Dependability Requirements of the LBDS and their Design Implications

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Etienne CARLIER AB/BT/EC
12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
LHC Beam Dumping system
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Failure mode impact studies and LV system commissioning tests
Beam Dumping System – Failure Scenarios Brennan Goddard, CERN AB/BT How the dump system can fail Catalogue of primary failures Failure classes and protection.
B.Goddard 08/11/04 HHH 2004 Workshop, CERN Beam Dump Brennan GODDARD CERN AB/BT The existing LHC beam dump is described, together with the relevant design.
Technical review on UPS power distribution of the LHC Beam Dumping System (LBDS) Anastasia PATSOULI TE-ABT-EC Proposals for LBDS Powering Improvement 1.
LBDS Kicker Electronic and Slow Control Etienne CARLIER AB/BT/EC.
LHC Beam Dump System Technical Audit Trigger Synchronisation Unit.
BIW May 2004 LHCSILSystemsBLMSSoftwareResults Reliability of BLMS for the LHC. G.Guaglio, B Dehning, C. Santoni 1/15 Reliability of Beam Loss Monitors.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
B. Todd et al. 25 th August 2009 Observations Since v1.
LBDS overview on system analysis and design upgrades during LS1 Roberto Filippini, Etienne Carlier, Nicolas Magnin, Jan Uythoven CERN Workshop Machine.
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
Etienne CARLIER, LBDS Audit, 28/01/2008 LBDS Environmental Aspects EMC, radiation, UPS… Etienne CARLIER AB/BT/EC.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
The LBDS trigger and re-trigger schemes Technical Review on UPS power distribution of the LHC Beam Dumping System (LBDS) A. Antoine.
Product & Technology Quality. Excellence. Support SIL Explanation 27.JAN 2006 Automation & Safety.
1 Reliability and Availability of the Large Hadron Collider (LHC) MachineProtection System Jan Uythoven CERN, Geneva, Switzerland Thanks to R. Schmidt,
1 Will We Ever Get The Green Light For Beam Operation? J. Uythoven & R. Filippini For the Reliability Working Group Sub Working Group of the MPWG.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
TRIGGER DELAY 100µs. G. Gräwer AB/BT/ECLBDS Trigger Delay2 The trigger delay is a back-up system that generates an asynchronous dump trigger for MKD and.
Commissioning / Reliability Runs / Dry runs 1 Jan Uythoven, LIBD meeting on LBDS Reliability Run 04/02/2014 Nov – Dec 2013 Commissioning individual MKDs.
CERN Dependable Design Example ITER – Machine ProtectionB. ToddMay 2010 Thanks to : TE/MPE/MI, CERN Machine Protection Panel, et al 1v0 Beam Related Machine.
BEAM INSTRUMENTATION GROUP DEPENDABILITY APPROACH CERN, Chamonix 26th January 2016 William Viganò
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
LHC’s Modular Machine ITER – Machine ProtectionB. ToddJuly 2010 Thanks to : TE/MPE/MI, CERN Machine Protection Panel, et al 1v0 Protection System.
Beam Interlock System Dependability Study RSWG – 31 st January 2005.
16 December 2005 IntroductionIntroduction System Layout Dependable Design Dependability Analysis Sensitivity ConclusionsSystem LayoutDependable DesignDependability.
Design process of the Interlock Systems Patrice Nouvel - CERN / Institut National Polytechnique de Toulouse CLIC Workshop Accelerator / Parameters.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
Reliability Analysis of the LHC Beam Dumping System Taking Into Account the Operational Experience during LHC Run 1 Roberto Filippini CERN ATS Seminar,
Data providers Volume & Type of Analysis Kickers
The TV Beam Observation system - BTV
DRY RUNS 2015 Status and program of the Dry Runs in 2015
2007 IEEE Nuclear Science Symposium (NSS)
UPS power distribution for LHC Beam Dumping System
Beam dump XPOC analysis
The LHC Beam Dumping System
Reliability targets in functional specifications
LHC Beam Dumping System Reliability Run Summary
MKD/MKB Review Meeting Scope and Definition
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
Jan Uythoven For discussion
M.Jonker CTC MPO-WG status
1v0.
LHC Risk Review: Kicker Magnet Reliability
Commissioning and Testing the LHC Beam Interlock System
MPSC Procedures An update
Remote setting of LHC BLM thresholds?
Machine Protection Xu Hongliang.
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Beam Dumping System and Abort Gap
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
BEAM LOSS MONITORS DEPENDABILITY
Global Post Mortem Event Event Timestamp: 15/06/12 15:54:
Machine Protection System Commissioning plans
1v1.
Will We Ever Get The Green Light For Beam Operation?
Operational scenario of the BLM system
The LHC Beam Interlock System
Interlocking strategy
Jan Uythoven For the LBDS Team
Mikael Olsson Control Engineer
What systems request a beam dump? And when do we need them?
Close-out.
Presentation transcript:

