M.Fitterer, A.Patapenka, A.Valishev (FNAL)

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Flat-beam IR optics José L. Abelleira, PhD candidate EPFL, CERN BE-ABP Supervised by F. Zimmermann, CERN Beams dep. Thanks to: O.Domínguez. S Russenchuck,
BSRT CALIBRATION MD SUMMARY LSWG #6-15/09/2015 BSRT TEAM.
First Collision of BEPCII C.H. Yu May 10, Methods of collision tuning Procedures and data analysis Luminosity and background Summary.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
Beam-beam compensation at RHIC LARP Proposal Tanaji Sen, Wolfram Fischer Thanks to Jean-Pierre Koutchouk, Frank Zimmermann.
February 5, 2005D. Rubin - Cornell1 CESR-c Status -Operations/Luminosity -Machine studies -Simulation and modeling -4.1GeV.
Beam Physics Issue in BEPCII Commisionning Xu Gang Accelerator physics group.
Beam-Beam head-on Limit J. Barranco, X. Buffat, T. Pieloni, C. Tambasco, J. Qiang, K. Ohmi, M. Crouch for the Beam-Beam team BI BSRT Team George and Enrico.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Linear optics - I Low beta* at injection –Reduction of injection could potentially reduce time to collisions and allow for a more relaxed ramp&squeeze,
Crossing Schemes Considerations and Beam-Beam Work plan T. Pieloni, J. Barranco, X. Buffat, W. Herr.
Fabio Follin Delphine Jacquet For the LHC operation team
Y.Papaphilippou Thanks to
Luminosity monitor and LHC operation
Operating IP8 at high luminosity in the HL-LHC era
Scenarios for 2017 and 2018 Thanks to Gianni, Fanouria, Gianluigi, Dario, Stephane, Elias, Michi, Jamie, Christoph, Rogelio, Mirko, Riccardo, Hannes,
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wire tests at injection energy
MD Planning Fri – Sat (26. – 27.8.)
Transverse Damping Requirements
1st LHC MD Period Started
LHC Commissioning with Beam
Task 2. 5: Beam-beam studies D. Banfi, J. Barranco, T. Pieloni, A
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Space charge studies at the SPS
Updated scenario and simulations for the BBLR LHC test
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wire, flat beams and beam-beam MDs in 2017
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Beam-beam Effects in Hadron Colliders
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Field quality to achieve the required lifetime goals (single beam)
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
Lost at 12:05 to power converter (RTQX2.R1) problem
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
HL-LHC operations with LHCb at high luminosity
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Pushing the LHC nominal luminosity with flat beams
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
MD Planning Fri – Sat (1. – 2.7.)
Summary for LPC (March 7th, Ralph Assmann)
Summary Tuesday h23: Machine closed. Precycle started.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Large emittance scenario for the Phase II Upgrade of the LHC
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

M.Fitterer, A.Patapenka, A.Valishev (FNAL) Second workshop for wire experiment for LRBB compensation, 20/03/2017 Wish list for wire MDs Y.Papaphilippou, G.Arduini, S.Fartoukh, R.Jones, D.Pellegrini, S.Redaelli, A.Rossi, H.Schmickler, G.Sterbini, R.Tomas (CERN), M.Fitterer, A.Patapenka, A.Valishev (FNAL)

Outline List of MD studies for 2017 Commissioning (beyond HW tests), preparation (crossing angle scans) and compensation tests Goals and procedures Beam parameters Intensity, emittance, train composition Machine configuration Energy, optics, crossing angle, orbit control, tune, chromaticity, octupole current Wire settings Position (alignment) and currents L/R of IP5 Observables and associated instrumentation Further beam-beam wire related studies, including synergies with other MDs Prioritization (following 1, 2, 3, 4) MD time request and time-line Key simulation studies for preparing MDs Y.Papaphilippou - 3/20/2017

