SMACC Tenth report [15 min] 13/09/2013

Slides:



Advertisements
Similar presentations
Alfa-Omega Team General information General information (Anna) W Bellows (Alain) DN200 (Andrea) A.A.A. - TE-MSC-CMI Section meeting Feb 19th, 2013.
Advertisements

Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
O. Pirotte, A.Perin, TE/CRG, 4 th LHC Splice Review, Page 2 4 th LHC Splice Review, July 22-24, 2013 O. Pirotte (TE-CRG), A. Perin (TE-CRG)
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
Leak Testing QC of Cold Vacuum Systems the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank.
Vacuum, Surfaces & Coatings Group Technology Department Cleanness of the 3-4 cold beam lines Outline:  History: Status of 2009 cleaning  Foreseen and.
Overview of SMACC-QA 1.Recall of SMACC-QA organization 2.Tuning the procedures 3.Main results from the QC teams 4.Auditors findings Ranko Ostojic 23 July.
Status of SMACC-QA 1.Recently resolved issues 2.Update from QC teams 3.Statistics S56 and S67 4.Auditors findings 5.4th Splice Review – 22/24 July Ranko.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Alfa-Omega Team Coordination LS1 Collaboration Seminar, 27 th November 2014 Anna Chrul, IFJ PAN Kraków.
Beam Vacuum Quality Control Outline  VSC consolidation  VSC support  Organization  Status Cédric Garion on behalf of TE-VSC Cédric Garion TE/VSC Beam.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
Technology Department 1 Visit to Hall 180: Presentation of the consolidation process Third LHC Splice Review, November 12, 2012.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Fourth LHC Splices Review Quality Assurance Review Review of actions from 3 last reviews NB : 8 non-closed ones from 1 st review 5 non-closed ones from.
LHC Magnets/Splices Consolidation (20 minutes) Francesco Bertinelli 7 June, slides  Status of LHC: electrical connections  Description of shunt.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project … Courtesy ….
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Work Organisation for Splice Consolidation Francesco Bertinelli 20 minutes presentation, 10 minutes discussion: 12 slides First LHC Splice Review, CERN,
Third LHC Splices Review Production Readiness Review Introduction Why this 3 rd review ? Planning, committee, mandate Evolutions since last review: SMACC.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
LHC magnet protection diodes status and recommendations for LS1 October 10 th, 2012 F. Savary on behalf of the diode working group (TE-MSC and MPE Groups.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
TE-CRG Activities D. Delikaris, TE-CRG.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
A. Perin, TE/CRG, DFBA LSC Page 2 LHC Long Shutdown 1 Committee June 14 th, 2013 A. Perin (TE-CRG) On behalf of the DFBA splices consolidation.
Proposed integration of cryo BLMs in LHC during LS1 V.Parma, CERN, TE-MSC With contributions/input from: M.Sapinski (BE-BI) Th.Renaglia (EN-MME) N.Bourcey.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
MSC Technical Meeting 29 August 2013 Overheated QBBI.A21L6 F. Savary with contributions from N. Dalexandro, H. Prin, C. Scheuerlein, P. Voisin.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
LHC Risk Review Installation Progress Francesco Bertinelli – TE/MSC 5 March, 2009 (20 minutes) On behalf of - and with several contributions from – the.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Third LHC Splices Review SMACC Organisation Scope of work (What’s new since Nov 2011) Organization chart update Human resources Budget Unforeseen? Unexpected?
K. Foraz on behalf of OSS members
SMACC Eighteenth report [20 min] 07/02/2014
Cold mass design, assembly plans and QA/QC at CERN
Status of LHC installation & New Installation Schedule
K. Foraz on behalf of OSS members
Update of cryogenic activities
12 October 2009 RRB Plenary R.-D. Heuer
Teleconference ACS – FREIA 10th May 2017
The LHC - Status Is COLD Is almost fully commissioned
LS1 Committee January 24th, 2014
Long Shutdown for the LHC: Vacuum Beam Pipes
LHC Dipole Diode Insulation Consolidation Review (I) INTRODUCTION
Consequences of warming-up a sector above 80 K
Reinforcement of the LHC Dipole Diodes Insulation during LS2
Renovation of the 45-year old PS magnets
SMACC local splice quality control
Functional specification for the consolidated LHC dipole diode insulation system and consolidation strategy C. Scheuerlein on behalf of the LHC dipole.
Consolidation of the dipole diode insulation Technical aspects
K. Foraz on behalf of OSS members
Teleconference ACS – FREIA 19th June 2017
Shortening the long RQF/RQD busbar segments in points 1 and 5
Presentation transcript:

SMACC Tenth report [15 min] 13/09/2013 Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project

Activities since last LSC (30/08/2013) By Activities By sectors SIT DFBA Dashboards Brief ElQC update Activities for the next 2 weeks Conclusions

