Transitional Exit Capacity Proposals -Update

Slides:



Advertisements
Similar presentations
NTS Exit Capacity - Amending the DN Adjustment Window Transmission Workstream, 1 April 2010.
Advertisements

UNC Modification Proposal Revised Timescales for LDZ Shrinkage Arrangements Simon Trivella – 25 th September 2008 Distribution Workstream.
UNC Modification Proposal 0116 Reform of the NTS Offtake Arrangements Transmission Workstream 5 th October 2006.
Operating Margins. 2 Competitive Provision of Operating Margins Change to National Grid Gas’s Transporter Licence which:  Introduced Special Condition.
Entry Capacity Release Methodology Statement Transmission Workstream, 4 th May 2006.
Capacity Release Processes and Investment Planning Transmission Planning Code Workshop 2 1 st May 2008.
Incremental Entry Capacity Release Methodology Statement Review 2005 Transmission Workstream - 15th June 2005.
Mod 214 – Reservation of firm NTS Exit Capacity at new NTS Exit Points in the transitional period Steve Rose.
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Mod 166 Review Group Incremental Exit Capacity at New and Existing Exit Points.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Review of Entry Capacity and the Appropriate Allocation of Financial Risk Review Group th Sept 2008.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th March 2009.
Exit Capacity Release Methodology Statement - ExCR Transmission Workstream – 5 th Feb 2009.
Transitional Exit Capacity Proposals -Update Offtake Agreement Workstream, 30 Nov 05 Dave Adlam.
NTS Exit Regime Transmission Workstream – 6 th July 2005.
Transitional Exit Capacity Proposals -Update Transmission Workstream, 1 Dec Nov 05.
Gas Transmission Charging Review: Final Capacity Charging Proposal Gas TCMF 14 th December 2006.
Stuart Forrest, Network Planning Manager, Scotia Gas Networks 19 th October 2010 MOD Review of Industry Charging & Contractual Arrangements in Relation.
European Transparency Requirements - update Transmission Workstream 1 st May 2008.
Transitional offtake arrangements – Ofgem Initial Proposals on transitional incentives 6 October 2005.
Transmission Workstream 6 January 2011
SGN Modification Proposal Amendments to UNC TPD OCS Process Long Term Allocation of Capacity for the Transitional Period.
Exit Capacity Release Methodology Statement
Entry Capacity Overrun price calculation
An alternative approach…..
Modification Proposal 0283 Update
Transmission Planning Code – Draft Document
Exit Capacity User Commitment – Transmission Workstream update
Transmission Planning Code
Transmission Workgroup 4th October 2012
Transmission Workstream 4th July 2007
Transmission Workstream, 6 August
SO Incentives from April 2010
UNC Modification Proposal 0373
UNC Trader User – Licence obligations
Capacity Methodology Statements: Impact of Mod 452
Capacity Methodology Statements
Connected System Exit Points Administration Options
Exit Capacity Substitution and Revision
Exit Capacity – Managing Incremental Signals
7th July 2011 Transmission Workgroup - Elexon
Update on Exit Capacity Substitution and Revision
0350 – Combining the NTS entry capacity and exit capacity credit checks Chris Shanley.
Transmission Workgroup 6th March 2014
MOD National Grid NTS Initiated Flow Swaps
Simon Trivella –5th May 2011 Transmission Workgroup - Elexon
Modification Proposal 0101 – “Amendment to demand forecasting timings in relation to the Gas Balancing Alert”
Transmission Planning Code Review
QSEC auction timetable
Flow Swap Scenarios – Agreed Logic
Long Term Non Firm Capacity Update
UNC Transmission Workstream 7th December 2006
Proposed Transitional Gas Exit Arrangements
Richard Fairholme E.ON UK
Gas Customer Forum DN Interruption Update - Introduction
Richard Fairholme Transmission Workstream 4th September 2008
Mark Freeman 29th January 2007
Entry Overrun Calculation
Generic Revenue Driver Methodology
Review Group 221: Review of Questions from Session 2
195AV “Future work” – system flexibility
Commercial Arrangements For Gas Quality Service – Introduction
Incremental Entry Capacity Release Methodology Statement
Modification 0043 – Limitation on offering for sale unsold capacity
Alignment of Part 4B with ISAE 3000
Presentation transcript:

Transitional Exit Capacity Proposals -Update Offtake Agreement Workstream, 2 Nov 05

Transitional Proposals - Update UNC Mod 0046 With Ofgem for decision IExCR/SC4B Consultation completed on proposed revisions DN and DC ARCA

Respondents IExCR SC4B ARCA Northern Gas Networks X Scotia Gas Networks Scottish and Southern Transco Distribution Association of Electricity Producers (AEP) Chemical Industries Association (CIA)

IExCR – Key Issues (1) Lack of clarity of definition of “incremental capacity” and difference between IExCR and Licence definitions Ofgem intend to clarify definition of “incremental capacity” for both interim and transitional periods as part of final proposals on DN Incentives “Initial Volume Allocation” for NTS/LDZ offtakes over transitional period to be stated in IExCR Requires re-consultation on IExCR

IExCR – Key Issues (2) Desire for NG NTS to publish available capacity at each exit point to understand whether a request would trigger investment Determination of available level of incremental capacity in advance of capacity requests is complex due to interdependence between capacity requests and hence the number of scenarios that could affect the level of capacity being made available Any estimate of availability may therefore be difficult to interpret and may not meaningfully inform user requests Only once the request has been made can the level of available capacity be determined with sufficient accuracy

IExCR – Key Issues (3) DNO view that ARCA not required for incremental capacity requests as already have sufficient Licence obligations to ensure don’t overbook We require ARCAs to demonstrate that “large” investments have been undertaken in response to a sufficiently strong “market signal” Therefore consider appropriate that same principles applied to all NTS Exit Points

IExCR – Key Issues (4) DNO view that ARCAs should not be required for 1 in 20 load growth In most cases we do not expect such requests to trigger Specific Reinforcement and hence would not require an ARCA However we believe that the definitions of Specific and General Reinforcement defined in SC4B should be applicable to any NTS Exit Point Under the exceptional circumstances that an ARCA was required in respect of a request due to 1 in 20 load growth, then as the DNO has a Licence obligation to meet such requirements then it should meet ARCA commitment

IExCR – Key Issues (5) We require assurance that if we incur investments costs by following the IExCR that we would be appropriately renumerated Ofgem view is that the level of commitment in the Langage determination (1 year’s Exit Charges paid over 2 years) would not necessarily be sufficient to justify all system investment costs and may prejudice the operation of DN incentives Discussions with Ofgem ongoing as to the appropriate level of financial commitment to justify our investment costs We may therefore propose a set of principles within the IExCR itself in respect ARCAs and the appropriate level of financial commitment

ARCA – Key Issues View that delay to capacity delivery date should be approved by the Authority similar to new process in place at entry The ARCA is a commercial agreement between National Grid NTS and the connecting party and is governed by English Law. Hence, where the counter party considers that National Grid NTS has not justified any extension to the delivery date then they can make a challenge through the courts It will then be for a judge to decide, based on the available evidence, whether National Grid NTS is justified, in accordance with the terms of the ARCA, in extending the delivery date

Way forward Anticipate to commence re-consultation on IExCR next week with 14 day consultation period (subject to Authority approval) Include Initial Volume Allocations for NTS/LDZ offtakes over transitional period and ARCA principles Also plan to issue consultation reports on previous consultations and final proposed versions of SC4B and ARCAs