Wire impact on single beam - goal Priority 1, 2, 3, 4 Goal: Test and calibrate the effect of the wires in a single beam Need to measure impact of wires on beam orbit, tune, beta-beating, chromaticity, tune-spread, coupling, RDTs Calibrate wires and estimate orbit and tune feedback functions during the compensation tests Align wires with respect to the beam (vertical orbit, coupling) Similar measurements for the external wires can be foreseen, but also for negative polarity and with vertical position at non-zero, e.g. @ 45o degrees Estimate impact in lifetime and emittance (tails, halo?) and compensate with other wire Y.Papaphilippou - 3/20/2017 See presentation of G.Sterbini

Wire impact on single beam – set-up Priority 1, 2, 3, 4 Energy: All can be done at 450 GeV Qualification of tune and orbit feed-forward would be desirable at 6.5 TeV Beams required: Only beam 2 Could be compatible with parallel studies using beam 1 Beam composition and intensity: Single nominal bunches of 1.3 x 1011 ppb ome tests can function already with probe Emittances: Nominal BCMS, i.e. ~1.5-2.0 μm.rad Optics: Nominal @ injection with nominal injection tunes, octupoles and chromaticity settings More exotic options if testing compensation or lifetime impact can be foreseen (for example beam2 squeezed with beam1 nominal, equal β aspect ratio at the wire,…) Y.Papaphilippou - 3/20/2017 See presentation of G.Sterbini

Wire impact on single beam - procedure Alignment Move the TCT collimators with 1 wire at a time and measure impact on vertical orbit, align the jaw to minimise this. Measure coupling. Orbit, tune For fixed wire distance (jaw at ~6 σcol), measure impact of different currents to the beam orbit and tune Do the same for fixed current, moving the collimator jaw. Set-up orbit and tune feed-forward Chromaticity: With corrected orbit and tunes, measure impact in chromaticity (maybe also non-linear) for different currents Beta-beating, tune-spread, RDTs: Usual optics correction set-up Repeat above for external wires and negative polarity Lifetime and emittance: With corrected orbit and tunes, measure impact in lifetime and emittance evolution. Compensate with other wire (needs special optics) Time needed: 1.5 x 8 h, 2 x 8 h, 3 x 8 h, 4 x 8 h Priority 1, 2, 3, 4 Y.Papaphilippou - 3/20/2017 See presentation of G.Sterbini

BBLR Compensation preparation - goal Priority 1, 2, 3, 4 Goal: Measure the crossing angle reduction impact on lifetime Ideally, part of the commissioning Synergy with crossing angle levelling setting-up Energy: 6.5 TeV Beam composition: 2-3 colliding trains in beam1 and 2 (without/with IR8), a few single bunches in beam 2 With full long-range, PACMAN-L/R, non-colliding Intensity: Nominal @ 1.25 x 1011 ppb Emittances: Nominal for trains i.e. 2.5 μm.rad for BCMS, some nominal single bunches and some blown up by ADT to 4-5μm Optics measurements can be done with pilot Optics: Nominal @ collision with nominal tunes, octupoles and chromaticity settings β* of 40 cm, but probably 33 cm if commissioned Y.Papaphilippou - 3/20/2017

BBLR Compensation preparation - procedure Reduce crossing angle in steps Measure impact on lifetime of different bunches, while keeping constant orbit and tune Monitor impact in emittances, luminosity, halo, losses Measure optics, e.g. beta-beating, coupling, chromaticity, tune spread, RDTs Time needed: 1.5 x 8 h, 2 x 8 h, 3 x 8 h Priority 1, 2, 3, 4 Y.Papaphilippou - 3/20/2017