SMACC Main activities for the next 2 weeks Sector 56 : Work on non-conformities Sector 67 Installation of insulation boxes and injection Rewelding of M sleeves Leak test of M lines Reclosure of interconnections DFBA consolidation Sector 78 Desoldering and resoldering of splices Installation of shunts Sector 81 ElQC of existing splices Other sectors: S12: Opening of M lines S23: Opening of interconnections and installation of DN200 S12, 23, 34 & 45 : Reconnection of replacing magnets Advanced opening for outliers and CSCM segments Inspection of connection cryostats From last LSC (30.08.2013)  On-going, 52 ICs reclosed, leak test of beam lines completed succesfully  In progress, critical activity  In progress, > 1/3 of sector rewelded Jeune Genevois …  Started, 2/14 vac subsectors validated  Started, 14 ICs reclosed  On-going Desoldering completed, starting in 81   On-going, > 1/3 of the sector equipped  On-going  On-going, > ¼ completed, see further > 80% open, DN200 installation completed Good progress     On-going 

SMACC Progress report by activity Opened interconnections in 8 sectors, > 6 sectors-eq are opened Back on schedule

SMACC Progress report by activity M line cutting : > 4.5 sectors equivalent (S12 well advanced) Replacing team leader at CERN since beginning of August Courtesy JM Hubert

SMACC Progress report by activity Desoldering : Completed in S56 & 67 & 78 Resoldering completed in S56 & 67 & at 75 % in S78 59 Desoldering: Nominal was 53/week; Now we need 95/week Increasing is seen (Effect of new staff and tooling) W36 included Jeune Genevois W37 not completed (preliminary: 85) Resoldering : Improving, not yet there 1 person of the team prepares intervention on overheated cable in 56 with a staff Courtesy H Prin

SMACC Progress report by activity Shunts are installed in > 2 sectors-eq. 50 ICs behind schedule (About one week at nominal rate) Delay effect of the reinforcement of resoldering teams Non-consecutive interconnections About 8 000 shunts installed (30% of the LHC) «Last 10% effect» in 2 sectors

SMACC Progress report by activity Installation of insulation box: Good progess in 67 ( 50 %) 2 phases : Minimum required: 45 ICs/ week (9 per day) Installation (time consuming, continuous) & Injection (By batch of ≈ 15 ICs) Installation completed in 56 and 55 % of 67 Injection completed in 56 and 45 % of 67 : Inject every 2 days by batch of 15 (37.5/wk) Bottleneck is still the installation of the electrical insulation  Work sequence is optimised  Resources are redirected 2 FSUs and 3 COAS (PAEC) in October THE critical activity Courtesy H Prin / M Duret

SMACC Progress report by activity Quadrupole diodes > 5 sectors are opened / 2 sectors are almost consolidated (1 diode to be exchanged because of too high internal resistance) Globally almost on schedule BUT One diode has to be replaced because of too high diode to heatsink resistance (Q31R6) Some components were delivered, allowing to barely complete S67; some pieces have to be reworked at CERN Not critical YET Alternative supply still under investigation to check that it can meet the requirement OK for the material certificate, price to be renegotiated, manufacturing method still to be confirmed (Delivery time of at least 2 months) Courtesy L Grand-Clement / F Savary

SMACC Progress report by activity M Welding : 290 ICs welded, ≈ 1.35 sec-eq: Reduced team, extrapolating: nominal rates seem achievable Limited by release rate, not by the team capacity (Presently 30/week) In-line with forecast of last LSC Delay wrt baseline Required rate to end according to baseline : 45 IC/week Team sized for 53-60 Margin for the «last 10%» has been eaten Situation to be monitored for a possible reaction in October. Courtesy S Atieh

SMACC Progress report by activity M sleeves leak testing : All possible subsectors (200 ICs) are leak tested All possible subsectors of S56 (11/14) are released and leak tested Starts in S67 : 3 subsectors released. 2 are leak tested In-line with forecast of last LSC Delay wrt baseline Required rate to end according to baseline : 3.1 subsec/week Foreseen for 3-3.5 subsec/week Margin for the «last 10%» has been eaten Situation to be monitored for a possible reaction Courtesy P Cruikshank / L Mourier

SMACC Progress report by activity Reclosure of interconnections : On-going in 67 (priority) and 56, 52 ICs are reclosed in 56 and 14 in 67 Stopped in 56 during beam lines leak test; contraint relaxed this week by VSC S56 will be delayed (Overheated cable, DFBAK bellows)

SMACC Progress report by activity Final leak test: 1st one STARTED  16 consecutive interconnections closed in 56 Final leak test started Results in 2 weeks, on schedule

SMACC Progress report by sector Main activities are on non-conformities Was temporarily stopped for beam lines leak testing Reclosure as a an activity to smooth work load (priority given to S67) Repair of overheated cable will start next week, with a completion by end of October One PIM to be exchanged for protruding RF fingers (QQBI.29R5): Re-rewelding capability will be limited – specific procedure (was consolidated in 2009)