Dependability Requirements of the LBDS and their Design Implications Jan Uythoven (AB/BT) References to work by R.Filippini (Ph.D. thesis) and Machine Protection Working Group

Outline Requirements on the LBDS in the context of the Machine Protection System Dependability numbers for the MPS Dependability numbers for the LBDS Safe Design of the LBDS Measures taken Sensitivity Procedures Conclusions Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Dependability Requirements of the LHC Machine Protection System Safety Assessment (‘reliability’) IEC 61508 standard defining the different Safety Integrity Levels (SIL) ranking from SIL1 to SIL4 Based on Risk Classes = Consequence x Frequency Machine Protection System for the LHC should be SIL3, taking definition of Protection Systems, with a probability of failure between 10-8 and 10-7 per hour (because of short mission times) Catastrophy = beam should have been dumped and this did not take place; can possibly cause large damage With 200 days of operation per year: 1/10-7 hours  1 failure every 2000 years Availability Definition: Beam is dumped when it was not required Operation can not take place because the protection system does not give the green light (is not ready) Requirement: Definition not according to any standard Downtime comparable to other accelerator equipment; maximum tens of operations per year Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

The LBDS within the Machine Protection System Study of simplified Machine Protection System LBDS, BIC, BLM, QPS, PIC Absolute value of the unsafety and # false dumps depend critically on model assumptions Dependability studies were made for each sub-system Unsafety of the LBDS and availability comparable to the other systems: Unsafety 2 x 2.4 x 10-7 /year False dumps 2 x 4 /year Resulting safety number can be between SIL2 and SIL4 LBDS Safety > SIL 4 ! Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Calculation of the LBDS Dependability Numbers Ph.D thesis Roberto Filippini FMECA analysis More than 2100 failure modes at component levels Components failure rates from standard literature (Military Handbook) Arranged into 21 System Failure modes Operational Scenarios with State Transition Diagram for each Mission = 1 LHC fill State Transition Diagram for Sequence of Missions and checks Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

No single point of failure should exist in the LBDS Fault Tolerant Design No single point of failure should exist in the LBDS Redundancy is introduced to allow failures up to a certain threshold Redundancy in components and in signal paths. Surveillance detects failures and issues a fail safe dump request. Redundancy 14 out of 15 MKD, 1 out of 2 MKD generator branches Surveillance Energy tracking, Retriggering 1 out of 4 MKBH, 1 out of 6 MKBV Energy tracking Energy tracking, Fast current change monitoring (MSD) 1 out of 2 trigger generation and distribution Synchronization tracking Reference energy taken from 4 Main Dipole circuits TX/RX error detection Voting of inputs Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Apportionment of Dependability Safety and number of false dumps are apportioned to the LBDS components. The MKD is the most complicated and critical system of the LBDS. It makes the largest contribution both to unsafety (75 %) and to the number of false dumps (60 %). Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Sensitivity to Fault Tolerant Design and Surveillance (ReTrig.System) All these systems are obligatory ! Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Sensitivity to Assumed Failure Rates Important for Safety Important for Availability Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Safety by Operation / Procedures Periodic checks to get back to a state which is ‘as good as new’ Failure rates of redundant systems increase in time – get back to zero (different from aging) Included in Dependability Calculations After each LHC beam dump the green light for injection is only given when Internal Post Operational Check (IPOC) is ok: MKD and MKB current waveforms Redundancy in current paths … External Post Operational Check (XPOC): Image on screen in front of beam dump Beam Loss Monitors in the extraction area and dump line Testing before operation Tests in the laboratory, before installation Tests once installed, before operation with beam Talk NM Talk EG Talk JU Jan Uythoven, AB /BT LBDS Audit, 28 January 2008

Conclusions The Beam Dumping System has been designed with Safety and Availability as design criteria Redundancy Surveillance Procedures A detailed dependability analysis has been made for the Beam Dumping System and other Machine Protection Subsystems Coherency within the Machine Protection System should lead to acceptable safety and availability of the MPS as a whole Beam Dumping System not a weak link of the MPS concerning safety Acceptable number of false beam dumps from the LBDS Within the Beam Dumping System Sensitivity to design parameters / redundancy shows that correct design choices seem to have been made To the ‘invited experts’ of the Audit to confirm (or not) Jan Uythoven, AB /BT LBDS Audit, 28 January 2008