EHN1 Extension planning Q. Bouirek / EN-EA 08/06/2017
H4 Beam line extension works EHN1_NP H4 Beam line extension works Quay construction delayed because of the coactivity Following activities must be postponed (supports, magnets, cooling connection, alignment, containment, cabling, etc) The goal is to allow EN-EL to work from September 2017 on the magnet cabling, i.e. Finish cabling before the YETS 2017/2018. Cabling + Cable trays installation Magnet installation : 1 month Support installation : 1 week Quai installation : 2 months Temporary access to the quay will have to be built. 08-06-2017
Infrastructure : Next steps EHN1_NP Infrastructure : Next steps EL/EL Second cabling from w25 to w29 ODH clean room Fire detection NP02 clean room Cryostat doors + access doors cabling Alarms + temporary alarms removal AUG Lighting BE/ICS Access control on the external doors ASAP Pit access doors Hall separation doors Quay + detector doors Fire detection + ODH installation EN/CV RIA commissioning next week 08-06-2017
EHN1_NP Metallic Structure 08-06-2017