Electric Utility Master Plan Update

Slides:



Advertisements
Similar presentations
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Advertisements

Regional Planning Group Project
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
TERRACE TO KITIMAT TRANSMISSION PROJECT UPDATE Feb/March 2015.
Eau Claire Area Study Northern MAPP Subregional Planning Group January 11, 2007 Daniel Kline.
Nelson Hydro Downtown Conversion July 26, 2010 Project Overview.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Oncor Electric Delivery Company LLC TOGETHER WE DELIVER ODESSA UPDATE Jan 22, 2013 Presentation to ERCOT Regional Planning Group Austin, TX Mike Juricek.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
Midwest Energy, Inc. Transmission Planning and Expansion
Customer Meeting April 28, 2010 Torrington, WY. Agenda Introductions Accomplishments Update on Torrington Area PVVC Overview PVVC Schedule and Cost Estimates.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM 1 Presented by Ed Briggs, P.E. Manager of Electric Distribution Planning.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com Challenges and Solutions for Large-Scale PV Integration on RPU’s Distribution.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
1 Green River Utah Area Transmission and Distribution System – January 16, 2009.
Jan 13, 2012 RPG Meeting El Campo – Vanderbilt 69 kV Project – Status report Ehsan Ur Rehman Planning Engineer ERCOT.
CITY OF LAKE WORTH, FLORIDA UTILITIES DEPARTMENT A Look at our Electric Utility A Plan For The Future.
Power Plant Construction and QA/QC Section 7.4 – Hydroelectric Generators, Transformers and Controls Engineering Technology Division.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
Subtransmission Reliability Criteria
Rocky Mountain Power Sub Transmission Five Year Study Findings and Kick Off Attachment K Meeting September 10, 2015.
1 The following are the planned transmission project at SCL for the next ten year. All the projects has no major impact to the bulk transmission system.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
Tacoma Power’s Compaq Server and Ethernet RTU Performance Testing Presented By Joe Orth 253/ EMS Group Meeting Presented.
Lyndonville Electric Department Feasibility Analysis Review December 2,
Rocky Mountain Power Five Year Study Findings and Kick Off Meeting December 2013.
Aug 17, 2012 RPG Meeting KEC & MEC – Load Addition Project – ERCOT Independent Review Ehsan Ur Rehman Planning Engineer ERCOT.
Distribution Planning Use of SMART Distribution Automation Control System (DACS) Presented by: Ed Briggs, P.E. Created by: Ed Briggs & Greg Wickliffe
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Utility Engineers, PC.  Generation  Transmission  Distribution.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
Yellowhead Area Transmission System Development
Electric Utility Infrastructure Commission Staff Workshop January 23, 2006.
EECE 887 Distribution System Engineering CHAPTER 1 Power Delivery Systems.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
Jesus A. Guerra, P.E. Distribution System Reliability CenterPoint Energy SWEDE 2011.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
Transmission Capital Project Updates. Transmission Expansion Plan Sigurd to Red Butte 345 kV line in-service May, 2015 Permitting activities continue.
© 2000 PACIFICORP | PAGE 1 SOUTHWEST UTAH AREA STUDY SEPTEMBER 2014 Nathan Wilson/Talmage Daley Need to review the LOADS before Friday.
2006 Hurricane Preparedness June 5, 2006 Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
© 2000 PACIFICORP | PAGE 1 –Main Transmission Sources  kV Transformers. Terminal, Mid Valley, 90 th South and Oquirrh –Generation: Gadsby (~350.
Tampaelectric.com Presented to the Florida Public Service Commission May 1, 2008 Tampa Electric Company 2008 Hurricane Season Preparation Regan Haines.
Jeff Billo Manager, Transmission Planning
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
Douglas Bowman, PE, PMP Project Manager Entergy Corporation New Projects and Processes Ensure Power Transfer for Northeast Arkansas Customers.
LINE 69H REBUILD AND CONVERSION PROJECT ERCOT Regional Planning Group April 21,2016.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Austin Energy Elevated Requests for High Reliability Service South West Electric Distribution Exchange (SWEDE) May 8, 2015 David Tomczyszyn, P.E. – Distribution.
Pasadena Water and Power Final Projects for Completion of Underground Utility Program City Council March 14, 2016 Item 16.
Freeport Area Master Plan Project
Project Costs 2016 Transmission & Distribution Benchmarking
JEA’s Initiatives and Capital Improvements Program
Progress Briefing - Energy Initiative
2016 RTP Update November, 2016 RPG Meeting.
Barrilla Junction Area Transmission Improvements Project
Local Area Planning Update to TRANSAC – December 21, 2016
Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
Director, Transmission Services
Warren Lasher Manager, Long-Term Planning and Policy
Local Area Planning Update to TRANSAC – June 29, 2017
City of Lebanon, Missouri Electric Department
Electrical Distribution System Basics
Key Biscayne Substation
Presentation transcript:

Electric Utility Master Plan Update Utilities Commission , City of New Smyrna Beach, Florida Electric Utility Master Plan Update March 20, 2017 Contact Info Ed Wisser, Project Manager 3970 Hendricks Avenue Jacksonville, Fla. 904/398-8636 ed@fwilson.com

Electric Utility Master Plan Scope It is prudent utility practice for a utility system to be reviewed periodically for performance The task included: Analysis over a 10-year planning period Normal Loading conditions Single Contingency conditions

