UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS

Slides:



Advertisements
Similar presentations
Update on FCPS Construction/Renovation Projects July 2009.
Advertisements

Update on FCPS Construction/Renovation Projects September 2009.
Confidential. ©ARXX Corporation 2010 Insulating Concrete Forms.
With the passage of the May 2009 NLISD Bond Election, campuses made improvements and repairs. New flooring in the elementary schools, updated kitchen.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Current Project Update October 25th 2012 Good Evening!!!
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Rebuild Stafford High School Update- October 2014.
IWTP Facility. Holes Drilled for Detailed Blast Drilling and Blasting for final grade prior to construction in 2011.
October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Foundation Systems.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
7 Set of Floor Plans Primary Considerations
Bar joist over kitchen and band room. Setting bar joist over kitchen and electrical/mechanical rooms.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Architectural Design Construction of a Wall Section Upon completion of this assignment, you will be able to accurately and neatly draw, to scale and limits,
© OnCourse Learning. All Rights Reserved. Basic House Construction Learning Objectives  List the primary styles of residential architecture  Describe.
ALMA PIERCE ELEMENTARY SCHOOL Presented by: Frank Architects Inc. JUNE 26, 2002 DESIGN DEVELOPMENT PHASE.
Reading Structural Drawings
ADDITION & REMODEL Eugene Field Elementary School.
Foundation Plan Layout
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Light Wood Frame Construction
Building Plans.
Facilities Modernization Program Funded by Measure B Project Report November 21, 2011.
First Baptist Church of Doylestown Senior Thesis Structural Emphasis James Chester Preliminary Phase II Design.
F ACILITIES, P LANNING, AND C ONSTRUCTION April 14, 2014 Construction Report.
Foundation Systems Unit 11. Types of Foundations Pilings Continuous Grade Beam.
Fundamentals of Structural Detailing
Project Status The project is progressing well with both grading aspects and building components. The mason has erected many walls to “scaffold high”
North Augusta High School Design Development Presentation.
Orthographic Drawings
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
F ACILITIES, P LANNING, AND C ONSTRUCTION December 14, 2015 – Monthly Construction Report.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Elevating the Quality of Life in the District. AFTER RENOVATION BEFORE RENOVATION.
Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Construction Foundations of Technology Construction © 2013 International Technology and Engineering Educators Association STEM  Center for Teaching and.
WEST DES MOINES LIBRARY ADDITION Team North Final Presentation Team North The Ace Mentor Program career direction for students in architecture,
Floor Systems and Foundation Support
Building Committee Presentation March 03, MAIN ENTRANCE.
TRIGON, INC ARDMORE CITY SCHOOLS 2013 BOND ISSUE PROJECTS.
MICROSOFT PROJECT MODULE 2 - BUILD A HOUSE.
Bond Oversight Committee
APPLICATIONS OF TECHNOLOGY
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Upcoming Activities Fun Fact Click here to view the live WEBCAM
Construction Documents
Goding Elementary Existing Conditions Presentation February 13, 2013.
Council Rock High School South
G R E A T L A K E S B U I L D E R S A Re-construction Company Specializing in Structural Remediation and Alterations.
Organics Waste Processing Facility Construction Progress Update December 15, 2010
Minuteman Vocational Technical Regional High School Progress
Course Contents Culverts Bridges Buildings 20 November 2018.
Progress Report 11/10/11.
FACILITIES, PLANNING, AND CONSTRUCTION
Minuteman Vocational Technical Regional High School Progress
2007 Bond Issue Capital Improvement Program
Value of contract: Length of contract: Contract start date:
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
North Augusta High School – Phase 2A and 2B
EAST PENNSBORO AREA SCHOOL DISTRICT
Presentation transcript:

UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS Business Operations and Facilities Meeting September 22, 2016

Building Area A – South Classroom wing closest to Doe Run Road Area B – Administration Suite, Main vestibule Area C - Gymnasium, Cafeteria, Kitchen Area D – North Classroom Wing

Area A - South Classroom wing closest to Doe Run Road All concrete slabs are poured. Structural Steel framing and decking is complete. Roofing started 9/20/2016 First floor CMU (Masonry) is complete. Second floor CMU starting . First Floor mechanical ,plumbing and electrical components are  being installed. Second floor MPE components to start in a week. Area A – Classrooms 1st floor Area A – South Elevation Area A – North Elevation Through Gymnasium Area A – Looking down corridor of north wing

Area B – Administration Suite, Main vestibule Footings are 100 % complete. Concrete SOG (Slab on Grade) is 100% complete. Structural Steel is presently being fabricated. Steel erection may be the last of the areas (A,B,C &D) to be done. Area B – Future administrative area. Area B – Main entrance looking at stage, cafeteria area. Area B – Future administrative and nursing area.

Area C - Gymnasium, Cafeteria, Kitchen Footings are 100%  complete. Piers and anchor bolts are 100% complete. SOG may happen in next two weeks. Structural steel is erected for the Gym, decking and detail work to  follow. Basement Concrete Walls are complete and backfilled. Structural Steel over Basement has started and is 70% complete. Boilers and Main pumps are being installed in the Basement. CMU Foundations to finished first floor are 95% and should be completed in a week. Area C – Gymnasium looking at Stage area Area C – Serving and Kitchen area. Area C – Cafeteria seating area. Stage to left.

Area D – North Classroom Wing Footings and Foundations are 100% complete. Interior Footings and Piers are 100% complete. Underground plumbing is 95% Complete. Underground Electrical is 98 % Complete. Prep. For SOG concrete will start within this week. SOG pour may happen in the next two weeks. Structural Steel will follow in a week and a half or two weeks.

The builder and contractors are working quickly! Area A Taken on 7/7/2016 Taken today, 9/22/2016 Area C