(Selected) Project Management Processes at the XFEL

Slides:



Advertisements
Similar presentations
CLIC Energy Stages D. Schulte1 D. Schulte for the CLIC team.
Advertisements

EC Review – 01/03/2002 – G. Zaquine – Quality Assurance – WP12 – CS-SI – n° 1 DataGrid Quality Assurance Gabriel Zaquine Quality Engineer - WP12 – CS-SI.
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
NORWEGIAN SOCIAL SCIENCE DATA SERVICES MADIERA Project Management.
SuperB. SuperB has been approved as the first in a list of 14 “flagship” projects within the new national research plan. The national research plan has.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
Introduction Riko Wichmann, XFEL Project Office (XPO) XFEL Technical Reviews.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
1 Tunnel implementations (laser straight) Central Injector complex.
Lesson 1: Examining Professional Project Management Topic 1A: Identify Project Management Processes.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Energy Stages D. Schulte1 D. Schulte for the CLIC team.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
ESS | title of presentation | 2012-xx-xx | name of presenter Roles and Responsibilities sub title.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014.
Agenda ESS Schedule Objectives and Current status Overview/Introduction Tools and Process ESS integrated master schedule Milestones.
19Jul06 Vancouver GDE meeting 1 S2 Task Force Status (String test definition) Tom Himel.
Collaborating for Quality through the Project Quality Plan Matthew Conlon ESS ACCSYS QA/QC Quality Learning & Planning.
Project Management & Project Management Software
Project Management Jukka A. Miettinen September 4, 2006
MicroTCA Development and Status
AMICI WP1 – Management, coordination and dissemination
Strategy and Status of Reference Cavities for European XFEL
SCT Project Management Issues
Project Management Chapter 3.
Installation Global System
DataGrid Quality Assurance
WP-X XFEL Project Progress Report (2016-3)
Software project mgt. session # 3– lab manual.
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
E-XFEL Status and First Beam Results
ICEC/IMC 2016 Sergiy Putselyk DESY MKS
WP-X XFEL Project Progress Report (2014-3)
EDR HLRF Work Packages Draft Summary
EFREMOV INSTITUTE SAINT PETERSBURG RUSSIA
Hosting Orsay Walid KAABI
Planning Phase: Project Control and Deliverables
WP02 PRR: Master Oscillator and RF Reference Distribution
Copyright Scott Bloss, All rights reserved.
ART-Review Schedule, Strategies and Conclusion
WP02 PRR: Master Oscillator and RF Reference Distribution
Racks Coordination 16 September 2011 E. Negodin
for X-ray Optics and Beam Transport
Hyper-V Cloud Proof of Concept Kickoff Meeting <Customer Name>
WP02 PRR: Master Oscillator and RF Reference Distribution
LLRF Functionality Stefan Simrock How to edit the title slide
MS Project Web Access to WP Plan
WP Coordinaten XFEL RF Operation
WP02 PRR: Master Oscillator and RF Reference Distribution
Markus Hüning 3rd XFEL Collaboration Meeting
Guidelines and Template for project oral presentation
Mastering Change Control
Guidelines and Template for project oral presentation
Product Development Scenario Overview
Software project mgt. session # 3– lab manual.
IS&T Project Reviews September 9, 2004.
Project Management Process Groups
EU-XFEL summary of performance degradation
Electron Beam Systems ETC and Methodology
Cryomodule Performance in FLASH and XFEL
Modified Beam Parameter Range
by Sven Mohr DESY D5 – Occupational Safety and Evironmental Protection
European Spallation Source ERIC
Conventional Facilities
Executive Project Kickoff
Hans Weise, DESY February 5th, 2019
SNS-PPU upgrades the existing accelerator structure
Summary of the maximum SCRF voltage in XFEL
Presentation transcript:

(Selected) Project Management Processes at the XFEL Riko Wichmann, DESY XFEL Project Office How to edit the title slide Upper area: Title of your talk, max. 2 rows of the defined size (55 pt) Lower area (subtitle): Conference/meeting/workshop, location, date, your name and affiliation, max. 4 rows of the defined size (32 pt) Change the partner logos or add others in the last row.