Electric Utility Master Plan Scope The task recognized: System configuration changes and improvements Shifts in load growth patterns The task analyzed: Present load level Two future load levels

Overview / Historical Load System: Three substations- Airport, Field Street, Smyrna Five power transformers Firm emergency rating 120 MVA Historical Load: 88 MW in 2006 to 101 MW in 2016 400 million kWh in 2006 to 441 million kWh in 2016 Relatively flat 2006 through 2014

Transformers and Feeders: Load Projections System: Forecast 1 (lower) 1.0% Growth to 105 MW in 2025 Forecast 2 (higher) 3.0% Growth to 128 MW in 2025 Transformers and Feeders: Forecast 1- 2.6% for Smyrna, 0.53% for Airport and Field St Forecast 2- 6.3% for Smyrna, 2.1% for Airport and Field St

Analysis – Normal Loading with Growth Loads above 100%: 2015- no issues 2025 Forecast 1- 2025 Forecast 2- Airport Sub transformer (Project 5.4.1) Smyrna Sub transformer (Project 5.3.1) Field Street Line 25 (Project 5.4.3) Smyrna Line 12 (Project 5.4.4)

Analysis – Single Contingency Feeder Contingency Loads above 100%: Airport Line 16 (Project 5.4.2) Field Street Line 7 (Project 5.5.5) Field Street Line 26 (Project 5.5.2) Airport Line 17 (Project 5.5.1) Smyrna Line 11 (Project 5.5.4) T-Line and Transformer Contingencies Smyrna to Field St circuit (Project 5.2.1 and 5.2.2) Smyrna Sub transformer (Project 5.3.1)

Recommendations / Program of Improvements Identified by Timing: Short-Term (< 5 years) Medium-Term (5 to 10 years) Long-Term (10 years +) Identified by Type and Priority: Growth-driven project Capital project Combination Growth / Capital project Priorities 1, 2, 3 within each Type

Recommendations / Program of Improvements T-Line Contingency Recommended Option: Tap the Airport 115 kV circuit, construct second pole line into Field Street, approx 2.4 miles (Project 5.2.1, $2.00M, 100% Capital) Expand 115 kV portion of Field Street Sub for new line terminal (Project 5.2.2, $891k, 100% Capital) Smyrna Add Capacity Recommended Option: Procure two new substation power transformers and five new distribution feeder circuit breakers Expand and reconfigure distribution portion of Smyrna Sub (Project 5.3.1, $3.88M, 75% Growth 25% Capital)

Recommendations / Program of Improvements Four Short-Term Priority 1 (High) Distribution Projects Five Short-Term Priority 2 (Medium) Distribution Projects Four Medium-Term Distribution Projects Five Long-Term Distribution Projects

Recommendations / Program of Improvements Growth Projects Project ID Load Level Priority Project Description Budgetary Cost 5.4.4 Short-Term Priority 1 Smyrna Line 12 Split and Serve From New Transformer $276,500

Recommendations / Program of Improvements Capital Projects Project ID Load Level Priority Project Description Budgetary Cost 5.2.1 Short-Term Priority 2 Second 115 kV Transmission Tie to Field Street Option 3 $1,998,000 5.2.2 Field Street Sub Additions for Second 115 kV T-Line $891,000 5.4.1 Priority 1 Airport Line 16 Transfer Load to Field Street Line 4 < $10,000 5.4.2 Airport Line 16 Rebuild #1/0 CU Dixie Hwy $135,000 5.4.3 Field Street Line 25 Transfer Load to Line 3 $21,000 5.7.2 Long-Term Field Street Line 25 Rebuild Along Saxon Dr $238,400 5.7.3 Airport Line 16 Rebuild #4/0 CU Dixie Hwy $315,300 5.7.4 Airport Line 17 Replace UG along Sunset Dr $522,100 5.7.5 Smyrna Line 11 Rebuild Along SR-44 East of I-95 $383,100

Recommendations / Program of Improvements Combination Projects Project ID Load Level Priority Project Description Budgetary Cost 5.3.1 Short-Term Priority 1 Smyrna Sub Add Transformer Capacity Option 2 $3,883,000 5.5.1 Priority 2 Airport Line 17 Rebuild with 652 AAAC $641,000 5.5.2 Field Street Line 26 Rebuild Along Findley and Old Mission $472,400 5.5.3 Airport Line 15 and Smyrna Line 12 Rebuild Along Pioneer Trail $174,300 5.5.4 Smyrna Line 11 Rebuild Along SR-44 West of I-95 $46,700 5.5.5 Field Street Line 7 Rebuild Along Canal and Milford $162,500 5.6.1 Medium-Term Priority 3 Field Street Line 7 Rebuild Along Mary Avenue $137,300 5.6.2 Field Street Line 4 Rebuild Along Julia Street $122,900 5.6.3 Field Street Line 4 Replace UG Along Dixie Hwy $485,500 5.6.4 Airport Line 15 Rebuild along Wayne Ave $156,200 5.7.1 Long-Term Schoolway Line 14 Convert Load to 23 kV $30,000

Recommendations / Program of Improvements SUMMARY   Growth Capital Total Short-Term Projects Priority 1 $3,188,750 $1,136,750 $4,325,500 Short-Term Projects Priority 2 $748,450 $3,637,450 $4,385,900 Medium-Term Projects $450,950 $901,900 Long-Term Projects $15,000 $1,473,900 $1,488,900 $4,403,150 $6,699,050 $11,102,200

Electric Utility Master Plan Update Questions?