Richard Catherall EN-STI 2nd February 2011

Slides:



Advertisements
Similar presentations
New Radiation Safety Interlock System for the SPring-8 Accelerator Complex C. Saji, M. Toko, T. Matsushita, R. Furuta, H. Hanaki, S. Hashimoto 1), Y. Hashimoto,
Advertisements

MEDICIS : status, plans, interlocks and coactivity with ISOLDE ISOLDE ISCC 13 February 2015 Stefano Marzari EN-STI-RBS.
Technical studies for the HIE- ISOLDE Frontend upgrade Jacobo Montaño Marie Curie Fellow; CATHI Project * The research project has been supported by a.
The ISOLDE robots upgrade JL GRENARD EN-HE ISOLDE Workshop and Users meeting
Mid Term Review Meeting, 26 September 2012S. GIRON1 * The research project has been supported by a Marie Curie Early Initial Training Network Fellowship.
ECFA Preparatory Group "Shutdown constraints and radiation and activation effects”. W. Zeuner, W. Riegler, R. Lindner, B. Di Girolamo, G. Corti, C. Schaeffer,
Remote manipulations / diagnostics in radioactive areas and handling of radioactive material Workshop, Geneva, Switzerland 6 th May 2013 THE REPLACEMENT.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Radiation Protection LS1 - Collaboration with CERN Technical Groups - Lessons learnt Stephane Bally (CERN), Sandro Di Vincenzo (CERN) Indico
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
EN-STI Group meeting 1 st February 2013 EN-STI Group meeting 1 st February 2013 Interventions for LS1 Elodie Macario EN/STI.
Richard Catherall EN-STI CERN, 1 st February 2012 ISOLDE Technical Report for the INTC.
Richard Catherall EN-STI CERN, 6 th July 2011 ISOLDE Technical Report for the ISCC.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
Engineering Department ENEN What is changing in EN 1. Streamlining and boosting remote handling and manipulation activities 2. Bringing small works closer.
Highlights of RP activities in support of ISOLDE operation and projects Joachim Vollaire, Alexandre Dorsival and Christelle Saury with material from others.
Status of renewal of Buildings 115 & 507 Borge & Erwin Siesling.
Richard Catherall EN-STI 2 nd February 2011 ISCC Technical Report & Report from the Standing Group for the Upgrade of ISOLDE.
RSSO refresher meeting J. Pedersen M. Tavlet, T. Otto.
Building 867 Project TE/MPE workshop status and schedule Presented by Tony Fowler, TE-ABT on behalf of the Project Team 28/09/2010Building 867 Project:
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
Mats Lindroos ISOLDE Technical report INTC 14/2/2007 Mats Lindroos.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
2005/06/22 ALBA Building Project David Carles Engineering Services Division - CELLS.
ISOLDE Technical Report Richard Catherall ISOLDE Technical Coordinator 50 th INTC meeting 1 st July 2015.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
EUROnu Costing Workshop May 2011 Beta-Beam Costing Exercise Elena Wildner, CERN 25/05/11 1 EUROnu Costing Workshop, CERN May 2011.
Floor plans, Infrastructure & Logistics Hie-Isolde Spectrometer Workshop Physics Department, Lund University 10 March, 2011 Hie-Isolde Erwin Siesling.
Integration and Installation Status for Collaboration Meeting Ans Pardons, 29/9/2015.
Technical Report for the ISCC Meeting 18 th May 2009 R. Catherall/ M. Lindroos.
ALARA REVIEW WORKING GROUP (ARWG) New ALARA recommendations proposed by the ALARA REVIEW WORKING GROUP (ARWG) Heinz Vincke on behalf of ARWG LS1 committee.
Physics coordinator report 2015 overview 2016 schedule Safety & access B. 508 & 275 Karl Johnston.
A. Herlert, CERN PH-IS ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008 ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008.
Richard Catherall EN-STI CERN, 3 rd November 2011 ISOLDE Technical Report for the INTC.
An Integrated Remote Target Handling System for CERN’s MEDICIS Radioactive Isotope Production Facility Keith Kershaw, Stefano Marzari, Jean-Louis Grenard.
Richard Catherall EN-STI CERN, 3 rd November 2011 ISOLDE Technical Report for the ISCC.
LIEBE Target Design Review. Schedule This comment is no longer valid as the schedule has been postponed and the beam permit will be requested for Q
Status of AWAKE Installation and Integration Presented 9/3/2016 at the AWAKE Collaboration Meeting Ans Pardons, for the AWAKE CP4 team.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
A summary of the SPES Safety Technical Advisory Committee SSTAC Richard Catherall ISOLDE Technical Coordinator 5 th December 2014 INFN, Legnaro.
Electrial Safety LS2 days November 2016 AP
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
ISOLDE Technical Report for the ISCC
ICE SECTION The coolest place to be! Elias Métral
Target & Frontend Switch Yard & Collection Boxes Medicis Seminar, 2nd and 3rd March 2016 Stefano Marzari EN-STI & Vincent Barozier EN-ACE.
Technical Report for the ISCC Meeting 23rd June 2010
ISOLDE Technical Report
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
ISOLDE and n_TOF Consolidation
n_TOF “Draft” plans for YETS and LS2
Technical Report for ISOLDE
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
Renovation of the 45-year old PS magnets
Cryogenic Risk Assessment in LHC
Proton Source and LEBT Luigi Celona & Lorenzo Neri
Alexander Herlert, CERN (PH-SME-IS)
MEDICIS Facility Isotope Separator Controls and HMI
A. Herlert, CERN PH-SME-IS
ISOLDE Technical Report for the ISCC
ISOLDE Technical report for INTC 21/5/2007
Technical Report ISCC Meeting 16th February 2009
Magdalena Kowalska, CERN PH-SME-IS
Magdalena Kowalska, CERN PH-SME-IS
Technical Report for ISOLDE
Magdalena Kowalska, CERN PH-SME-IS
Technical report Mats Lindroos.
A. Herlert, CERN PH-SME-IS
The HIE-ISOLDE Design Study and the CATHI Fellow Participation
Alexander Herlert, CERN (PH-SME-IS)
Presentation transcript:

