Test CERN Marta Bajko CERN

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

1. 2 LHC consolidation: tests completed in 2010 Projects completed in 2010 Test facility consolidation Where are we now? Planning Foreseen Activities.
Sc Magnet test facility Consolidation Project presentation M. Bajko for the TEMB on behalf of the MSC TF section team 31. Aug
Booster Main Bending Magnet Test in SM18. Why The energy upgrade of the PS Booster main bending magnet requires endurance tests at high current (≈12 kA)
SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing &
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
2 Technical seminar - 5 th June 2014 Vincent Roger - TE-MSC-TF.
Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
HQ02b : Test plan overview Test plan overview: Main elements and Open questions H. Bajas TE-MSC-TF H. BAJASUpdate meeting on HQ02b assembly and test plan02/05/2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
HL-LHC/LARP, QXF Test Facility Workshop– R. Carcagno QXF Test Requirements Ruben Carcagno BNL Workshop December 17, 2013.
HOW THE DUMP RESISTOR’S TANK LOOKS LIKE COOLING OF THE LHC ENERGY EXTRACTION RESISTORS G. Peón (ST/CV), K. Dahlerup-Petersen, G. Coelingh (AT/MEL) Air.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
CERN Rüdiger Schmidt FCC week 2015 Long Magnet Stringpage 1 Incident September 19 th Architecture of powering and protection systems for high field.
ISTITUTO NAZIONALE DI FISICA NUCLEARE SEZIONE DI MILANO LABORATORIO ACCELERATORI E SUPERCONDUTTIVITA’ APPLICATA Magnet Test LASA, INFN-Milano.
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Readiness of test stations for design validation Marta Bajko on behalf of the TE-MSC TF team CERN, 11 th December 2014 QXF design review, CERN.
5 th Joint Hi-Lumi LHC-LARP Annual Meeting 2015 SC Link Protection A.Ballarino 28/10/2015.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
AT-ACR B. VULLIERMECSOC Meeting 29 September Cryogenics for LHC Test Benches Safety Aspects Overview of the Test Station Overview of the Operation.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Magnet R&D for Large Volume Magnetization A.V. Zlobin Fermilab Fifth IDS-NF Plenary Meeting 8-10 April 2010 at Fermilab.
XVII SuperB Workshop and Kick Off Meeting - La Biodola (Isola d'Elba) Italy May 28 th June 2 nd 2011 P.Fabbricatore Sezione di Genova The air core magnets.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
CHATS-AS 2011clam1 Integrated analysis of quench propagation in a system of magnetically coupled solenoids CHATS-AS 2011 Claudio Marinucci, Luca Bottura,
WP10 General Meeting, Giovanni Volpini, CERN 1 December 2015 Test progress INFN 1.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
SIS 100 Vacuum chamber Recooler String system Components
Final Design Cryogenic and mechanical configurations
Power Supply and Energy Extraction System for the CBM magnet
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
HL-LHC IT STRING and Series test of SC link
MQY-30 Test Result Report
Marta Bajko X EUCARD2 Annual Meeting Malta 2016
HFM Test Station Main Cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.
EPFL-SPC, 5232 Villigen PSI, Switzerland
Magnet Test Stands at Fermilab
SPS cryogenic proximity equipment and SM18 validation
Powering the LHC Magnets
Hollow e- lens, Cryogenic aspects
ACCESS to magnet testing facilities
Circuits description and requirements - Closed Session-
ESS RF Development at Uppsala University
EN-ICE Technical Committee SM18 activities & projects
Status of studies on FCC magnet circuit architecture and protection
Block 4 and Cluster D - Safety
Power Supply and Energy Extraction System for the CBM magnet
TEST PLANS for HL LHC IT STRING
Jeremy Weiss & Danko van der Laan Chul Kim & Sastry Pamidi
High Magnetic Field Lab, CAS
ILC Experimental Hall Cryogenics An Overview
MQY as Q5 in the HL LHC era Glyn Kirby MQY 001 bat 927.
as a prototype for Super c-tau factory
Thermohydraulic behaviour of the cryogenic system
HL-LHC Long term behaviour of magnets Test facility limitations
News from the FNAL test facility
Power Leads for Test Stands
Review Bloc 4 and SM18 facilities and upgrade
Presentation transcript:

Test stand @ CERN Marta Bajko CERN 1st International Workshop on Superconducting Magnet Test Facilities @ CERN 13th-14th of June 2016 https://indico.cern.ch/event/507584/

