Sector 002 Assembly status report

Slides:



Advertisements
Similar presentations
Filter Changing Procedures For TEOM Series 1400ab and Model 8500 FDMS (B & C Types)
Advertisements

1 Ann Van Lysebetten CO 2 cooling experience in the LHCb Vertex Locator Vertex 2007 Lake Placid 24/09/2007.
Manchester 09/sept/2008A.Falou & P.Cornebise {LAL-Orsay}1 CALICE Meeting/ Manchester Sept 2008 SLAB Integration & Thermal Measurements.
P. Béné, F. Cadoux, A. Clark, D. Ferrère, C. Husi, M. Weber University of Geneva IBL General Week - 11, 12 February 2010 IBL Stave Loading Status Summary.
Design Ash finished electric hybrid tracing to connector fields –Changes to allow for HCC-less and HCC running on one hybrid awaiting final confirmation.
Assembly Procedure ALICE Outer Barrel Stave 14 Module 2 Cold Plates 1 Stave.
ATLAS IBL Tool for gluing flex on omega C.Bault/FX Nuiry - IBL Stave Meeting - UniGe August 31st Process description This tool has been designed.
STEAM HEATING.
S Temple CLRC1 End-cap Mechanics FDR Cooling Structures Steve Temple, RAL 1 November 2001.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
21/01/02 - ECAL Cooling - Arnaud Hormiere ST/CV 1 Development of ECAL COOLING PLANT Application to a Super Module.
Hybrid Integrated Circuit
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
Back up stave test program status Eric VIGEOLAS Pixel week December 2000 Pre production status Assembling phase comments Geometrical control Stave Qualification.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
M. Gilchriese Disk Geometry January 18, M. Gilchriese 2 ATLAS Coordinate System.
M. Gilchriese Module Assembly and Attachment at LBNL M. Gilchriese for F. Goozen April 2000.
Silicon /pcb assembly R Thompson, J Freestone LAL 3 June 08.
Manchester Qualification M-O-048. Mechanical dummy. Check that tuning of alignment parameters had correct sign and adjustment of transfer chucks Z was.
Optical surveys: sensors for the upgrade Adrian Bevan, Karen Hayrapetyan, Camillia Messiouni 1.
WP6 meeting 30/07/2013. Status of flex prototypes production New laser soldering tests Discussion on mass production schedule.
CMS FPIX Cooling System Studies Joe Howell, Fermilab for the FPIX Upgrade Mechanical Working Group CMS Upgrade Workshop April 27,
Assembly Procedure ALICE Outer Barrel Stave 14 Module 2 Cold Plates 1 StaveMarco Kraan Paul Kuijer.
Strip Stave cores Stephanie Yang ATLAS upgrade Oxford activities, January 2015.
WP6 status report A. Di Mauro (CERN) ITS plenary meeting
K.W. Glitza University of Wuppertal IBL Stave (Lessons for Upgrade)
Loading stave 4000  Receiving test of modules : No problem despite some damages at one edge of few modules (AMS) One MCC failure in one module, reworked.
WP7&8 Progress Report ITS Plenary meeting, 10 June 2014 LG, PK, VM, JR.
Pixel upgrade test structure: CO 2 cooling test results and simulations Nick Lumb IPN-Lyon MEC Meeting, 10/02/2010.
S Pyatt 1 UV glue dispensing studies on the Dima Dotmaster Glue gap checks.
Stave #12 This stave core was built together with William Emmet, Tom Hurteau, and Jeffery Ashenfelter from Yale University in the week of November.
Stave Tooling & Plans for Future Stave-building (Tim)
VEA’s proposal of automated assembly system WP6 meeting, 16/01/14.
DOE CD-2/3a Review of the BTeV Project – December 14-16, BTeV Pixel Detector Pixel Module Assembly and Half-Plane Assembly Guilherme Cardoso James.
Eric Vigeolas, July the 3 rd Status The IBL detector construction already started and the components assembly (flex, modules, stave loagin) will.
Progress on Stave assembly tooling Stephanie Yang (Oxford) WP4 meeting at Liverpool University, 13 th November 2014.
FP420 Hybrid Mechanical Design Ray Thompson / Manchester Manchester Xmas O7 Ray Thompson Julian Freestone, Andy Elvin.
Origami and Cooling 24th September 2012 C. Irmler (HEPHY Vienna) Joint PXD and SVD Meeting Göttingen.
SVD QCG Report F.Forti. Outline Sep 09, 2015QCG Report, F.Forti2 view/Detector/SVD/SvdQCQAGrou p.
1 IST development status  Seattle  Composite Design.
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Thoughts about PS module assembly Ulrich Heintz, Meenakshi Narain, Bill Patterson, Eric Spencer, Juan Trenado Brown University, Providence 4/16/2015Heintz,
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Infrastructure & issues and solutions for ATLAS Upgrade Hybrid/Module strip bonding Fred Doherty, Joe Ashby, Fiona McEwan & Calum Gray ATLAS Upgrade Module.
BM&N STS ladders assembly in VLHEP
Feedback on transfer line sizing and flow calculations for UT
ATLAS pixel module assembly flow
Micro Vertex Detector of PANDA Status of Strip BARREL and DISC
Cryomodule test stand at ESS site
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
Glue curing studies (contd)
Ladder Assembly All tools and jigs produced Glue dispensing works
Module Loading Task Force Meeting October 21, 2004
new straw end plug: D=10.6 mm straws support frame Levan option
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Ladder Assembly All tools and jigs produced Glue dispensing works
Status of straw production straw module assembling
Endcap shielding senarios:
Gluing jigs for Demonstrator
Equipment for Assembly – UK Experiences
UV glue dispensing studies
ATLAS Upgrade Module Bonding Trials Using Glass Asics
Determining the Empirical Formula of Magnesium Oxide
Module/Ladder Assembly
“Lesson – Installing Material Cartridge and Printing a File”
GLAST Large Area Telescope:
Pixel module assembly tooling
as a prototype for Super c-tau factory
Bunker Wall Design Wall ESS
Presentation transcript:

