Cesar Luongo Thomas Jefferson National Accelerator Facility

Slides:



Advertisements
Similar presentations
Zian Zhu Superconducting Solenoid Magnet BESIII Workshop Zian Zhu Beijing, Oct.13,2001.
Advertisements

GlueX Solenoid Recent progress and Coil cold tests Paul Brindza September 9, 2004.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
Progress on the MICE Cooling Channel Solenoid Magnet System
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
CASIPP Design of Cryogenic Distribution System for CFETR CS model coil Division of Cryogenic Engineering and Technical Institute of Plasma Physics Chinese.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Thomas Jefferson National Accelerator Facility Page 1 IPR October Independent Project Review of 12 GeV Upgrade Jefferson Lab October 18-20,
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Roberto Than CRYOGENICS SYSTEM.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
Magnet vacuum vessel w/radiation shield and cold mass in place Magnet leads (left) and the three cryocoolers on the top of the spectrometer solenoid service.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Installation of the T600 at Fermilab CSN2, September 22,
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Max-Planck-Institut für Plasmaphysik 1 ICEC 26- ICMC 2016 March 7-11, 2016, New Delhi, India Michael Nagel Cryogenic commissioning, cool down and first.
S A Griffiths CM42 June 2015 Electrical & Control.
SIS 100 Vacuum chamber Recooler String system Components
Final Design Cryogenic and mechanical configurations
Teleconf ACS – FREIA 28th March 2017
12 GeV Project Status Glenn R. Young 12 GeV Project Status
Installation of the T600 at Fermilab
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Status of the PANDA Solenoid Magnet Production in BINP
CBM magnet overview of the BINP work
Process Simulation for the LCLS-II Cryogenic Systems
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
Renuka Rajput Ghoshal John Hogan Ruben J. Fair Probir K. Ghoshal
FRIB Cryogenic Support
HFM Test Station Main Cryostat
Proximity Cryogenics P&IDs meeting
N. Hasan1, P. Knudsen2 and V. Ganni2
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
LARP Vertical Test Facility
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Status of the PANDA Magnet
Spectrometer Solenoid Fabrication Status and Schedule
Small Coolers for MICE MICE Collaboration Meeting RAL Michael A. Green
DOE/SC Status Review of 12 GeV SHMS HB Magnet: Update since Oct 2015
Mathew C. Wright October 2016
SHMS Cryogenics and Q2(Q3Dipole) Cool Down
Operation experience of cryogenic system and cryomodules for the superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf of Cryogenics.
Teleconference ACS – FREIA 20th February 2018
ILC Experimental Hall Cryogenics An Overview
Cryogenics – The Basics
Updated concept of the CBM dipole magnet
Cryogenics – The Basics
SNS Cryoplant Commissioning Past Experiences
as a prototype for Super c-tau factory
Cryogenic behavior of the magnet
Teleconference ACS – FREIA 19th June 2017
Cryogenics – The Basics
UPPSALA UNIVERSITY_GERSEMI PROJECT
Thermohydraulic behaviour of the cryogenic system
Presentation transcript:

Commissioning of the CLAS12 Torus Detector Magnet at Jefferson Laboratory Cesar Luongo Thomas Jefferson National Accelerator Facility Newport News, Virginia, USA G. Biallas, K. Bruhwel, R. Fair , P. Ghoshal, D. Kashy , S. Mandal, J. Matalevich, M. Mestayer, R. Miller, R. Rajput-Ghoshal , C. Rode, N. Sandoval, G. Young Thomas Jefferson National Accelerator Facility , Newport News, VA, USA 2016 Applied Superconductivity Conference Denver, CO, USA September 4-9, 2016

Outline Overview of Jefferson Lab and the Hall B-CLAS12 Upgrade The CLAS12 Torus Detector Magnet Coil Fabrication Magnet Installation Commissioning of the Torus Magnet Administrative Steps and Safety Reviews Phases of Commissioning Leak-checking and vacuum pumping Cooldown Magnet energization Field mapping

