EYETS 2016-2017 David Hay EN-OSS
Opening of the machine (weeks) 1470895 2.3 DRAFT Extended Year-End Technical Stop 2016-2017 References: 20 weeks beam to beam stop for CMS Ions run Proton-Lead References [1], [3] and [4] Machines Opening of the machine (weeks) not including the xmas break of 2 weeks Linac2 9.5 PSB 11.5 PS 13.5 SPS 11.5 (BA1,BA2) – 12.5 LHC 15 5 weeks
PS Booster Activities completed Activities in progress BWS False-floor 50% 75% 100% Activities completed Enlargement of the shaft (transport of the BT.BHZ10 magnet) ECR PSB-K-EC-0003 PSB injection BI.BVT power cables & cooling circuit POPS-B 6Kv cabling installation ECR PSB-LJ-EC-0008 Installation of new cable trays in BRF2 and BOR Civil engineering works to repair water seepage in the basement area. Activities in progress De-cabling project (ref Georgi’s presentation) Modifications to the MPS output filter ECR PSB-LJ-EC-0008 LIU & consolidation cabling (ref Georgi’s presentation) Replacement of the RF heat exchanger motors in periods 7 & 10L1 Installation of the distributed optical fibre radiation and temperature sensing (DOFRS) ECR PSB-EIOF-EC-0001 PSB BCER switchboard and containment Installation ECR PSB-LJ-EC-0005 BT.BHZ10 magnet BWS False-floor stabilization Cooling circuits BRF2 Water seepage repairs BR.TMD POPS-B 6Kv cables Shaft 09-Jan-2017 David Hay EN-ACE
Extended Year-End Technical Stop 2016-2017 1470895 3.0 RELEASED Extended Year-End Technical Stop 2016-2017 Machines From beam OFF to Hardware Tests (not including the xmas break of 2 weeks) PSB 12 PS 14 SPS 13 LHC 17 Require temporary powering: BTMS system racks RA776 and 778 in the BOR (20th February wk8) For the DCCTs (BRi.BCTDC9L1) commissioning; racks RA756 and 757 (BOR) repowered from the beginning of week 9 (27th of February wk9). Remise sous tension Racks PSB (6th March) VIC 2 (20th Feb)
EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016 PSB EYETS 2016-2017 Machine LIU Renovate electronics for 4 BR.BCTDC (section 9) On track. Now requires power to racks 756-757 (P. Odier) Vers PS Consolidation 4 BRi.BCTI8L1(8L1) On track. Modifs terminated (bg 867) ready to install transformers next week (P. Odier) New ring Trajectory Measurement System (PSB-TMS) On track. Now requires power to racks 776-778 in the BOR (J.Belleman) Remove unused cooling pipes EN-CV Start next week? PSB EYETS 2016-2017 New prototype wire Scanner BWS (4L1) On track. Pump down, small leak detected. New BLMs (FIC detectors) Clamps fitted ECR Needs approval New Tune pick-up BPM (3L1) Postponed. Exchange Septum SMH (15L1) Start week 10 New kicker KSW (16L1) Start week 8 Install upgraded BI.BCT10 transformers On track. Relocate Monitor BTV (BT.BTV30) On track. Enlargement of the shaft DONE EYETS Overview, Marzia Bernardini, LMC 2nd Nov. 2016
ECR’s
Thank You for listening. Q’s