1st LHC MD Period Started

Slides:



Advertisements
Similar presentations
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Advertisements

RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Preliminary MD Report R. Assmann, G. Papotti, F. Zimmermann
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
The LHC - Status Is COLD Is almost fully commissioned
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Wednesday 21 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Morning Meeting - G. Arduini
Machine availability reaching well over 80%
Tuesday TOTEM and transverse loss map (1) OK
Summary of Week 13 G. Arduini, B. Holzer
LHC Injection and Dump Protection
Thursday morning 09:30 Dump of pPb fill.
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Wed :40 Lost S78 - QPS controller.
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
Monday February 28th 8h00: Injection
Week 36 Machine coordinators R.Assmann, R.Bailey
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Yesterday morning Held 1647 for a while – SPS kicker problem
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Tuesday morning 08:30-09:00 Squeeze with probe.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Programme for Friday 9 July
Sat morning Until 12:40: Loss maps at injection
MD Planning Fri – Sat (1. – 2.7.)
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Summary for LPC (March 7th, Ralph Assmann)
Plan for 1 m b* J. Uythoven & J. Wenninger
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
RAMP FOR COLLIMATOR SETUP
Another Immortal Fill….
Saturday 26th March 9:15 Problem with RB78 temporarily solved. It's running on one Thyristor bridge only and without the active filter LHCb polarity change.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

1st LHC MD Period Started 05/05/2011 MD #1 2011/12

MD Wed – Sat Status 3.5.2011, 09:30 Day Time MD Wed 06:00 UPS repair, ATS optics checks w/o beam 12:00 Cycle, test ATS optics w/o beam 16:00 0.45 TeV: BPM offset determination for triplet BPMs Thu 00:00 0.45 TeV: Alignment TCDQ/TDI and injection losses (other beam) 08:00 0.45  3.5 TeV: RF single-bunch instabilities 14:00 Ramp down, cycle. 0.45  3.5 TeV: 90 m optics unsqueeze Fri Ramp down, cycle 02:00 0.45  3.5 TeV: Cross calibration of BSRT/WS/BGI 10:00 0.45 TeV: Collision tunes at injection + ramp down, cycle 20:00 0.45 TeV: Beam-beam limit Sat 04:00 0.45 TeV: Investigation on CODs 05/05/2011 MD #1 2011/12

MD Sat – Mon Status 3.5.2011, 09:30 Day Time MD Sat 10:00 0.45 TeV: ATS (including cycle to new injection settings) 20:00 0.45 – 3.5 TeV: Nominal collimation, single bunch tune shift 04:00 Ramp down, cycle Sun 06:00 0.45 TeV: RF multi-bunch instabilities 0.45  3.5 TeV: Coupled-bunch instability rise times 18:00 0.45  3.5 TeV: Quench test in the DS of IR7 Mon Technical Stop Lost 6h 3.5 TeV: Tune scan – beam-beam optimization, lifetime, losses 05/05/2011 MD #1 2011/12

0.45 TeV: BPM offset determination for triplet BPMs I MD was successful (Jorg, Kajetan, Tobias) lot's of good data was collected. The MD started eventually around 18:00, but the first 2 hours were spent to correct the beam parameters and to decide on how to handle the missing RQTF on B1. Finally the circuit was masked at the BIS level (PIC maskable) and the MD could proceed. When trying to flatten the orbit, 2 dumps were generated with the probes due to the fact that the injection protection was not re-centered like the TCTs around a flat orbit. We therefore kept on the Xing in IR2 (and also in IR8). If any other MD requires a fully flat machine, the beam must be injected with Xing, then the injection protection retracted and finally only the Xing in IR2 can be ramped down. In the end we had about 3 1/2 hours of efficient MD time. 05/05/2011 MD #1 2011/12

0.45 TeV: BPM offset determination for triplet BPMs II We took data from four quadrupoles: Q6.L5B2 Q6.L7B2 Q9.R6B2 QX1.L5 Preliminary analysis was done for Q6.L5B2 and Q9.R6B2 vertical: For Q6.L5B2 we found a very good alignment of the BPM with the quadrupole, while we found that the beam was off-center by -0.2mm, as indicated by the BPM. The preliminary analysis for Q9.R6B2 indicates an offset between quadrupole and BPM of 0.2mm, while the beam was really off-center by about 1.5 mm! 05/05/2011 MD #1 2011/12

K-Modulation Result I 05/05/2011 MD #1 2011/12

K-Modulation Result II 05/05/2011 MD #1 2011/12

Summary of TCDQ angle alignment and TI8 shielding MD I TI8 shielding studies (Chiara, Wolfgang, Annika): B2 use probe bunch opened all TCDIs to +/-15 mm for one after the other close left jaw to 3 sig across zero to dump beam on this jaw take 3 shots per collimator analysis to check shielding effect offline Completed successfully. 05/05/2011 MD #1 2011/12

Summary of TCDQ angle alignment and TI8 shielding MD II TCDQ angle alignment (Chiara, Wolfgang) B1 use probe bunch TCDQ maximum angle corresponding to 2mm discrepancy between up and downstream corner ==> 300 urad, due to LVDT noise we could apply 250 urad as a maximum angle. measure angle of TCDQ apply angle on jaw move jaw into the beam until the beam is completely lost repeat for different angles (0, +/-125urad, +250urad) the minimum in jaw position (from beam centre) gives the correct angle Stopped by problem with an SPS kicker. Not complete. 05/05/2011 MD #1 2011/12