Content Magnet test stand layout @ CERN Vertical cryostats : on-going upgrades HFM Cluster D Horizontal test benches: on-going upgrades Cluster A Cluster E Associated facilities upgrades Summary and conclusions Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Magnet test stands layout @ CERN THE SUPERCONDUCTING MAGNET TEST STAND AT CERN in SM18   CLUSTERS F E D C B A STRING and SC LINK LN2 TEST ZONE CRYOGENIC ZONE Superconducting RF CAVITY TEST ZONE HORIZONTAL BENCHES Is located in a building of 7200 m2 over which the test stands for magnets occupies about 50%. INSTALLATIONS 3 vertical cryostats, 1 feed-box for supercritical He, 1 cryostat for LN2, 10 horizontal benches OPERATION I= 0.12 kA-20 kA T = 1.9 K to 70 K He withstanding U = 1kV to 3 kV Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Magnet test stands layout @ CERN INSTALLATIONS 3 vertical cryostats , 1 feed-box for supercritical He, 1 cryostat for LN2, 10 horizontal benches OPERATION I= 0.12 kA-20 kA T = 1.9 K to 70 K He withstanding U = 1kV to 3 kV Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Vertical test stand upgrade Cluster G Cluster D The vertical cryostats zone, called Cluster G is about 400 m2 . It is under upgrade with an extra space called Cluster D of 150 m2 . It will accommodate the test of larger diameter magnets @ higher operating current for HL LHC. Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster G upgrade CRYOGENIC FEED BOX FOR He 4.2-80 K “HFM” CRYOSTAT for MAGNET TESTS WITH Φ 1500 mm and 2.5 m length PRE-COOLING WITH He GAS AND QUENCH BUFFER FOR COLD He RECOVERY 20 kA POWER CONVERTER with EE and DUMP RESISTOR The circuit is distributing current towards vertical cryostats orto the feed box via a commutator “DIODE/LEAD” CRYOSTAT @ 4.2 K “LONG” CRYOSTAT : 3.8 m long and Φ 600 mm @ 1. 9 K “SIEGTAL” CRYOSTAT 1.4 m long Φ 800 mm @ 1.9 K Ref. HFM cryostat is financed by EUCARD and the WP19 task of HL-LHC Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Vertical test stand upgrade Cluster D Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster D test stand CRYOSTAT : 4.8 m LONG AND Φ 800 mm @ 1. 9 K EE and DUMP AT THE 2 m LEVEL POWER CONVERTERS30 kA AT GROUND LEVEL PREPARATION ZONE AT 0 AND -3 m LEVEL -10 m -3 m 0 m 2 m 5.5 m ELECRICAL AND CRYO-RACKS NEAR THE CONTROL ROOM TWO ODH ARE IN THE -3 m ZONE ( mostly justified by presence of N2) CONTROL ROOM NEAR THE CLUSTER NEW OVERHEAD CRANE ALLOWS HADLING 25 t AND UP TO -3 m LEVEL COLD He RECOVERY BUFFER - 10 m3 at 5 bar, UNDER THE WORKING AREA IN CONFINED SPACE Integration by A.Kosmicki Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

