LHC during week 45 LHC delivered ~0.837 fb-1 in week 45

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

(ATLAS) Higgs Prospects at HL-LHC. ATLAS CMS ALICE LHCb Center-of-Mass Energy ( ) 7 TeV Center-of-Mass Energy (Nominal) 14 TeV ? Center-of-Mass.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Status & Goals of LHC 1 1pb-1 of delivered and recorded luminosities reached! As of this morning: Delivered: 1420 nb-1 Recorded: 1245 nb-1 New record Inst.
J. Leonard, U. Wisconsin 1 Commissioning the Trigger of the CMS Experiment at the CERN Large Hadron Collider Jessica L. Leonard Real-Time Conference Lisbon,
Patrick Robbe, LAL Orsay, for the LHCb Collaboration, 16 December 2014
19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics.
E-CLOUD VACUUM OBSERVATIONS AND FORECAST IN THE LHC Vacuum Surfaces Coatings Group 03/07/2011 G. Bregliozzi On behalf of VSC Group with the contributions.
February 19th 2009AlbaNova Instrumentation Seminar1 Christian Bohm Instrumentation Physics, SU Upgrading the ATLAS detector Overview Motivation The current.
The SLHC and the Challenges of the CMS Upgrade William Ferguson First year seminar March 2 nd
M. Gilchriese ATLAS Upgrade Introduction January 2008.
SLHC SG: ATLAS Pixel G. Darbo - INFN / Genova SLHC SG, July 2004 ATLAS Pixel at SLHC G. Darbo - INFN / Genova Talk overview: A table with different High.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Ideas for Super LHC tracking upgrades 3/11/04 Marc Weber We have been thinking and meeting to discuss SLHC tracking R&D for a while… Agenda  Introduction:
Run 14 RHIC Machine/Experiments Meeting 6 May 2014 Agenda: Run 14 Schedule (Pile) Machine Status (Robert-Demolaize) STAR and PHENIX Status (Experiments)
August 24, 2011IDAP Kick-off meeting - TileCal ATLAS TileCal Upgrade LHC and ATLAS current status LHC designed for cm -2 s 7+7 TeV Limited to.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
Upgrade Intro 10 Jan 2010 Norman Gee. N. Gee – Upgrade Introduction 2 LHC Peak Luminosity Lumi curve from F.Zimmermann : Nov Upgrade Week ? ?
Introduction to L1Calo Upgrade L1Calo Collaboration Meeting Cambridge 23-Mar-2011 Norman Gee.
Sundry LHC Machine Development starts 19 June –Original plan to have 90m comm. next week was torpedoed by private discussions between spokesperson and.
14 Aug. 08DOE Review John Huth Future Harvard ATLAS Plans John Huth.
29 October 2015 B. Di Girolamo. B. Di Girolamo – Collider-Experiments Day – 5 th HiLumi Annual Meeting 2 Collider-Experiments Interactions There is a.
Run 14 RHIC Machine/Experiments Meeting 24 June 2014 Agenda: Run 14 Schedule (Pile) Machine Status (Robert-Demolaize) STAR and PHENIX Status (Experiments)
An Idiot’s Guide to LHC Upgrades Bohr Lunch Seminar. 16/5/08 Terry Wyatt. University of Manchester.
CERN’s Large Hadron Collider
First collisions in LHC
Fabio Follin Delphine Jacquet For the LHC operation team
Operating IP8 at high luminosity in the HL-LHC era
Detector status and commissioning: LUCID
The CERN Physics Programme
TC activities.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
Machine-Experiment Interface
Machine Coordinators: G. Arduini, J. Wenninger
Beam-beam effects in eRHIC and MeRHIC
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Francesco Forti University and INFN, Pisa
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
14 paesi, 62 universita’ e laboratori
Monday 11/07: Recovery Plenty of accesses.
Thursday 09:30 VdM scan for CMS, standard ADT gain.
Real-time orbit the LHC
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
Summary of Week 16 G. Arduini, J. Wenninger
Scrubbing progress - 09/12/2012
First Beam in the LHC September 10, 2008 in the ATLAS control room.
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Wire almost entirely through beam before BLM triggers dump
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Summary Tuesday h23: Machine closed. Precycle started.
Monday 27th August & night
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Saturday 10:00: Cryo Pt8 back, starting the pre-cycle.
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
Saturday 26 November 2011.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

