Kings Bluff Raw Water System Parallel Raw Water Main Project Pender County Board of Commissioners Retreat March 9, 2017
Kings Bluff System Map
Kings Bluff System Phased Improvements Phase I – Kings Bluff raw water pump station expansion - 2009 Phase II – 60-Inch parallel intake construction - 2010 Phase III – 14-Mile Parallel Raw Water Transmission Main – Next Phase
Recent Raw Water Main Failure Pipe Failure Temporary Bypass Pipe Raw Water Main Pipe Failure Repair Efforts
Pender County Water Plant September 2006 - Pender purchases 6 MGD raw water supply from LCFWSA 2012 – Pender County Water Treatment Facility is Completed Pender WTP permitted at 2 MGD but readily expandable to 6 MGD
Pender Inter-Basin Transfer 2015- Pender begins IBT process IBT requests 14.5 MGD Source water is the Cape Fear River via LCFWSA EMC approval was anticipated for 2017 Raw Water Intake Cape Fear River Raw Water Pump Station Lock & Dam No. 1
Parallel Raw Water Transmission Main Projected Allocations Customer Allocation (MGD) CFPUA 43 Brunswick County 38 Pender County 6 LCFWSA 2 Total Allocation 89
Capacity Vs. Allocation Three pipe diameters currently considered * 48-inch * 54-inch * 60-inch Diameter Capacity (MGD) Allocations (MGD) Difference (MGD) 48-inch 87 89 (-2) 54-inch 94 5 60-inch 106/96 17/7 *Note capacities are “total system capacity” in conjunction with existing 48-inch transmission main *Maximum withdrawal from Cape Fear River 106 MGD with 10 MGD accommodated via the CFPUA raw water pump station
Initial Design Cost Estimate Estimated Allocation (MGD) Pender Current Allocation 6 MGD Pender County IBT 14.5 MGD Additional Allocation (IBT) 8.5 MGD Current System Capacity 48 MGD Projected Capacity (60-inch) 96 MGD** Additional Capacity Gained Pender % of Additional Capacity 17.7% Estimated Design Cost $1.7M Estimated Pender Share of Design $0.30M **Maximum withdrawal from Cape Fear River 106 MGD with 10 MGD accommodated via the CFPUA raw water pump station
Potential Construction Estimate Item Amount Estimated Construction Cost $66M Pender % of Additional Capacity 17.7% Estimated Pender Share of Construction $11.7M
Design Schedule Request for Qualifications - March 2017 Selection of Engineering Consultant – April 2017 Execute Design Contract – July 1, 2017