RF-SRF Infrastructure: Operation,Maintenance&Upgrades

Slides:



Advertisements
Similar presentations
1 User Analysis Workgroup Update  All four experiments gave input by mid December  ALICE by document and links  Very independent.
Advertisements

Technology Solutions, LLC MU April Thompson – Project Manager Neera Desai – Operations Advisor Charles Lively – Technical Advisor.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing &
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
Cleanroom refurbishment in SM18 Upgrade for the SPL high gradient resonators 26/11/2010J. Chambrillon - CERN BE/RF1.
Meeting summary (so far, Monday morning) and comments Tom Peterson, Camille Ginsburg (FNAL), Alex Ratti (LBNL) Crab Cavity Meeting, CERN, 1-6 Aug 2013.
Risk Assessment – An Essential Standard
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
CHAPTER 5 Infrastructure Components PART I. 2 ESGD5125 SEM II 2009/2010 Dr. Samy Abu Naser 2 Learning Objectives: To discuss: The need for SQA procedures.
ERP. What is ERP?  ERP stands for: Enterprise Resource Planning systems  This is what it does: attempts to integrate all data and processes of an organization.
Needs of a European SCRF Facility - the BIG plan Lutz Lilje DESY -MPY- DESY 11/2006 Planning Resource needs.
Resources Planning Human Resources Planning  = Resources.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Lutz Lilje DESY -MPY- SCRF Infrastructure for ILC EGDE Meeting Lutz Lilje.
Assembly Organisation and Duration. Work Site Organisation STORAGE SMA18 UNLOADING CLEAN ROOM CERN-SITE CLEANING MANUFACTURE DIRTY TRIAL ASSEMBLY ISO7.
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
HERA Operation 2004 M. Bieler, -MPY- PRC, Mai Performance Improvements in Remaining Problems - Improvement Program - Schedule 2004.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Revised SPL-study work-plan W. Weingarten 3 May 20101SPL Cavity WG Meeting.
Accelerator/WP High Beta Structures Alan Wheelhouse HIGH-BETA CAVITY DELIVERY April 21, 2015.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
FNAL efforts on LHC Crab Cavity R&D (Proposals for R&D sub-tasks, resources and schedule) Nikolay Solyak.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
D&D Review 6 August PEP-II Minimal Maintenance State Upkeep Stan Ecklund (J. Seeman, S. DeBarger, D. Kharakh, M. Zurawel)
October, 2009 Cost of SRF Components Gary McIntyre October, 2009 Internal Review.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
TE-CRG Activities D. Delikaris, TE-CRG.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
A European SCRF Infrastructure DESY -MPY Goals of the Infrastructure – ILC – Other projects Timeline – Phasing of work Needs.
Scope of CERN SC RF Activities Status Report for A&T Sector Meeting 18 Nov’13 BE, TE, EN Departments Summarized by José Miguel JIMENEZ 1 BE-RF (E. Jensen*,
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
SRF Test Facilities – Functions and Costs Alexander Romanenko Test Facilities Review 17 Mar 2015.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
CERN – ENGINEERING DEPARTMENT: A. Dallocchio on behalf of EN-MME
Crab Cavity Technical Coordination meeting:
CC LLRF SM18 test plan and BA6 infrastructure
CERN – Zanon discussions
Cryomodule test stand at ESS site
Status and plans for the 3.9 GHz section of XFEL
Plans towards CC in the LHC a US – centric perspective
HL-LHC IT STRING and Series test of SC link
WP5 Elliptical cavities
Cleanroom Upgrade in SM18 Optical Inspection bench
Uppsala Commitment to ESS and FREIA Planning
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
Infrastructure inventory and use
Update on HW commissioning
Me, FESA classes, Testing
Hollow e- lens, Cryogenic aspects
DESY experiences on education and training of cleanroom team
Overview & baseline of LS2 and roadmap for CRG
ESS RF Development at Uppsala University
P. Maesen for CERN BE/RF-SRF team
UK RFD Pre-Series cryomodule
SRF Section Cuvée 2014.
XFEL cavities and cryomodules measurements at AMTF
Cryogenic cavern in Asian site
TEST PLANS for HL LHC IT STRING
DS Collimators TE-MSC-CI
HIE-ISOLDE contribution packages
Installation Binder / IRR – an example
Daresbury ESS In-Kind Contributions
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