BBLR Compensation goal Goal: Prove BBLR compensation with powering wire when crossing angle reduction impacts beam lifetime Leading order octupole effect compensation possible with present hardware Energy: 6.5 TeV Partial squeezed optics @ injection could be envisaged Simulation work to be done and optics commissioning overhead Beam composition A few single bunches (around 3-4) in beam 2 (weak beam) spaced by > 15x25 ns for machine protection (abort gap kicker rise time) With full long-range, 1 non-colliding As many trains in beam 1 Intensity: Nominal of 1.25 x 1011 ppb for strong (or highest possible from SPS) Emittances: Nominal for trains i.e. 2.5 μm.rad for BCMS, some nominal single bunches and some blown up by ADT to 4-5μm Small enough to guarantee that long range kick identical to 1/r field corrected by wire for all LRs Optics: Nominal @ collision Nominal @ collision with nominal tunes, octupoles and chromaticity settings β* of 40 cm, but probably 33 cm if commissioned Un-squeezed optics in IR1, only if synergy with IR compensation MD Crossing angle: Nominal in both IR1 and 5, no collisions in IR2 and 8 Moving only one IR crossing angle could be envisaged Priority 1, 2, 3, 4 Y.Papaphilippou - 3/20/2017

BBLR Compensation procedure Inject and ramp up a few bunches in beam 2 to commission orbit and tune feed-forward with wire (ideally during calibration phase) and blow-up effect of ADT Compatible with parallel tests in beam 1 Inject, ramp-up and collide strong (beam 1) and weak beam (beam 2) Set internal TCT/L jaw at 5-6σcol (including other collimation adjustments enabling this) Reduce crossing angle in steps, while keeping orbit and tune constant Observe lifetime reduction and ramp-up the current of each wire in steps, observing lifetime recovery in colliding weak beam Note that if collimator distance in mm is equal L/R from the IR, wire current should be the same, whereas if distance is equal in σ, L/R current should be adjusted independently Monitor emittance, luminosity, halo, losses Repeat the test with different weak beam flavours (Pacman-L, Pacman-R, without HO and non-colliding) Measure optics, e.g. beta-beating, coupling, chromaticity, tune spread, RDTs, with wire compensation Repeat the test with IR1 crossing angle fixed and/or separated in IR1 Repeat the test using the wires in external jaw Time needed: 3 x 8 h, 3.5 x 8 h, 4 x 8 h, 5 x 8 h Priority 1, 2, 3, 4 Y.Papaphilippou - 3/20/2017

Observables and instrumentation Priority 1, 2, 3, 4 Observables instrument Lifetime FBCT Losses (D)BLMs Halo coronograph Emittance BSRT Orbit, crossing angle BPMs, DOROS Tune, chromaticity BBQ, Schottky Tune-spread BPMs, BBQ, BTF RDTs BPMs, BBQ See presentations of B.Salvachua, G.Trad, T.Levens, R.Tomas, X.Buffat Y.Papaphilippou - 3/20/2017

Other compensation studies and spin-offs BBLR Compensation with octupoles (arc, IR) Flat optics Wires are powerful enough to be used for linear and non-linear optics studies but also collective effects Measuring tune-spread, RDT, instability studies, halo cleaning See presentation of S.Fartoukh See presentation of M.Fitterer, X.Buffat and R.Tomas Y.Papaphilippou - 3/20/2017

MD schedule and time-line Only 15 MD block days Possibility for additional days after TS2 if LHC lumi goal reached Wire MD requests 48 h for strict minimum (96 h for more complete studies) Ideally wire calibration and crossing angle scanning should profit from recommissioning time in May (~16h) Would like to profit already from the 1st MD block for most of the studies See presentation of R.Tomas Y.Papaphilippou - 3/20/2017

Outlook Devise a strict minimum commissioning and MD plan that demonstrates BBLR compensation already in 2017 Continue simulations studies for consolidate experiment Start discussing configuration for 2018 and possible optics options (injection, flat optics, etc.) still using the present H/W solution Start a reflection for the optimal configuration and hardware to put in operation for (HL-)LHC Y.Papaphilippou - 3/20/2017

Thanks for your attention Y.Papaphilippou - 3/20/2017