UTILITY DESIGN SERVICES OLD KINGS ROAD North Widening UTILITY DESIGN SERVICES
BACKGROUND Approximately 3.3 miles Modify roadway from a 2-lane roadway to a 4-lane divided roadway Modify and add limited turn lanes Provide 8’ wide paths on both sides of road Replace existing strain pole traffic signal with a new mast arm
PROJECT LIMITS PALM COAST PARKWAY FOREST GROVE DR
TYPICAL SECTION
PROJECT SCHEDULE Design Phase Currently 90% Complete Utility Conflicts Have Been Identified Anticipate 100% Complete in FY17 Right-of-Way Phase Additional Property/Easements have been Identified Property Appraisals have begun Construction Phase No Funding Allocated City Continues to Pursue FDOT funding as a TOP Priority Project
COUNCIL ACTION Approve Change Order with DRMP for: Utility Design Services Fee Amount of $200,000
Questions? Palm Coast Pkwy includes Old Kings Rd and Cypress Point Pkwy