RF-SRF Infrastructure: Operation,Maintenance&Upgrades

Recent History of RF-SRF and Mandate New SRF section 10.2012: cryolab activity – recovered collimator lab and refurbished to warm reception + tuning lab. Restructuring 03.2013: bldg. 252 rinsing/coating lab plus SM18 operation to SRF section, including cleanroom&testing staff + P. Maesen, no RF technician. Done CRISP upgrades for High Gradient programme. LHC Pt4? HIE-ISOLDE cryomodules: dedicated Clean-Processing, Assembly- and Testing Infrastructure. Implemented between 07.2013 and now in SM18 RF space. SMA18 parts preparation under TE-MSC Oct. 2015: In-sourcing of Crab cavity: production, processing, testing and assembling in different configurations. So far no plan for dedicated infrastructure, just some upgrading plus additional tooling. Cryostating facility to be implemented in existing SRF space in SM18. 06.2016 - ?: SM18 side extension - additional 625 m2 for assembly/storage/shielding reinforcement. 11.2016 - ?: bldg. 252 refurbishment: safety issues –heavy component handling plus obsolete clean processing facilities.

Cryolab

B.252 Cable channels in the underground: floor deforming under load Crane exchange scheduled but Asbestos in the roof structure Heating/Ventilation obsolete; lighting outdated; new rinsing/coating preparation clean booth needed; integration with assembly cleanroom desirable Space issue for parts storage and coating activities – parallel projects suffer from bottlenecks Right now: bring services for coating stands to safety standards plus AC - ! HSE ! Next urgent: concrete injection into cable channels – floor stabilisation!

SRF Space in SM18

LHC Pt4 upgrade

How to operate and maintain CP- Facilities Cleanroom Technician for RF: rare species!!! Needs long training on the job plus specific behavioural skills. Difficult hiring ! We have 3 CR-Technicians– all 3 are complementary and account for many yrs. relevant professional experience – obviously we should keep them, isn’t it??? Project Engineers to follow-up their activities in all phases, but the clean work proper to be done by the skilled technicians. Procedures mandatory! CP infrastructure needs regular maintenance/conditioning – the heavier it is used the more maintenance is required. There are running costs for this kind of facilities and manpower needs even if there is no project SRF assembly/test activity.

How to operate and maintain CP- Facilities We provide experts advice all over CERN and we organize specific training courses for large component cleanroom activities and RF related topics – for the RF group but also for other groups at CERN (HIE-ISOLDE cryomodule, Crab project). We are setting-up teams for on-the –job training of new section members whilst coping with the very high workload of the projects and the core tasks. More details: see dedicate talks on SRF coating, testing, assemblies etc. Training new people to our needs is additional workload on the CP core team – efficient only if there is not too much rotation of personnel. People receiving the training are requested to apply the instructions as received – there is no room for applying different philosphies inside the common CP space. Wrong procedures put all activities at risk!!

How to upgrade CP- Facilities Needs a team including the project engineer(s), CR technicians and the section management to bundle a “project” – consultants if required. Needs funding plus purchase expertise to kick it off. Needs “down-time” of facilities – difficult topic these days! Most important: Needs vision on future mandate and SRF projects to be considered for the upgrade. Difficult task if these change frequently!! CRISP framework has helped in setting targets for multi-million CHF spending in a low-activity period. Unfortunately the focus has been on SPL 704 MHz that today seems to be the least relevant objects – even if synergy with other programmes obviously exists.

2 K Cryo-Upgrade in SM18 Bldg. RF Test facility area V3 V4 V5 V6 New helium transfer line Vertical test stands V3 to V6 for cavities M7 M9 Horizontal test stands M7 and M9 for cryomodules He supply from 25 m3 liquid tank

Cavity and module test area – Cryo-upgrade Service module in horizontal bunker Helium tank Cavity RF Test Area

New cavity reception area

Clean room and cavity preparation upgrade Existing clean room upgrade and extension New clean room facility Clean room layout High-pressure rinsing Ultra-pure water station J. Chambrillon

SM18 side extension

Extension Main entrance 70m 9m SM18_Plan view

Extension building

Summary Defining SRF infrastructure needs is strongly linked with the strategic management decision about the future of CERN. Results can not be obtained easily without a distinct project definition and preparation phase. The responsibility for the operation of the infrastructure stays with the experienced SRF staff. They will make sure that the needs of different programmes are respected. Personal on temporary basis can be tolerated only to a certain extent. Loosing expertise in that field is difficult to compensate. Todays infrastructure is not adequate for CRAB series production – needs to be assessed after the SPS module experience according to the project needs. Additional space is required a.s.a.p