CEBAF Accelerator Status

Slides:



Advertisements
Similar presentations
12GeV Project CD-4 Leigh Harwood Associate Project Manager Accelerator Systems.
Advertisements

Chris Tennant Jefferson Laboratory March 15, 2013 “Workshop to Explore Physics Opportunities with Intense, Polarized Electron Beams up to 300 MeV”
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Dark Current Measurements and Simulations Chris Adolphsen 2/4/15.
Thomas Jefferson National Accelerator Facility Page 1 23 rd Annual HUGS Program June 2-20, 2008 CEBAF Overview HUGS08 June 3 CEBAF Overview HUGS08 June.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
J-PARC Accelerators Masahito Tomizawa KEK Acc. Lab. Outline, Status, Schedule of J-PARC accelerator MR Beam Power Upgrade.
Welcome to Jefferson Lab R. D. McKeown Jefferson Lab Hypernuclear Workshop May 27, 2014.
BIA’s Director Review, September Accelerator Improvements FY11-16 Fulvia Pilat.
Experience with LEP (and LHC) cryo-modules Workshop on cryogenic and vacuum sectorisations of the SPL O.Brunner – November ’09.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Jefferson Lab Overview Bob McKeown April 20, 2015.
Thomas Jefferson National Accelerator Facility Page 1 SPL Cryogenic and vacuum sectorisations 9-10 November, 2009 Joe Preble Workshop on cryogenic and.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Jonathan Creel Electrical / Cryogenics Engineer Cryogenics.
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
Modeling SNS Availability Using BlockSim Geoffrey Milanovich Spallation Neutron Source.
Science and Technology Briefing Sept
SRF Operating Experience at JLab
Dark Current and Radiation Shielding Studies for the ILC Main Linac
Cost Optimization Models for SRF Linacs
Introduction Six-Month Follow-Up on Action Items of Feb 2016 CEBAF Field Emitter Workshop Rongli Geng September 12, 2016.
Preliminary Review of LERF as Cryomodule Testing Facility for LCLS-II
Field Emission Minimization for LCLS-II
Cryomodule test stand at ESS site
Jefferson Lab Overview
Process Simulation for the LCLS-II Cryogenic Systems
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
Partial Warm-Ups at CLS
Online Helium Inventory Monitoring of JLab Cryogenic Systems
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Jefferson Lab Reliability Task Force and Initiatives
CEBAF Injector Update PREX/CREX March 3-4, 2017
SNS Operational History
CEBAF Accelerator Status
R&D Activity for Field Emission and Vertical EP
Operational Experience - Field Emission
ESS RF Development at Uppsala University
Regular cryomodule maintenance plans (radiation damage, seals, etc)
Accelerator status after the 12 GeV upgrade
Cost Optimization Models for SRF Linacs
Introduction to Jefferson Lab
C75 Risk Assessment Geoff Krafft
Operations Department
Mathew C. Wright January 26, 2009
Electron Source Configuration
Operations Department
Thoughts on Energy Reach
C75 Commissioning Michael Drury SRF Operations Support
Strategy for operation and recovery of performance at SNS -Background -History of performance -What is our operational strategy -Performance recovery.
Performance Recovery at CEBAF
SNS Cryoplant Commissioning Past Experiences
Outline: Recent CEBAF performance JLAB-TN-022 Energy Reach Plan
CTF Users’ Perspective
Ken Baggett JLab Staytreat, 2017
StayTreat Wrap Up OPS 2015 StayTreat.
Extraction Michael Bevins May 17, 2007
Field Emission and Mitigation in the CEBAF Linacs R Legg, R Geng Jlab SRF Ops Dept. TTC,
JLab Users Organization Annual Meeting June 24, 2019
Comparison between 4K and 2K operation performance of CEBAF injector cryomodules Grigory Eremeev Monday, August 19, 2019.
C100 Operation Enhancing gradient reach for the
Electron Collider Ring Magnets Preliminary Summary
SNS-PPU upgrades the existing accelerator structure
Summary of the maximum SCRF voltage in XFEL
Presentation transcript:

CEBAF Accelerator Status Arne Freyberger Operations Department Accelerator Division Jefferson Lab

Outline Accelerator Management Changes FY17 Accelerator Operations Fall 2016 Spring 2017 Optimizing 12GeV Operations Reliability/Availability Energy Reach FY18 3+ Hall Operations Summary

Accelerator Division Leadership On April 30 Andrew Hutton stepped down as the head Accelerator Division ~10 years as Division Leader Prior to assuming the Division Leadership, Andrew was Director of Accelerator Operations for ~15 years. Commissioning of 4 GeV CEBAF Ramp up to 6 GeV Recovery post-Hurricane Isabel Fulvia Pilat has assumed the role of Acting Division leader until the completion of the search for the new Division leader Fulvia has also accepted the Director of the Research Accelerator Division at SNS and will assume this position in Fall 2017.

