Test Liquid Handling Before and After Containment Sump and Spill Bucket Hydrostatic Testing Edward S. Kubinsky Jr. CROMPCO, LLC Director of Regulatory Affairs, Training and Certification ed.kubinsky@crompco.com ASTSWMO UST Workshop Louisville, KY 05/24/2017
Crompco Hydro Testing Solution – “Water Wagons”
Crompco Hydro Testing Solution – “Water Wagons”
Crompco Hydro Testing Solution – “Water Wagons”
Crompco Hydro Testing Solution – Potable Water at Yard for Quick Water Wagon Filling With Clean Water
Crompco Hydro Testing Solution – 5,000 Gallon “dirty water” Trailer Used for Water Storage for Disposal
Full Hydrostatic Testing Performed on 05/08/2017 (Buckets, Sumps, UDC’s) Test water was approximately 3-4 weeks old. Owner of the site “owns” the water used for testing and handles disposal costs. Water is used only at this customer’s sites.
Started Job w/ Hydro Test of All Spill Buckets
Then Started STP Sumps
Testing being performed
Time to Move to the UDC’s
Testing being performed
Time to Vac it Out