SMACC Progress report by sector All non-problematic ICs are shunted Main activities are installation of insulation system and welding of M lines Leak test of M lines is on-going (2/14 subsectors validated) Reclosure started

SMACC Progress report by sector Main activities are: desoldering of splices (just completed), resoldering of splices, installation of shunts and related QC/QA

SMACC Progress report SIT 2 cryomagnets are reconnected, the other ones are under reconnection and it has started for Q5L8 Standard reconnection will be done by the train when it will arrive PIMs: Rewelded in 6 sectors, 2nd RF ball test done successfully in S56 (Only one more to change in 56) 2 Y-line leaks are repaired and validated, only the closure of IC remains, by the train, end of 2013 To start : Interventions on SAM (Tooling under checking in workshop) and IT Courtesy N Bourcey, S Le Naour

SMACC Progress report DFBA M Bellows: See report by L Tavian Splices consolidation has restarted at a good rate, with reinforced team Courtesy TE-CRG, TE-MSC and EN-MME

SMACC Dashboards

SMACC Dashboards Opening is back ahead of schedule despite closure of interconnections Shunting starts to improve with reinforcement and optimisation of critical activities Welding: Limited by release rate, confident that nominal rate can be achieved, margin has been eaten up M leak test : Limited by release rate, confident that nominal rate can be achieved, margin has been eaten up ReClosure: started ahead of schedule, now in S67 Final leak test started (Results in 2 weeks)

SMACC Dashboards Will be completed by beginnig of November Baseline: 26.1 % (22.3 %) Completed: 23.0 % (20.0 %) Delay 10 (9) days Baseline: 47.0 % (41.1 %) Completed: 33.0 % (29.7 %) Delay 27 (17) days Baseline: 42.9 % (35.7 %) Completed: 23.0 % (22.3 %) Delay 41 (36) days Baseline: 100 % (100 %) Completed: 82.4 % (72 %) Delay 64 (52) days Will be completed by beginnig of November

SMACC Dashboards Progress: Baseline: 31.8% (27.2 %) Completed: 25.6% (22.4 %) Delay 18 (15) days

The impact of the summer period on the planning was 3 weeks SMACC Summary on progress Main 13 kA Splices:  Started a week in advance, now 2 weeks delay (stable) Special Interventions:  27 days delay, non-conformities start to impact DFBA:  > 1 month delay: should recover for end of the year Bellows issue could have a large impact DN200:  ≈ 2 months delay: not critical SMACC:  About 3 weeks (stable) The impact of the summer period on the planning was 3 weeks Can recover next year when resources are freed by finishing activities

Preliminary results of existing splices quality control (7.09.2013). SMACC ElQC Status Preliminary results of existing splices quality control (7.09.2013).   Sector Sector 56 Sector 67 Sector 78 Sector 81 LHC Measured [%] 100 25 40 To redo [%] 28 32 29 31 30 30 % seems confirmed as more solid number Dedicated presentation in October with half of the LHC measured Courtesy C Scheuerlein, S Heck

SMACC Main activities for the next 2 weeks Sector 56 : Work on non-conformities including repair of overheated cable Reclosure (not in priority) Sector 67 (Priority sector) Installation of insulation boxes and injection Rewelding of M sleeves Leak test of M lines Reclosure of interconnections DFBA consolidation Sector 78 Complete resoldering of splices Installation of shunts Sector 81 ElQC of existing splices Start desoldering of splices Other sectors: S12: Complete opening of M lines S23: Opening of interconnections S12, 23, 34 & 45 : Reconnection of replacing magnets Advanced opening for outliers and CSCM segments Inspection of connection cryostats

Conclusions So far, not so bad … Issues: New activity: Start of final leak testing (The last one ) About to start to repair the overheated cable in 56 in-situ The ratio of 30 % of splices to redo seems confirmed for 40% of the LHC Reduced ElQA test frequency allows to cope with > 3 sectors in // Global delay of 3 weeks due to summer period and technical issues under solving ; difficut to recover this year Margin has been eaten up for some activities (M welding, M leak test) Issues: Reach nominal rate for arc splices consolidation (Ramp up with de/re soldering and optimise installation of insulation box) DFBA busbar bellows Components for diodes consolidation So far, not so bad …

SEQUENCE AND STATUS Availability of components Install DN200 ≈ 80% OK to open Open ICs Open M sleeves 8 sectors > 6 sectors ≈ 4.5 sectors Undo / Redo splices ELQC (new splices) ≈ 2.5 sectors ≈ 2.5 sectors ELQC (old splices) Machine Cu ELQC after Cu mach. > 3 sectors > 2 sectors ≈ 2 sectors Consolidate Q diodes Availability of components ≈ 1.7 sectors Install shunts ELQC after shunt Insulate splices Weld M Leak test M Close IC Final LT > 2 sectors > 2 sectors ≈ 1.7 sectors ≈ 1.3 sectors ≈ 1 sector ≈ 1/4 sector Started