Fall 2016 Accelerator Operations Hall A (1,3,4,5 passes, 70 uA) & Hall-D 5.5 passes Linac Energy: 1050 MeV/linac Commission 5th pass separator Validate improvements made over the Summer 2016 Compact Geometry (+9%) Increase RF power (+10%) Changes validated! Vacuum leak in one of the cavities immediately following commissioning rained on the parade

Fall 2016 Accelerator Operations Availability Challenges Arc7 Box Supply choke failure Unable to support beam beyond 4th pass, required a change in program. One of 12 new large box power supplies Design flaw in estimating heat generated in choke Klixons install on all chokes Infant mortality issue SRF Warm Poly Window failure Required thermal cycle to repair and clean beamline vacuum (one-week lost time) End-of-life issue Replacing all Poly windows this summer with ceramic South Access Main 1 Feed issues Persistent ground fault, jumpered out

Spring 2017 Accelerator Operations 2+ Hall Operations Hall-D 5.5 passes (first production run of GlueX) Hall-B&C @ 3-pass (KPP) Hall-A 1-pass Linac Energy: 1050 MeV/linac Commission 5th pass separator (AGAIN, after vacuum repair) All Good! Hall-D received the majority of its beam using 5th pass separator 5th pass separator operated week(s?) without a trip. Hall-B and C KPP complete! End of beam related 12 GeV Project activities 3-hall operations with two high current halls (A&C) established

Availability Challenges Low energy running for PRad Peak Month to date

Cryogenic Status Spring 2017 run was going well up to March 9th 2017 CHL1->SC1 tripped off in the evening Recovered and tripped in the early morning of March 10th Cold Compressor 5 (CC5) inoperable post 2nd trip.

Cryo: CHL1->SC1->CC5 Update 2017-05-02: Broken wire on magnetic bearing connector was found.

Optimizing 12GeV Operations Reliability/Availability Focus Improved Linac/Cryogenic changes: Reduce risk of cryoplant contamination Linac LHe Pressure Identifying errant magnets 4-Hall Operations Energy Reach Linac energy setting: margin -> reliable operations Identifying source SRF Particulate Cleaning/processing warm girder regions Improved in tunnel vacuum procedures C75 Upgrade

Reducing Risk of Cryoplant Contamination Contamination in the LHe volume migrates to the heat exchangers (HX) in the 2K cold-boxes (SC1 & SC2) Spring 2015 and Spring 2016 contamination events Takes weeks to warm-up and recover Source of contaminants likely from numerous cryomodule connects and disconnects from the sub-atmospheric system. HX Since Summer 2016 new procedure for connecting/disconnecting systems from the LHe supply Linac must be transitioned to 4K atmospheric before connecting or discconnecting systems Fall 2016 and Spring 2017 no contamination events

Optimizing 12 GeV Operations: SRF/Cryo LHe Pressure: Higher operating pressure -> less stress on 2K cold-box compressors ~2milli-atm of pressure margin availabe All CC spin reduced CC4: 552 Hz -> 532 Hz

Optimizing 12 GeV Operations: Optics The 2R Optics Anomaly Optics matching consistently required MQA2R02 quadrupole set 30% off design. Detective work by Tiefenback identified MQA2R09 quad as problematic Confirmed with magnet coil resistance and pole field measurements

Optimizing 12 GeV Operations: 4-Hall OPS Laser table upgrade completed Summer 2016 750 MHz 5th pass separators completed/commissioned Spring 2017 Laser RF controls completed April 2017 System pieces are complete Full integrated system tests this Fall