Sector 002 Assembly status report Module loading task force meeting 25 May 2004

Contents Sectors Glue 3-D Survey Other sector 2 Results Tool Upgrade Procedure Upgrades C6F14 Cooling

Sector Sector 001 (FE_I1, prototype) had been assembled in 2003 with most of the final tooling, but not final glue procedures. It was never fully characterized. Sector 002 is our pre-production sector (FE-I2.1). It has been loaded with 3 module so far using “production” tooling and glue. Some revisions to the tooling and the procedure are now being implemented, reacting from the experience of loading the first side. Side 2 will be loaded when all the upgrades are in place. These are incremental small changes. We are not going off in any new direction.

Glue Implemented CPPM standards with a few adaptations specific to sector Our dispenser is calibrated to 16 drops/ minute Had some problems getting fresh glue- long lead time. Now have too much fresh glue. Implemented new storage method when new tubes are opened, take out each component and mix well Transfer immediately to individual, very cheap, 3cc syringes for storage (store 2cc in each syringe) when mixing, empty each syringe out completely into cup. This gives 1-1 by volume. Do this on scale to control that it matches 1-1 by weight, which it does for fresh glue to good accuracy.

Glue (cont.) Implemented glue drop mask which works very well. Dispensing takes 10min. /module, which is acceptable Quantity dispensed is 4 drops in outer hole + 3 drops in inner hole (16 drops/minute with CPPM syringe and needle) 80% chip area coverage (gap is 75um set by fishing line).

3-D Survey A 3-D survey program has been implemented. It only works on side 1 of a sector due to interference with the cooling pipes. Sectors 1 and 2 have been measured (see next slide) Both sectors show out-of-plane modules with a small systematic tilt and with some modules bowed. We suspect the tilt is an imperfection of the tool head- deviations in the steel pins for example. The bow as well as some random tilts are due to lack of degrees of freedom in the pickup chuck to deal with module-to-module changes in how the module “hangs” from the flex.

3-D Survey (cont.)

Other Sector 2 Results 3 modules have been loaded so far (1 side) 2 modules are within 20 microns of nominal (all alignment marks) 1 module has 2 alignment marks off in x-y by 100um (x+y in quadrature) The cause is understood to be (1) operator error and (2) lack of procedure to prevent such an error. New assembly checklist now safeguards against this error. Quick electrical test shows no digital problems in 3 modules loaded No cooling test until 6 module loaded.

Tool Upgrade Extreme case of tilt in module placement shown by glue pattern on chips Adding +/- 200um of independent vertical adjustment to each vacuum cup

Procedure Upgrades New step-by-step checklist. Check each item off for each module loading operation. Vacuum chuck planarity calibration procedure using glass slide on deposition site (need adjustable cups first for this).

C6F14 Cooling Closed circuit C6F14 loop operation demonstrated with dummy sector with heaters. 0.2m2 heat exchange area to chiller bath implemented with coil.

C6F14 Cooling (cont.)