Introduction BaBar Components The Problem IFR Upgrade: 2004 & 2005

Slides:



Advertisements
Similar presentations
October 21, 2003LST Mechanical Design Review - SLACN. Yu BaBar IFR Upgrades An FEA Study of the Effects of Adding Brass Plates in the IFR.
Advertisements

10/21/03H.J. Krebs1 LST Mechanical Design Review Brass Absorber Design H.J. Krebs October 21, 2003.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2005 IR-2 Installation Discussion H.J. Krebs October 22, 2003.
BaBar: The Detector Richard F Boyce 21 October 2003.
May 5, 2004H.J. Krebs LST Installation Readiness Review 2004 IR-2 Installation Schedule H.J. Krebs May 5, 2004.
March 23, 2009H.J. Krebs1 BaBar D&D Schedule & Budget Overview H. James Krebs March 23, 2009.
May 4, 2004Bill Wisniewski1 Installation Review. May 4, 2004Bill Wisniewski2 Charge ( W. Althouse, G. Bowden, W. Innes(chair), J.Weisend, (D. Nelson))
October 22, 2003H.J. Krebs1 LST Mechanical Design Review Mechanical Installation Preparation H. James Krebs October 21, 2003.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2004 IR-2 Installation Schedule H.J. Krebs October 22, 2003.
Vertex Detector Mechanics Bill Cooper Fermilab VXD.
IFR End Door Enhancement Mechanical Engineering Status & Installation Issues H. James Krebs June 23, 2001.
October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and Fabrication Status H.J. Krebs October 10, 2003.
Joint Institute for Nuclear Research Further optimization of the solenoid design A.Efremov, E.Koshurnikov, Yu.Lobanov, A.Makarov, A.Vodopianov GSI, Darmstadt,
1 ILD/CMS Engineering Meeting M. Joré – ILD integration philosophy Integration philosophy of ILD Matthieu Joré – January 21st Integration of the subdetectors.
Experimental hall in Japanese mountain site Y. Sugimoto 1.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
Hcal Geometry and Assembly CLIC Meeting - LAPP December 2008, 15th.
Page 1 BaBar IFR Mechanical, Schedule Cost Review Outbriefing (1) Excellent job on preparing and presenting review Overall, the Committee feels that the.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
LST Upgrade LST Upgrade Readiness Review William Sands, Princeton University,
11/15/02H.J. Krebs IFR Improvement Phase II (Barrel) Mechanical Engineering Issues H. James Krebs November 15, 2002.
November 15, 2003Bill Wisniewski1 Introduction Brief Status of LST project QA Review Mechanical, Schedule and Cost Review.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Tsukuba-hall webcam 1 Beam Pipe and Vertex Detector extraction: on Nov. 10, 2010 Belle Detector Roll-out: Dec. 9, 2010 End-caps, CDC, B-ACC, TOF extraction:
Laura Ingalls Huntley Office of Science, SULI Program Franklin & Marshall College Stanford Linear Accelerator Center Menlo Park, California 16 August 2006.
9 September 2004The Straw Tube Chamber1 The CDC Curtis A. Meyer Carnegie Mellon University Physics Requirements and Specifications Prototype Construction.
E.Guschin (INR) 21 November 2003Integration EDR PRS/SPD static envelop, assembly and installation Detector layout Static envelop along the beam Detector.
Luca Lista Object Oriented Reconstruction Software for the IFR Detector of B A B AR Experiment Luca Lista INFN, Sezione di Napoli for the BaBar Computing.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
The BaBar Upgrade Load transfer of the Barrel and Endcap Calorimeters Richard F Boyce 21 October 2003.
September 20, 2007H. J. Krebs/B. Wands/B. Cooper1 SiD Collaboration Preliminary End Door Design Concept Support of Forward Systems H. James Krebs Bob Wands.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
LARP Review, June 12-14, 2006 Prebys, Todesco, Zisman 1 Accelerator Systems Eric Prebys Ezio Todesco Mike Zisman.
May 31, 2010Bill Wisniewski1 Mechanical Integration Issues.
Integration Prototype1 BaBar Integration as a Prototype for SuperB Bill Wisniewski SuperB Workshop at LNF 6 April 2011.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
Comments on Services Elba Comments on Services & … Bill Wisniewski SLAC.
October 6, 2009Bill Wisniewski1 State of drawings Remedies? Forward Region DIRC/DCH/EMC interplay Road Trip Discussion Beam pipe & forward cone plug ‘Quick’
01 June 2011F. Raffaelli1 Super B Mechanical integration. List of reference persons and institutions for the mechanic of the sub detectors. Review of the.
Operation, performance and upgrade of the CMS Resistive Plate Chamber system at LHC Marcello Abbrescia Physics Department - University of Bari & INFN,
Straw man layout for ATLAS ID for SLHC
Roberto Calabrese Ferrara University and INFN
Next steps toward the beam test
IOP HEPP Conference Upgrading the CMS Tracker for SLHC Mark Pesaresi Imperial College, London.
IBL Overview Darren Leung ~ 8/15/2013 ~ UW B305.
BaBar LST Upgrade Mark Convery SLAC 13 Jun 07.
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
PANDA Yoke of the Magnet
SiD Calorimeter R&D Collaboration
PANDA Collaboration Meeting , BINP Sergey Pivovarov.
Bill Wisniewski SuperB Frascati Meeting September 30, 2010
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Integration issues Denis Diyakov, Alexander Seletskiy,
IFR detector mechanics
Pierre-Alexandre Thonet
The Compact Muon Solenoid Detector
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
Integration and IR Hall
LST Module Installation
Limited Streamer Tubes
RPC and LST at High Luminosity
DET. Integration Inner detector envelope Radial clearances.
ILC Detector Technology
L H C A T L A S International Collaboration on the LHC Project
SuperB Integration Summary of previous integration sessions.
Inner DET. Integration Inner detector envelope Radial clearances.
Limited Streamer Tube Project Summary
General Introduction to IFR
as a prototype for Super c-tau factory
BaBar LST Upgrade Richard F Boyce
Presentation transcript:

