parallel (not shown) 2K commissioning with known cavities to compare measurements KEY Critical path STFC or industry Industry task STFC or external STFC task

High-β Cavity Schedule Hold point: Trimming & welding of HC for series cavities only after successful pre-series tests KEY Critical path STFC or industry STFC task Industry task STFC or external

Infrastructure Preparations

SRF Hall VTF Cleanroom Full crane coverage Cryo-plant Offices upstairs He Compressor House Offices upstairs Cavity Goods-In & Out downstairs Thin Film Lab Crab Lab 20m VTF Cleanroom Cryo-plant 55m

Shielding Detailed assessment performed by Nuclear Technology Bunker excavation completed ~2.0m Concept block shielding design completed Concrete thickness is defined – 1.85 m Final shielding design progressing with suppliers; iterating for installation crane requirements Includes radiation detectors inside the bunker for each cavity Being reviewed in 2 weeks time

Cryogenic Plant Air Liquide Advance Technologies have provided (Feb 2017) : He Liquefier (100 l/h) 3000 l LHe Dewar Helium Recovery System (10g/s) Installation is on-going Commissioning of system due to commence end of June 2017 Produce liquid He (4K) PFD & Process description Cold Box Dewar

Cryogenic Plant Air Purification Dryer Cycle and Recovery Compressors Majority of the pipework is in place (except final connections) Electrical distribution on-going Frame work for gas bag recovery system is due in June PLC program for 2K pumps is being developed Oil Recovery System

Cryostat Cavity support inserts (inverted for assembly purposes!) Cavities to be tested horizontally Crystat is being produced by Criotec Cryostat ahead of schedule Delivery June Magnetic shielding is being provided by MSL Magnetic Shield Ltd and has been completed Test fitting successfully undertaken at Criotec Delivery to Daresbury is being arranged Installation scheduled - June / July Cryostat pressure vessel & thermal shielding 2K Box

Cleanroom Cleanroom HPR System CEA HPR System The cleanroom design has been surveyed by an external cleanroom specialist and reviewed by external experts to ensure the correct standards are met for the re-work of the high-β cavities. Outline procedures for the cavity workflow and personnel are complete. A zoned area for the disassembly + assembly of the cavity has been incorporated into the design to ensure ISO 4 standards are maintained – for QA/QC. Order to be raised in August HPR System Specification for the HPR facility has been completed and reviewed by external experts. Design based on the HPR system at CEA Saclay Tender has been run and an order placed with Acmel Acceptance test to be performed with a Perspex cavity CEA HPR System

Cleanroom ISO 4 areas: Assembly room & HPR ISO 5 areas: Changing room & Preparation room ISO 7 area: Inspection room

Cryostat Insert Stand Requirements: Structure to hold 2 Cryostat inserts 1500kg, laden ~1800kg (each) Personnel access for vacuum and electrical connections to be made on top of the cryostat. Access for cavity lifters to load and Unload cavities between the structure support legs. Framework to support a cleanroom solution. Access from the ground floor or office platform including escape route.

Modular Cleanroom Progress Modular cleanroom testing has been completed Two configurations reviewed Full cleanroom Large glovebox Glovebox design is the preferred solution Modular cleanroom & cavity support stand Design being finalised Contract for manufacture is imminent Target for fabrication and installation to be completed by the end of June Mock-up for testing & training

RF System Rack design reviewed and finalised drawings completed All parts have been delivered; rack build to be completed by the end of June LLRF control system being developed Labview control system based on JLabs system developed by Tom Powers FPGA system being developed in-house; Self-excited loop algorithm has been implemented and tested IOC software development is on-going Cold system testing to be performed using a Nb coaxial resonator (Q~1x107) and cryo-cooler - planned for June/July First cold tests using a cryostat targeted for Nov 2017 FPGA Development Rack Labview Control System RF Rack

Cavity Qualification Preparation

Procurement Major procurements are on-going Niobium Cavity fabrication Niobium – Initial tender unsuccessful 4 bids received; none compliant Technical, commercial, schedule and selection issues Market survey repeated and specification has been revised Tender to be re-launched soon Eddy current scanning of the sheets is to be performed at DESY Cavity Fabrication Specification on-going (90% complete) Market survey performed Planned pre-series cavity production ‘Final’ design and drawings awaited from ESS/CEA; existing drawings to be used on tender Design issues Flange on diphasic line Helium inlet (bimetallic transition)

QA: Cavity Fabrication Niobium Acceptance Detailed STFC scheme in development Aligning with known systems XFEL, LASA, industrial experience Incorporate prototype learning Incorporate any requirements specific to ESS Cryomodule design Will include all required control measurements RF frequency, FF, HOM spectra Mechanical dims, CMM etc Visual inspections, ultrasound Treatment parameters Mass measurements Acceptance level 1 A.L. 2 Acceptance Level 3

Future Plans & Summary

Future Plans Re-launch Nb tender Launch cavity fabrication tender Progress infrastructure installation and commissioning Cryoplant commissioning Cryostat delivery – July 2017 RF system commissioning – Dec 2017 HPR system delivery – Jan 2018 Cleanroom delivery – Jan 2018

Summary Infrastructure development progressing well with much progress made over the last year - Need to ensure the schedule is maintained Nb procurement is on the critical path – Tender to be re- launched. Cavity fabrication tender to follow shortly after Nb tender Schedule for the high-β elliptical cavities is tight wrt the ESS programme Programme needs continued strong coordination between ESS, STFC, CEA & INFN to ensure requirements and timescales are maintained

Any Questions

Additional Slides

Horizontal Tests in a Cryostat Aim to test 3 cavities horizontal in the cryostat Diameter sufficient to test 3 vertically if required Helium vessel will be used to cool the cavities: Reduced LHe requirements  75% saving on LHe and gas storage Automatic leak checks on He vessel Higher confidence in performance Quicker cool-down/warm up periods Cryostat order placed with Criotec Schedule discussions held Kick-off meeting 1st June 2016 Requirements to be fully defined and agreed Delivery May 2017 (Improvement from the original date of July 2017) Cryostat Proposed Design

Magnetic Shielding of the Cryostat Target field at the cavities is 1µT Background field measurements performed Defined magnetic shield needed to be capable dealing with fields of:- 100 µT vertically 50 µT horizontally Full size model of shield constructed in OPERA – 2D with background fields and accurate mu-metal BH curve Defines a mu-shield thickness of 1.5 mm For the lid a cylinder designed with a coil around the inside the top to provide active shielding allows suitable compensation of field at current densities in the region of 0.4 – 0.45 A/mm2 for heights below 1.8 m

Modular Cleanroom Progress Insert 2 Insert 1 Laminar Flow Unit Full enclosure Full enclosure Changing room Laminar Flow Unit Laminar Flow Unit Cleanroom 1 Cleanroom 2

Glovebox Solution The Glovebox solution has been designed to: Reduce the size of the cleanroom. Speed up the process, minimising cleaning of the cavity and infrastructure – reduced manpower. Eliminate the changing area and full gowning procedures. User friendly solution for enclosure/ isolation of the cavities. Reduce overall costs. Fixed particle counter monitoring for each cavity – quality control. Cavity 1 ISO 3 1 Cavity 2 ISO 3 2 Cavity 3 3 ISO 5 Laminar Flow Unit Best result: ISO 3 at rest Glovebox