Jefferson Lab Located in Newport News, VA Pre-eminent Nuclear Physics accelerator facility in the USA 800 staff, 1400 users and collaborators from 30 countries $338M Upgrade from 6 GeV to 12GeV of the accelerator (SRF) along with 1 new Experimental Hall and 2 of 3 existing Halls being upgraded (2006-2017) (CD1 – CD4b) 8 superconducting magnets are part of the 12 GeV upgrade $70M Upgrade of Hall B includes the CLAS12 Torus Detector Magnet

CLAS12 Detector System

CLAS12 Torus in Hall B Distribution Box (DBX) – Feeds Torus and Solenoid Torus Cryo Service Tower (TST) Connection to Refrigerator Chimney (Cryo interface) Cryoduct (bus leads) ~ 10m Very thin coils/cryostats 6 coils electrically in series Conduction-cooled with SHe Coils hydraulically in series, re-cooled by counterflow 1 atm He in thermosyphon mode LN2 (shield) circuits also in thermosyphon mode Torus Magnet

Coil Fabrication Coils shipped from Fermilab were instrumented and cryostated (in assembly –line manner) at JLab. Cold-tested (80K) for thermal and insulation performance JLab provide conductor, Fermilab wound and impregnated the coils (6 + 2) MT-24: S. Krave et al. , “Overview of Torus Magnet Coil Production at Fermilab for the Jefferson Lab 12 GeV Hall B Upgrade, “IEEE Trans. Appl. Supercon. 26(4), 4102705, 2016

Installation Coils installed via “spit” (rotisserie) method Coils attached to spit hub one by one “Hex beams” attached and assembly rotated Method allows for all the coil-to-coil electrical and hydraulic connections to be made in a consistent (horizontal) position from the subway balcony Assembly can be rotated for welding VJ as needed MT-24: C. Luongo et al. , “The CLAS12 Torus Detector Magnet at Jefferson Lab, “IEEE Transactions on Applied Superconductivity 26(4), 4500105, 2016

Installation Installation complete ~ April 30, 2016 Applying MLI Splices between coils Welding the vacuum jacket Installation complete ~ April 30, 2016

Commissioning: Administrative steps and safety reviews Pressure System Review Internal JLab review (Engineering Division) to ensure all piping and vessel components comply with ASME codes (design, manufacturing, procurement, and documentation) Magnet and its Cryo service tower: March 24 Cryogenic Distribution System: May 24 Experimental Readiness Review (ERR) – Magnet Cooldown Internal/External review (Physics Division) to ensure all operating procedures have been prepared, reviewed, and approved. That there is a hand-over plan in place, and that all documentation is in order prior to transferring operational responsibility to Physics (hand-over) ERR Part I: April 13 ERR Part II: June 27 Final approval for hand-over to Physics (and release to start magnet cooldown): August 5 Cooldown ERR 1 Cooldown ERR 2 Power-Up ERR Pressure Review 1 Pressure Review 2

Vacuum P&ID Turbo (top) Single vacuum space Roots blower Turbo (bottom)

Commissioning: Leak Checking and Vacuum Pumping Pumping Port on TST Vacuum Instrumentation Rack Turbo Roots Blower

Commissioning: Leak Checking and Vacuum Pumping Leak-checking of internal circuits (He and N2) Leak-checking of vacuum jacket, plus fixes (feedthroughs, welds, etc.) Vacuum jacket completed in early May, leak-checking phase lasted ~ 6 weeks. Continuous pumping since mid-June. Decrease at ~ 10-7 Torr/hr An RGA was connected, most of pump-out was water (>85%) A de-watering strategy was devised and implemented Multiple pump-and-purge cycles (no apparent help) Run up to 10 A through the coils, maintain temperature < 325K (~320K) Flow warm N2 through the thermal shield circuits using the heated U-Tube (3 kW) and keep inlet temperature < 350K Once system was warm pumping speed increased 30-50% ROR tests done before and during warming cycle showed water release increased by a factor of 3 (accelerated de-watering) After ~ 2 weeks of warming cycle, pressure started to decrease Warming disconnected (but took another ~2 weeks for system to thermalize back to room temperature) ~ 0.5x10-4 Torr reached on all internal gauges after ~ 3 mos. of pumping

Commissioning: Leak Checking and Vacuum Pumping Pump-and-purge cycles Pressure in vacuum space (Torr) De-watering Cycle Start of Cooldown Days of continuous vacuum pumping