Introduction BaBar Components The Problem IFR Upgrade: 2004 & 2005 Charge to the Committee October 21, 2003 Bill Wisniewski

BaBar Detector October 21, 2003 Bill Wisniewski

Quarter Section of BaBar Barrel Endcap October 21, 2003 Bill Wisniewski

Barrel IFR RPC Problem October 21, 2003 Bill Wisniewski

IFR Barrel Upgrade Mechanics Blocks of steel limit access to IFR slots. Removal of this steel makes replacement of the RPCs with LSTs a complicated, difficult upgrade. Doors and beam line components also restrict access. October 21, 2003 Bill Wisniewski

IFR Barrel Timeline Philosophy for installation: Install fully tested and burned-in LSTs Minimize the impact on the data taking schedule In order to minimize schedule impact, take advantage of summer down periods required by budget and the machine improvement program. In order to maximize the physics benefits of the upgrade, install as soon as the LSTs are properly Q/A’d. October 21, 2003 Bill Wisniewski

LST design Graphite- Coated PVC single-layer large cell (15x17 mm) October 21, 2003 Bill Wisniewski

IFR Barrel Timeline: 2004 Replace 2 sextants. Aim to complete the work on a sextant: load LSTs and brass. Start with the top and bottom sextants. These have very few services crossing them: they are the best place to discover ‘gotchas’ in the installation process. October 21, 2003 Bill Wisniewski

IFR Barrel & SVT Timeline: 2005 Replace 4 IFR sextants. These will be diagonal sextants. The doors complicate access. Another complication is transfer of the calorimeter load. At the end of Run 5 (summer 2005) the horizontal elements of the inner layers of SVT are projected to have received about 5MRad dose. Replace these. The support tube must be removed for SVT work. This provides an opportunity for machine component upgrades that would allow continued increase in luminosity. October 21, 2003 Bill Wisniewski

BaBar Barrel IFR Upgrade Mechanical, Schedule and Cost Review Charge BaBar Barrel IFR Upgrade Mechanical, Schedule and Cost Review Charge to the Committee (W. Althouse, G. Bowden, G. Deis (chair), F. Raffaelli, J. Weisend) The BaBar Instrumented Flux Return (IFR) system consists of the return yoke of the superconducting solenoid magnet along with instrumentation used to detect the passage of particles (μ’s, π’s and long-lived neutral kaons). The steel is arrayed in sextants consisting of 18 layers of steel with thickness increasing radially outward. Resistive Plate Chambers (RPCs) constitute the sensors located in the slots between the steel layers. The performance of the RPCs has been decaying since the start of the experiment. The performance in the barrel has now decreased sufficiently that the sensor elements must be replaced. The problems that have been found with the ‘monolithic’ RPCs have led BaBar to choose a better understood and more robust sensor technology, Limited Streamer Tubes (LSTs), to replace them. It is expected that this more modular technology will last reliably through the balance of the decade. The barrel RPC system has 19 layers of sensor. The outermost of these layers can not be accessed. In order to more than compensate for the loss of the last layer of steel absorber, six of the gaps between the steel plates will be filled with brass. October 21, 2003 Bill Wisniewski

Charge (cont’d) Access to the RPCs is limited by the array of steel that covers the ends of the barrel and provides a connection path from the barrel to the endcap for the magnetic field. In order to remove the RPCs, these parts of the barrel structure which have been in place since the construction of the experiment will need to be removed. Engineering studies have been conducted to understand the stability of the barrel structure under the increased load from the brass while the structure is partially disassembled. Four of eight magnet vessel restraints will be disconnected during the first phase of the installation, when the top and bottom sextants will be upgraded. The four supports for the barrel calorimeter are attached to the steel corner blocks. Two of these blocks will be removed during the second phase of the upgrade, requiring a transfer of the calorimeter load. Please evaluate the adequacy of the engineering studies performed thus far. Are they moving in the right direction in cases where they are not yet complete? Can we put the detector together again? Tooling and platforms will be needed for removal and restoration of the steel, for insertion of the brass absorber, and for the installation of the LSTs. Please comment on the status of the design of these items, as well as mechanical design of the LST modules. The sensor elements will require services: gas, readout cables, high voltage system. Is the plan for integration of these services on the BaBar detector adequate? Are safety considerations receiving sufficient attention? October 21, 2003 Bill Wisniewski

Charge (cont’d) The installation of the LSTs, brass and services is expected to be a complicated task. Installation plans have been developed. Manpower estimates have been made based on schedules which aim to minimize downtime, since BaBar is engaged in competition with another experiment. The schedule for summer 2004, when the first phase of installation will occur, is driven by the desire to match as closely as possible the normal two month machine shutdown. In 2005 the second phase of barrel upgrade will take place, as well as repairs to the Silicon Vertex Detector and upgrade of beam line elements also contained with it in the support tube. Due to the complexity of this multi-system upgrade, it is expected that it will take significantly longer. The 2005 schedule is less mature than that of 2004. Please comment on the installation plan. Does the manpower estimated appear adequate? Is there enough float in the 2004 schedule, or is it a very success oriented schedule? Is the time estimated to be needed in 2005 adequate? Finally, please consider the cost estimates and WBS for this upgrade. Please comment on their maturity and adequacy. Please provide your preliminary feedback via a closeout session on the afternoon of the second day of this review, with a written report to follow. October 21, 2003 Bill Wisniewski