XFEL User Facility under Construction 2008-2017 Length 3,4 km total tunnel length ca. 6 km Depth 6 – 38 m Start user operation Q2/2017 6 experimental station 550 m Undulatoren 3,4 km 2 km LINAC in SC RF Technologie pulse duration: ~ 10 - 100 fs up to 27000 pulses/s Wave length 5  0.04 nm Ebeam=17,5 GeV Status: tunnels are completed, above ground under construction series fabrication of all components in full swing general infrastructure installation in full swing (staged) machine installation began 2013 with injector

Underground Civil Constructionffinished all 5.8 km of underground tunnels are completed

Series Production of Components in Full Swing

Scheduling Process: XFEL Project Structure: Work Packages plan, execute & report

Roles and Responsibilities Project Board joint project management of XFEL GmbH and DESY technical and organizational decisions with the scope of the project roles and responsibilities described in XFEL project handbook and sublementing documents [ … ]

Planning Process: The Challenges distributed planning approach with in-kind contributions bottom-up project planning by work package leaders ~50 work package plans with often strong dependencies XFEL Project Office (XPO) to maintain overall schedule Challenges: maintain overall consistent project plan over ~8 years maintain dependencies between WPs (transparent & traceable)‏ track schedule development provide reporting platform

The XFEL Project Plan Landscape XFEL Global Schedule Plan (GSP with TLM) start / end IS installation start / end machine install. Top-Level Milestones (TLM) start/end comm. first beam etc TLM Work Package Dependency start / end IS installation start / end machine install. start / end fabrication technical reviews etc. PIT XCS RfI RfI … WP-x1 WP-x2 WP-x3 WP-x4 WP-xn RfI: Ready for Installation PIT: Project Installation Timeschedule XCS: XFEL Commissioning Schedule [ … ]

WP Dependency Schedule (WPD) 14 WP Dependency Schedule (WPD) no direct links between WP plans WPL is responsible for the WP schedule / update avoid automatic WP schedule shift by the system schedule adjustment is a controlled & moderated process Work Package Dependency Plan WP-x Mx1 current: 15.04.12 approved: 15.04.12 WP-x Out-going milestones Mx1 current: 15.04.12 WP-y Incoming milestones Myx1 approved: 15.04.12

general structure identical for all XFEL project plans Work Package Plan planning and reporting processes are supported by the XFEL Project Management System (MS Project Enterprise) WPD  schedule information for the WP WPD: WP Dependency plan GSP: Global Schedule Plan PIT: Project Installation Timeschedule schedule information provided by the WP  WPD  GSP  PIT general structure identical for all XFEL project plans incoming milestones, WP activities, outgoing milestones

Project Integration Time Schedule (PIT) general structure identical for all XFEL project plans incoming milestones, PIT activities, outgoing milestones PIT: structured in facility section defines installation windows for the different trades / components

Project Internal Reporting Process 3x3 aproach: 3-tier process running 3x a year Tier 1: Update of project plans in the XFEL PMS % complete on tasks and miletstones shift un-finished tasks into the future (ref. status date) “general” update / refinement of tasks and schedule Tier 2: generate a written status report from plan 3 weeks before reporting meeting (tier 3) start consolidation of the over schedule WP representative can “digest” status info before reporting meeting

Reporting Process: Status Report

Project Internal Reporting Process 3x3 aproach: 3-tier process running 3x a year Tier 1: Update of project plans in the XFEL PMS % complete on tasks and miletstones shift un-finished tasks into the future (ref. status date) “general” update / refinement of tasks and schedule Tier 2: generate a written status report from plan 3 weeks before reporting meeting (tier 3) start consolidation of the over schedule WP representative can “digest” status info before reporting meeting Tier 3: status presentation in reporting meeting 2 day meeting: 10 minutes presentation presentation template follows status report reports by WP leader and the PM team

Reporting Process: Reporting Meeting

Schedule Monitoring Process not to scale! Construction: with fabrication and assembly Installation Commissioning RfO Monitored by the XFEL Project Board XFEL Global Schedule Plan (GSP with TLM) Work Package Dependency Schedule (WPD) PIT XCS Monitored via the WP Status Reports Work Package Plans RfO: Ready for Operation PIT: Prioject Installation TimeSchedule XCS: XFEL Commissioning Schedule

Schedule Monitoring Process: Consolidation of Schedules after every status update (3x per year) before the project progress reporting meeting based on auf WP Dependency Plan and Global Schedule milestones beyond the internal WP scope in case of delays: reason proposal of possible counter measures, effects on overall schedule and other WPs eventually acceptance of new schedule by members of the Project Board

Schedule Monitoring Process: Consolidation Global Schedule last date accepted by Project Board current date from WP schedule

Summary main PM processes for XFEL defined and documented in a project handbook main emphasis: roles and responsibilities planning process reporting process review based engineering process planning and reporting process: supported by the XFEL Project Manage- ment System