Cooldown: Simplified diagram of hydraulic circuits * Pressure Relief Valves Not Shown

Commissioning: Cooldown Cooldown proceeds by independently cooling the shields and the cold mass Shields are floating from each other and the cold mass, so they could potentially be cooled at any rate (as long as cold mass is not cooling too fast) Shield circuit is cooled by 80K gas, inlet temperature controlled by 3kW heater to adjust cooling rate Helium circuits cooled via warm helium “split” into two circuits, one of them running through heat exchanger in LN2 (80K). Fraction of “split” controls helium inlet temperature to cold mass Max allowable delta-T between coils and hex beams (supports) is 45 K Controls set to keep this delta-T to ~ 10 K (alarm at 30 K) Controls set so that cold mass cools at ~ -0.5 K/hr (alarm at -2 K/hr) N2 shield cooled independently consistent with above control actions After shields are below 100K, start introducing liquid nitrogen in shields After cold mass is at 80 K, switch cooling mode and introduce liquid helium into buffer dewar to continue cooldown process down to 4 K

Commissioning: Cooldown Status Cooldown started on Aug. 12 - Coils currently at ~ 180K Shield cooling starts Temperature (avg.), K Days since beginning of cooldown

Commissioning: Magnet Energization Magnet energization expected to start by mid to late September Step 1: Low current polarity and instrumentation checks. Inductance measurements Step 2: test of Fast Dump and QD from 500 A Step 3: Conditioning ramp-up to 3800 A with wait/evaluate at 3000 A

Commissioning: Field Mapping Field mapping expected to start in October Field quality requirements: ± 0.1% in toroidal direction, ± 1% in other two directions Mapper consists of temporary attachments (surveyed) and carbon fiber tubes with 3-axis hall probes and stepper motor translation Mapping of hub and in four locations across each sector (25 lines in total) Mapper shown accurate to within ± 0.01% Mapping to take ~ 1 week

Summary Magnet installation successfully completed in April 2016 A series of 5 safety and readiness reviews carried out in parallel to commissioning, all successfully passed Torus Magnet Commissioning Leak checks (internal cryo circuits and vacuum jacket) Vacuum pumping Cooldown (@ 180 K) Magnet energized (early October) Field mapped (mid October) Turnover to Physics (late October)

BACK-UPS

Torus Technical Parameters DESIGN VALUE Magnet Type Toroidal Field Geometry Number of Coils 6 Coil structure Double pancake Number of turns per pancake 117 Number of turns per coil 234 Conductor SSC outer dipole (36 strands) soldered in Cu channel Nominal current (A) 3770 Ampere turns 5.3E6 Peak Field (T) 3.58 Peak Field Location Inner turn near warm bore adjacent to cooling tube B-Symmetry 99.9% Bdl @ nominal current (Tm) 2.78 @ 5 degree , 0.54 @ 40 degree Inductance (H) 2.00 Stored Energy (MJ) 14.2 Warm bore  (mm) 124 Total weight (Kg) 26,000 Cooling mode Supercritical He with indirect conduction Supply temperature (K) 4.6 Temperature margin (K) Min 1.58 (@5.3 K) to Generation temperature 6.878 Turn to Turn Insulation 0.003” E-Glass Tape ½ Lap

Chronology of Torus CCM production, cryostating, and installation Coil in storage Coil installed in Hall B FNAL JLab Cryostat Factory Hall B 08/14 09/14 10/14 11/14 12/14 01/15 02/15 03/15 04/15 05/15 06/15 07/15 08/15 1 2 3 4 5 6 10 20 30 Weeks Coil # Evidence of Learning Curve From start of production at Fermi to Coil installed in Hall B: First Coil: 30 weeks Last Coil: 20 weeks While maintaining safety and quality

Torus Magnet – Coil + Cryostat Design 4K Cooling Tube ½” ID Shield Out of Plane Support Copper cooling sheets 0.050” total thickness (x2 sheets) Double Pancake Coil 234 turns 80K Cooling Tube 3/8” ID FNAL 6061 T6 Aluminum Heat shield 3.2mm thick JLab