Richard Catherall EN-STI 2nd February 2011 ISCC Technical Report & Report from the Standing Group for the Upgrade of ISOLDE Richard Catherall EN-STI 2nd February 2011

Agenda Shutdown Work Safety Office Space FE#7 installation REX upgrade RILIS upgrade On-going work Safety Office Space Report from Standing Group for the Upgrade of ISOLDE

Target Removal Use of Type A transport container as requested by RP. Shutdown Work Use of Type A transport container as requested by RP. Implications to be assessed New 5 year buffer zone under construction Gives time for hot cell construction B. Crepieux

Front End #7 Front End #4 removed successfully Shutdown Work Front End #4 removed successfully Cables and insulator successfully removed New insulator in place Difficulty in assuring cable passage between FE faraday cage and separator area. Phases 1 → 80% of provisional collective dose Phase 2 →~60% PCD S. Marzari, T. Giles, T. Stora, E. Barbero, M. Owen

REX Upgrade Shutdown Work REXTRAP Controls         1. Dismantling of the old system (FINISHED)         2. Electronics racks cleared (FINISHED)         3. Hardware installation (ONGOING)         4. Local validation of PLC and power supplies (TO BE DONE during February)         5. FESA validation (ONGOING) Applications Timing editor application  (ONGOING) Electrode graph display   (FINISHED…to be tested when all the hardware will be in place)     Time of Flight application  (FINISHED)  Scanning application  (TO BE DONE during February) RF editor application  (TO BE DONE during February) REX Vacuum Controls Cables removed Cabling divided between TE-VSC and EN-EL as a function of priorities EBIS TRAP SEPARATOR E. Piselli, J. Sanchez, F. Wenander, S. Blanchard

RILIS Shutdown Work B. Marsh, S. Roth, D. Fink & V. Fedosseev Move the dye laser system to the new tables to make space for the new Ti:Sa lasers and move the pump laser chiller to the roof of the cabin. Install the Ti:Sa laser system (Nd:YAG pump laser and 2 or 3 Ti:Sa lasers, plus multiple harmonic generation units). Redesign the HRS launch mirror system to include a 4th path for ISCOOL pumping. Install the laser path for ISCOOL pumping in the HRS separator zone. Optimize the little remaining space in the RILIS cabin remove the electronics racks and desks and replace with a new compact workbench and shelving area. Install a frame, laminar flowbox and safety shielding around the Ti:Sa section of the RILIS table. LIST Tests on-going at off-line separator Tl ions have been extracted Preparations for installation on FE#7 on-going B. Marsh, S. Roth, D. Fink & V. Fedosseev