LHC during week 45 LHC delivered ~0.837 fb-1 in week 45 In total: 20.4fb-1 54 hours of downtime (32%): Cryo Pt 8 ~24 hours. ‘Recovery’ after injector TS & MD ~ 16 hours. SPS flooding ~16 hours. Injection line steering 6+ hours. SPS dump kicker ~4 hours. ALICE ~4 hours. Dump reasons: ATLAS weekly meeting 13.11.2012 Dominic Hirschbühl Bergische Universität Wuppertal

ATLAS Issues LAr FE cooling problem BCM side A noise: still present 2nd pump connected, running continously Access granted twice this week for visual inspection. Intervention during an appropriate moment is considered and discussed. Toroid needs to be off. BCM side A noise: still present noise hunting efforts not successful so far Inclusion of BCM into abort logic and injection permit: after a discussion with BCM, ID, and RC, it was decided to include the BCM again in the abort logic and injection permit will be done after approval of the machine protection panel, likely in two weeks VdM scan request: ATLAS requested a VdM scan early next week (exact time to be confirmed) at beta*=11m, with improved beam conditions (more gaussian tails). CMS will join the scan. Will take ~3 shifts (including setup time) Details to be finalised in the coming days. RPC firmware test with unstretched hits in the trigger requested 40k events for trigger studies in view of 25ns running to be discussed: whether one can use the CMS VdM scan (one trigger configuration, only pre-scale changes). Danger: impact on HLT? ATLAS weekly meeting 13.11.2012 Dominic Hirschbühl Bergische Universität Wuppertal

As per design, the water cooling circuit operates below atmospheric pressure to prevent damage to irreplaceable (and inaccessible) front-end electronics, should a small leak develop. Underpressure is maintained by a vacuum pump which runs briefly whenever the pressure exceeds 0.62 bar; and until the pressure has been brought back down to 0.60 bar. Partial power off of FEB HEC:L1 2nd vacuum pump installed

Schedule No changes w.r.t. to Schedule presented last week ! vdM? No changes w.r.t. to Schedule presented last week ! ~20 days of pp-physics data taking left to go (=3 fb-1?) Magnets: LAr FE cooling: if it is decided by LAr to intervene, we plan to switch off the toroid during MD4 and scrubbing in order to maximise chances for an access during a possible longer downtime of the LHC (e.g. cryo). During MD4: bring down toroid and solenoid for ~1 day for thermosiphon crane handling ATLAS weekly meeting 13.11.2012 Dominic Hirschbühl Bergische Universität Wuppertal

25 vs 50 ns "ATLAS arguments for running with 25 ns bunch spacing after LS1,“ 6/11/2012, ATL-COM-UPGRADE-2012-035: https://cdsweb.cern.ch/record/1484651 These public notes are not intended for journal publication or for submission to the arXiv. This document will form the basis of discussions w.r.t. future LHC running options. This note compares the implications for ATLAS of running the LHC after Long Shutdown 1 (LS1) with 25 ns or 50 ns bunch spacing. For the same instantaneous luminosity, 50 ns spacing gives twice the event pileup per bunch crossing, leading to higher detector occupancy, more combinatorics in the inner detector and higher pileup noise in the calorimeters. The implications for readout bandwidth (in particular for the Inner Detector), trigger, computing and physics are discussed. For all these reasons, ATLAS strongly prefers LHC operation in 2015–2017 at 25 ns from the beginning, both to maximise the utility of the initial 13–14 TeV data samples, and as an essential step on the path to future high luminosities of 2–3×1034 cm−2s−1 and beyond. The same arguments also apply for the period between LS2 and LS3, before the Phase-II tracker upgrade.

This week: Hadron Collider Physics conference First update on Higgs after July discovery announcement and paper

Next week is ATLAS Upgrade week Milano involvements in Phase0 and Phase1. Today: IBL, FTK Phase2: First draft of note "Letter of Intent for the Phase-II Upgrade of the ATLAS Experiment" ATL-COM-UPGRADE-2012-040: https://cdsweb.cern.ch/record/1491186 This will be submitted to the March LHCC and be publicly available at that point. From around 2022, the HL-LHC will operate at a nominal instantaneous luminosity of 5x1034 cm-2 s-1, around twice the expected Phase-I luminosity, with the aim of delivering an integrated luminosity of 2500 fb-1 over ten years. The increased instantaneous luminosity results in the number of interactions per event increasing from 55 to 140, assuming a beam crossing time of 25 ns