Energy Reach CEBAF C20 RF trip rate is a function of cavity gradient Well modeled by Linac Energy Manager with frequent cavity parameter updates from Benesch Operations requires sufficient gradient margin so that emergent problematic cavities do not derail the program (CEBAF down hard) Margin of 60 MeV/linac at the start of each FY Provides enough margin to deal with entire C20/C50 cryomodule Determine Energy setting that results in 8 RF trips/h from C20 modules (assume C50/C100 contribute another 2 trips/h) Subtract 60 MeV/linac from this value to determine the maximum linac energy gain allowed. Elinac < E8trips/h - 60 MeV

Energy Reach Linac Energy that would result in ~ 10 trips/h

Optimizing 12 GeV: Search for new Field Emitters Source in Cryomodules New field emitters on SRF surface results in degradation of operational gradient. Historical average of the loss is ~34 MeV/pass/year A hunt for the source of the new field emitters has been ongoing (led by Geng, Reece, & SRF) Detailed surface analysis has been performed on the last two modules removed from LERF/CEBAF Particles as large a 1 mm found Metallic dominates: Steel, Copper Particulates found on cavity and warm region surfaces

Particle Type Distribution Cavities Beamtubes btw cavities 18

Beyond Particulate: Condensed Hydrogen on Cavity Surface Condensed Hydrogen on cavity and wave guide surface can acerbate field emission Perhaps source of C100 excessive quench signatures: Waveguide discharge due to H2 Analysis vacuum levels vs Temperature of C100 warm-up consistent with H2 being release Levels consistent with H2 desorbed from the warm region Additional reason for upgrading the warm region pumps R-L. Geng TN-17-027

Improved Tunnel Vacuum Procedures and Warm Region Pumps Particulate found on SRF cavity and warm region surfaces likely sourced in the warm region between girders. New procedures have been put in place to try to minimize particulate generation and migration New portable clean rooms constructed New particle counters purchased and used to establish proper clean room conditions prior to exposing beamline vacuum to air Clean-room attire used inside the clean room. Warm regions that connect to refurbished cryomodules (C50s) are processed/cleaned by SRF prior to connecting to the fresh C50 C50/C75 upgrades now include modern ion/neg pumps for increased pump capacity and less particulate generation

C100 Field Emission induced Radiation Damage Experience radiation damage in C100 warm girder regions Vacuum systems in particular: random valve closings Installing lead collars on C100 exits to minimize the damage Does not protect the cryomodule, C100 lifetime at risk See George K. presentation at 2016 OPS StayTreat

C75 Plan Comparable in scope to C50 program post hurricane Isable Proposed path to design energy (1090 MeV/linac) Comparable in scope to C50 program post hurricane Isable If annual degradation is mitigated: might achieve 1090 MeV/linac by FY21

Fall 2017 and beyond Cryogenics situation still fluid, but… planning for a 2K operations on two cold-boxes by Sept. Beam operations resume first week in Oct (start of FY18) 3+ hall operation Linac Energy: 1050 MeV/linac Challenges include: 4-hall operation for the first time Expect lower availability First time two beam for physics through the same slit First use of the vertical separators for simultaneous 5th pass beam to A, B or C Fully loaded linac currents: May push the old compromised klystrons over the edge There are 50+ klystrons showing end-of-life symptoms

Summary 12 GeV Experimental program established Hall-A: GMp completed (Hall-A), schedule portion of DVCS completed Hall-B: PRad completed, HPS engineering run Hall-D: First production run Spring 2017 12 GeV beam related activities completed Hall-B KPP Hall-C KPP Accelerator Operations continues to dial in 12 GeV performance Combined effort with CASA, SRF, Engineering, Facilities Availability Challenges Remain New systems issues: Box supplies, magnet buses End-of-life issues: SRF Window failures, SC1 2K cold-box Performance Plan (JLAB-TN-17-022) Lack of critical spares End-of-life issues and obsolescence

Backup

CEBAF Performance Plan (JLAB-TN-17-022)

Performance Goals

Performance Plan Cost Estimate

4-Hall Operations and Beam Availability Hall lines contribution to CEBAF Beam Availability. High current halls tend to have higher rate of MPS (BLMs, Ion Chambers, BLA) faults More invasive beam tuning for the supported halls. Expect 10% less Beam Availability for 4-Hall OPS In terms of Physics hours, 4-Hall ops out performs 3-Hall operations MPS/tuning Impact to a Hall Physics-per-week 1-Hall Ops 0.97 2-Hall Ops 0.94 1.88 3-Hall Ops 0.90 2.7 4-Hall Ops 0.87 3.5