Francois and Lau EATM 17 July 2012

Slides:



Advertisements
Similar presentations
Lau Gatignon, EATM, 7 October  The T9 and T10 lines have been running smoothly from mid July and the T11 beam started up very smoothly for CLOUD.
Advertisements

LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Construction and Installation of the CLIC Experimental Area
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Challenges and Overview From Technical Coordination 27/08/2013 -FH1.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
SPSC Questions to the 2014 NA62 Status Report 1 Beam: which is the beam structure expected in October? Which is the intensity you can reasonably expect?
R. Fantechi. TDAQ commissioning Status report on Infrastructure at the experiment PC farm Run control Network …
STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.
Compressor status AWAKE Technical Board meeting 19 August 2015.
Cooling of NA62 vacuum system November 11 th, 2014 E. Harrouch, EN-MEF, on behalf of the NA62 Vacuum Team.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
East Area, M2, K12 Lau Gatignon / EN-MEF, EATM
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
The Building 180 Cryogenic infrastructure water cooling system Status Update Stefano Moccia, EN-CV Coordination meeting 14/10/15.
Installation status Control Room PC farm room DetectorsEB Infrastructure 918 ECN3.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
NA62 CV activities Piero Valente 5 th September
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Installation of the T600 at Fermilab CSN2, September 22,
MEF - Machines & Experimental Facilities March 2013 Project meeting Activities in Linac4 tunnel and building in 2013 March 2013 Project meeting 14/03/2013J.Coupard1.
TE-CRG Activities D. Delikaris, TE-CRG.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
Laser Line work package (WP6) AWAKE Technical Board meeting 19 May 2014.
ELENA installation progress F. Butin / ELENA collaboration.
S A Griffiths CM42 June 2015 Electrical & Control.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
High energy beam transport.
Linac4-PSB 160 MeV connection readiness review
Status, Schedule and EVM for the test facility project
CBETA Technical Review
ELENA installation and commissioning status
AD consolidation activities in LS2
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
Consequences of warming-up a sector above 80 K
SPS Planning for the EYETS Meeting 8 (07/12/2016)
EN-STI activities in LHC during EYETS
Renovation of the 45-year old PS magnets
NA CONSOLIDATION & SAFETY SYSTEMS
Status of the cryogenic system for B180
K. Foraz on behalf of OSS members
TEST PLANS for HL LHC IT STRING
Extract from today’s talk given to DCB
East Hall under construction
Overview of the TARGET Monolith Rough Vacuum
East Hall under construction
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

Francois and Lau EATM 17 July 2012 NA62 / K12 Status Francois and Lau EATM 17 July 2012

BEAM LINE: Installation of last magnets under way, now installation of plug-in bases Hope to complete collimator preparations before end of July, including controls by EN-STI and new inserts by MEF. TAX block delivery still expected in October. Plan B exists in case of late delivery. Big Fisc is on critical path, vital for beam diagnostics. A new tank must be constructed – meeting on 18th of July with BI team. Cedar feet remain to be installed and aligned. Final alignment of all beam line elements, once installation is complete.

VACUUM BEAM Layout is defined in detail and agreed. Fabrication of all connections upstream of blue tank is on-going. Installation and leak tests after holidays. Downstream of LKR some transition pieces are not yet made. Follow the installation of detectors vacuum wise. Control cables (for technical run) are being pulled. Compressed air distribution (local connections) must be clarified soon. The Cedar prototype windows are in the final phases of evaluation. If successful – ready to produce final windows soon. Baseline for the Technical Run: 150 and 200 micron thickness. Turbo-pumps are still operational, but obsolete. Recommend to foresee some spare pumps from operations budget.

BLUE TUBE VACUUM The cryo-pump order has gone out. Still some discussions on-going with manufacturer concerning routing of primary pump system. The firm will visit the site on July 25th. The ongoing tests with the full blue tube section for the Technical run are now stalled due to non-availability of compressor cooling (planned). Also suddenly the pumps started to saturate far too quickly. Some damage was found at the level of the pump. Discussions under way with the company. A new link person has been nominated in TE-VSC: Berthold Jenninger.

DETECTORS MUV installation is under way. MUV3 will be installed this week. MUV2 is foreseen next week. MUV1 will be much later. The CHOD has been tested successfully and is ready for the Dry Run. The Straw detector is scheduled to arrive in September.

MUV3

UNDERGROUND INFRASTRUCTURE The T10 cooling system seems on track for the Technical Run. The “skid” is ready at the Iniziative Industriale premises. The tube layout is ready for approval soon and must be integrated in Catia. The cooling for the cryo-pumps will be delayed by two weeks, but this is not on the critical path. The PPG air lock tightness will be made in the next week and the degree of tightness evaluated by CV. This system is still on track for commissioning in September. The design of the TCC8/ECN3 separation wall must be endorsed by CV, as well as minor modifications to the present system and operational procedures for the 2014 run. The electrical infrastructure is essentially completed. The contract for the ECN3 crane renovation has been granted. For TCC8 the renovation will be done later. The RP upgrade (to RAMSES) will be done after the technical run. A workaround has been prepared by RP.

SURFACE BUILDING The surface building is ready for the Dry Run, apart from the air conditioning. Two temporary coolers have been installed in the control room and PC farm room. These remain available until July 27th. X-ray and pressure tests are on-going this week. The pipe insulation work starts on Wednesday and will last 2 weeks. The corridor floor will thus be open in a number of places. The access control to the different rooms is almost completed. The EDH authorisation system is being prepared. It is not clear how long the commissioning will take. Painting will be done between the Dry Run and Technical Run.