VENTILATION OF AD TARGET Kick off meeting

Slides:



Advertisements
Similar presentations
Heating, Ventilating, and Air-Conditioning
Advertisements

Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005.
CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
Paolo Guglielmini TS / CV / DC08th April 2005 BIDDERS’ CONFERENCE Invitation to Tender 3307 Supply and Installation of water cooling equipment for the.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.
PSB MPS Building 245 CV Status EN-CV-PJMichel OBRECHT – Frédéric TEIXEIRA
EN-CV status EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2015/08/06.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
N-TOF review HVAC and cooling systems YB-JIG 15/06/07.
D. Gasser ST/CV 1 Fluid distribution from UW85 Fully available now.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
R2E relocation & shielding activities Anne Laure Perrot EN/MEF- LE R2E project meeting, 23 rd October 2012.
The Building 180 Cryogenic infrastructure water cooling system Stefano Moccia, EN-CV Coordination meeting 26/09/14.
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
LS1preparation & planning status A L Perrot on the behalf of EN/MEF R2E project meeting 11 th May 2012 EN.
Contributions from BE -ABP -ASR -BI -CO DG -RP EN -CV -EL -MEF -STI GS -SEM -ASE IT -CSPH -CMXTE -CRG -EPC -MPE Follow.
1 CNGS Electrical Services (PBS 5.5) S. AKHTAR - ST/EL.
R2E Point 5 mini safe room cooling / ventilation A. L. Perrot, 30 th April 2013.
IT-4014/EN/NA62 Technical Specification Dismantling, Design, Supply and Installation of a Ventilation and Air Conditioning System for ECN3, TCC8 and GHN300.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 24/05/2006 LHCb - Install Meeting 24/05/06 TS/CV/DC activities for LHCb: - IT, TT, OT & SPD/PS, RICH.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
Update on the PSB Cooling and Ventilation Systems
Demineralised water cooling system
SPS-FIRE The SPS Fire Safety Project Planning Status
EN-CV activities for LHC during LS2
Linac4-PSB 160 MeV connection readiness review
SR1 extension follow up 27-Mar-17 Marco Ciapetti.
Conventional Facility & Siting (CF&S) Overview for the Positron Source
SR1 extension follow up Extract and update of “Minutes of the keep-up meeting for SR1” sent on 27/02/ results from the visits and new requirements.
EHN1 Extension planning
EHN1 Extension North Side wall (Removal of Existing services & platforms) Michael Jeckel & Bastien Rae.
CLIC / ILC Collaboration for CFS works
CMS Area Working Group Meeting
n_TOF “Draft” plans for YETS and LS2
FCC Tunnel and Shaft Cross Sections
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
LHC Civil Engineering Activities for YETS – LS2
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
Y. Muttoni - J.P. Corso TS Workshop Archamps
SR1 cleanroom extension
CV maintenance works during YETS
Cooling systems for HL-LHC (WP17.3)
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
SPS activities during LS2 TE-EPC (Power Converter Group)
East Area Cooling & Ventilation Status
East Hall under construction
AHU connection kit.
Top 6 Strategies of Digital Marketing.
N N D D C Ventilation Map FAB Entry 1 Entry 2 Entry 3 Jim Swan 30-inch
Discussion on MERIT Cryogenics Specifications
Aziz AMAMOU EACM – 21th May 2019
LINAC 3 Meeting ICL machines Injectors
East Area Renovation Supply of control rooms b.157
eSPS 2nd CDR meeting – 17th June 2019
Linac4 Connection Broken Line 07/08/19
IS&LEBT Commissioning Review Safety and Radiation Protection
Presentation transcript:

VENTILATION OF AD TARGET Kick off meeting https://indico.cern.ch/event/662254/ VENTILATION OF AD TARGET Kick off meeting A.BROCHE – EN/CV 04.09.2017

Content Integration Current status of the project Milestones and timing Activities requiring coordination with other groups (type of activity and timing) 4th September 2017

Integration Surface 90% complete AHU b.823 to be included CV control room: Modify cable tray position Add air-conditioning units and pumps cubicles 4th September 2017

Integration Underground 4th September 2017

Sump pump TT6 in Study Work: 1 new power cubicle in new b.196 In TT6 In b.196 Work: 1 new power cubicle in new b.196 1 control box underground Temporary solution in 2019 (power and pipe) New piping at the top New pumps ? ? Not present in CE model 4th September 2017

AD target sump pump in Study Work: 1 new power cubicle in new b.196 1 control box underground No temporary solution in 2019 Any communication required with control room? New pump? 4th September 2017

Current status of the project Ventilation Waiting for requirements of the access control Tender Specification for construction to be written Sump pumps TT6 and AD target Both in Study. Dismantling of demineralised water cooling b.195 No study required. Procurement strategy for dismantling b.196 and b.195 and sump pumps to be discussed 4th September 2017

Milestones and timing 2017 2018 2019 2020 Invitation to tender and finance committee AHUs and cubicles Construction Relocation of sump pump TT6 New AD target pump B.195 cooling TS ventilation Market Survey Temporary sump pump TT6 Ventilation Sump pump Dismantling 4th September 2017

Activities requiring coordination with other groups EN-STI Requirements for sump pump AD target BE-ICS Requirements for control access EN-EL Temporary supply to sump pump TT6. Cables to CV supervision SMB Integration up to date, in particular sumps in tunnel TT6 Discussion regarding the rain water connexion in b.196 during work ? Integration of equipment in tunnel 823 4th September 2017

Thank you. Any question ?