On-going Shutdown Work Pico-ampere meters for Faraday cups Cabling and hardware installation on-going Waiting for software installation Redundancy in tunnel fire detection implemented Cause of “false” fire alarm in 2010 Tesla meters for the HRS magnets to be moved externally. Complete renovation of ISOLDE timing New distribution hardware this shutdown Timing signal cards to be addressed next shutdown General maintenance HT, vacuum, controls, robots,FE#6, beam instrumentation, power supplies, magnets E, Siesling, G. J. Focker, D. Raffourt, P. Fernier, T. Giles

Safety ALARA Level 3 Visits Traceability Most interventions in the shielded areas of ISOLDE are classed as level 3 ALARA with respect to the present criteria. The contamination criteria is the main reason for so many level 3 ALARA committees 9/14 level 3 over last year. 5 ALARA level 3 interventions addressed in the last 2 months Protocol still unclear 4/5 interventions have been “accepted” by S. Myers – derogation High impact on resources and planning Visits New rules for visits to controlled radiation areas…to be announced Traceability Investigating possible use of Timber database (used by LHC) to monitor machine operation and RIB distribution. A-P Bernardes, E. Macario

Office space – under discussion Removal of Class C lab in 275 Requested by RP and makes efficient use of B. 275 Initial discussions and plans under way to extend B115 Displace all ISOLDE personnel and labs to Bs 570 and 275? Nearer to ISOLDE More office space? Remove B507 (light building) and build anew Include DAQ rooms (outside Class C perimeter) Visitor Centre? (outside Class C perimeter) Machine workshop Kitchen? (outside Class C perimeter) Cost estimate under preparation Possibility to use offices in B54?

Office Space

Office Space Building 570

Synthesis Out of 25 offices owned, 20 offices used by PH Office Space Out of 25 offices owned, 20 offices used by PH 360 m2 → ~260 m2 used EN owns 3 offices and borrows 5 from PH 50 m2 → 150m2 used Number of offices available in B.570 – 15 277m2 Number of offices available in B.275 – 6 111m2 Modifications to B570 will be required to increase surface area. Total of 28 offices 410m2 office space Total of 21 offices 388m2 office space

SGUI - Introduction New members Mandate Report from SGUI New members Magdalena Kowalska replacing Alex Herlert as ISOLDE Physics Coordinator Joachim Vollaire representing Radiation Protection and RP issues for new projects Klaus Hanke as Booster operations supervisor. Mandate To address the short-term upgrades of the ISOLDE Facility excluding the HIE-ISOLDE project and to set priorities for future beam development. The frequency of the meeting shall be twice per year. The next meeting will take place on the 7th July 2011

Developments in 2010 Report from SGUI The successful production of 140Nd using RILIS. Nd beams can now be made available for physics. However, tests for the production of Sm beams are on-going. The production of 12Be using thin foils. The priority of this development was changed to 11Be in order to provide beam to IS430. The High Density Uranium Carbide (HDUC) from Russia is currently being tested on-line The LIST ion source at the off-line separator currently being tested. Courtesy of T. Stora

New priorities The development of 30Na beams Report from SGUI The development of 30Na beams The successful production of 72Kr The production of 8B beams. 6 LoI’s have been presented in the recent INTC meeting. Completion of the 142Sm beam development The following points were also retained The development of 9C beams should continue the experiment should not be scheduled until tests have been validated on- line. Better characterize the potential of VADIS/target combinations for the planning of future experiments. Sufficient time should be made available for testing

Production of long-lived beams. Report from SGUI Consequences when opening the machine to atmosphere for intervention. In collaboration with RP, procedures will be drafted and preparations made for the opening of the REX machine taking into account the worst possible scenario. If the procedures proposed by RP are accepted and followed, and the level of activity remains low, physics with long-lived radioactive beams may be done at REX. The INTC will be provided with information from RP and the Technical Advisory Committee describing the consequences for machine maintenance and chamber openings in case long-lived radioactive beams are accepted. Limited consequences for the opening of REX (3 times per year ) MINIBALL will be most affected should the intervention times be long. Test at the end of 2011 by implanting beams into MINIBALL and characterizing the risks when opening the chamber. F. Wenander, J. Vollaire

Target Area Upgrade (New robot) Report from SGUI There will be one system for both separators The robot arm will be mounted on an autonomously guided vehicle (AGV) The system will be stored externally to the target area There will be an independent back-up in the case of failure Emphasis on the inherent and operational safety file Installation is for 2013 K. Kershaw, J. L. Grenard, B. Feral