Forsyth County 2016 Bond Referendum Forsyth Technical Community College Capital Projects
Oak Grove Project Complete Main Campus renovation Site demolition – Piedmont, Parkway, Winston, Salem, Carolina Annex Buildings Site development – Grading, irrigation, landscaping, paving curbs, walks, amphitheater Construction – utilities, Tech Drive and parking lot improvements, maintenance storage building Equipment – Campus Police, IT infrastructure
Oak Grove Project $21 million Renovate unfinished space in the Oak Grove Center – 83,000 sq. ft. Program facilities – 3-D printing center, mechanical engineering technology, fine arts, culinary arts and hospitality facilities; Conference Center breakout rooms; classrooms, labs, and offices Academic Support facilities – testing center, tutoring, computerized individualized instruction $21 million
Aviation Center $16.6 million Purchase/renovate or build office and hangar space (100,000 sq. ft.) on or contiguous to Smith Reynolds Airport property Provide program facilities -- classroom, shop, and laboratory space – for technology education and training serving aviation/aerospace manufacturing and service industries (including FAA certified training) $16.6 million
Transportation Center Expansion Construct 30,000 sq. ft. facility at the Transportation Technology Center (Patterson St. and Germanton Rd.) Shop, laboratory, classroom and office space to support growth of automotive technology, motorcycle service, and race car technology $6.4 million
Learning Commons $21 million Construct 70,000 sq. ft. facility on the Main Campus Replace current library Student meeting rooms, study space, technology-rich design, expanded stacks and holdings, and faculty and community learning commons $21 million
Summary of 2016 Bond Projects Oak Grove Center Project $21,000.000 Aviation Facility $16,600,000 Transportation Center addition $ 6,400,000 Learning Commons $21,000.000 Total bond funds $65,000,000
Forsyth County Bonds: Forsyth Tech Schedule FY17 $16,250.00
Timeline for Projects Oak Grove Center Project $21,000.000 projected construction start date March, 2018 projected completion date September, 2019 Aviation Center $16,600,000 projected construction start date August, 2018 projected completion date January, 2020 Learning Commons $21,000,000 projected construction start date October, 2020 projected completion date March, 2022 Transportation Center Addition $6,400,000 projected construction start date March, 2022 projected completion date September, 2023
Forsyth County Bond Tracker Contact Information Ken Jarvis Manager of Facilities Forsyth Technical Community College Phone: (336) 734-7209 Email: kjarvis@forsythtech.edu Website: forsythtech.edu Forsyth County Bond Tracker Located on the Forsyth County home page under Bond Tracker