CLUSTER D: electrical circuit EL CIRCUIT PARAMETERS Max stored energy 10 MJ Short Sample current 21.5 kA Magnet inductance 8.27 mH/m Nominal Ramp Rate 11 – 20 A/s Max Ramp Rate 200 A/s Max current 30 kA Max EE voltage 1 kV Reaction time : < 10 ms DESIGN DRIVEN BY: cost reduction and operation optimization implying the use of two existing 15 kA power converters for the new circuit Ref. H. Thiessen, C. Giloux, G.J. Coehling, P. Viret Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster D : energy extraction DESIGN DRIVEN BY : Reaction time < 10 ms, which implied the use of IGBTs THE 30 kA SWITCH IS MADE WITH TWO 15 KA UNITS EACH COMPOSED BY A MODULE OF 7.5 kA EACH UNIT OF 15 kA IS EQUIPPED WITH A DUMP RESITOR FOR 5 MJ DESIGN GOLAS FOR BUS BARS Equal paths for all currents Equal impedances Compact and cold: (T max 110 °C and 80 °C on junctions) Ref. G.J. Coehling, A. Dinus, K. Petersen Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster G and D: cryostat and insert USE OF CRYOGENIC BUFFER FOR COLD He DESIGN DRIVEN by optimization in operation Minimizing time and risk at hydraulic connection Minimizing the loss of He after quench INSERT DOES NOT HAVE ANY CRYO LINE CONNECTION CRYOSTAT PARAMETERS (Cluster G/D) Max internal pressure : 5 bara Magnet temperature : 1.9 K Useful diameter : 1500 / 800 mm Useful length in 1.9 K bath : 2.5 / 5.2 m Max. thermal gradient : 50 K Magnetic measurements: yes Estimated lifetime : 20 years Number of thermal cycles : < 1000 Number of Quenches : < 10000 Ref. Cryostat: A. Van De Craen, M. Struik Cryogenics: V. Beda, A. J. Lee Insert: M. Strychalski, P. Viret Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster G and D : WCC and Current Leads CONVENTIONAL GAS COOLED Cu LEADS: length: 1.7 - 2.1 m top flange Φ 260 - 280 mm connection : SC cable DESIGN DRIVEN BY Optimization in operation : Flexible cables Current lead operation homogenized with the rest of the test stand and minimizing the flow 500 mm2 CABLES SECTION Water Cooled Cables SPECIFIED PARAMETERS Current: 5 kA DC Max in. temperature: 28 °C. Pressure in operation: 16 bar. Maximum delta T: 10 °C. Water speed : < 2.5 ms-1 Max. temperature : 50 °C. Operating Voltage: 1 kV (if fault to ground) He vapor flow @ 4.2 K: 20 kA lead: 0.87 g/s 30 kA lead: 1.82 g/s 15 kA lead: 0.88 g/s Current Leads SPECIFIED PARAMETERS Main circuit: 20 kA / 30 kA Secondary circuit: 15 kA Design pressure : 5 bara Max. Voltage to GRD: 3.5 kV Ref. WCC: C. Gonzalves Perez Current Leads: S. Gianelli, P. Moyret Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster DAQ system Data Analysis with DIADEM DAQ SPECIFIED PARAMETERS Example of HF system DAQ SPECIFIED PARAMETERS Input channels: +/- 10 V analog Nr of HF channels: 200 differential HF frequency: 200 kHz HF,MF,LF resolution: 16 bit resolution HF,MF,LF accuracy: 1 mV MF frequency: 50 kHz Nr of LF channels: 144 LF frequency: 1 kHz Timing: GMT synchronization Data Analysis with DIADEM Ref. DAQ: H. Reymond, M. Charrondiere, M. I. Tapani Analysis: H. Bajas, F. Gomez de la Cruz Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Cluster D in pictures Ref. Construction: H. Botella, R. Morton, E. Perez Duenas, Safety: E. Paulat Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Horizontal test bench upgrade Cluster A Cluster E The horizontal test zone Cluster A to F excluding D is composed by 10 benches. They are equipped with 5 independent electrical circuits allowing to test magnets up to 15 kA @ 1.9 K. Two clusters are planned to be upgraded to 20 kA capacity. Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Horizontal test bench upgrade Cluster A The UPGRADE is DRIVEN by HL-LHC needs: Cluster E Magnet weight: 25 tonnes Operating temperature: 4.2 K and 1. 9 K Max. Operating current: 20 kA, 2 x 2 kA Max. Pressure in the magnet in case of quench: 20 bars Max. Test voltage: 3 kV Magnet weight: 25 tonnes Operating temperature: 4.2 K and 1. 9 K Max. Operating current: 15 kA, 2 x 0.6 kA Max. Pressure in the magnet in case of quench: 20 bars Max. Test voltage: 3 kV Target for prototype test: 90% ISS ≤ 20 kA Target for series test : 108% Inom = 17.8 kA Cluster E will have the same characteristics. Foreseen later. Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Facilities Upgrade Remarks CRYOGENIC COOLING PRODUCTION: + 35 g/s LHe UPGRADE DRIVEN BY The recommendation enabling to carry out the full test programme with no contraints For 2019 CRYOGENIC COOLING PRODUCTION: + 35 g/s LHe Needs essentially for HL-LHC IT STRING run in parallel with magnet testing DEMINERALISED WATER PRODUCTION: + 150 m3/h Needs for demineralised water entirely coming from magnet operation HANDLING: 25 t and longer rope Needs for overhead crane entirely coming from magnet operation nCONTROL ROOM Needs to extend the small control room of the vertical . Test facility to be used also for horizontal benches and Sc link Operational Operational For mid 2016 Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Marta Bajko for the TE TM June 2016 SM18 2020-2022

Thank you for your attention Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Spare slides on Facilities upgarde Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Test stands : cryogenics upgrade An additional 35 g/s liquefier (thus bringing the total production capacity for LHe at 4.2 K to 60 g/s) The existing total pumping capacity in SM18 at 1.8 K is 12 g/s, combining the capacity of WPU1 and 2. If need for IR STRING a dedicated 3rd WPU shall be installed. Foreseen for 2019 Ref. L. Serio Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Test stands : demineralized water production The demands for the magnet test stations, including the IT String, will rise to a peak of 1.7 MW (142 m3/h). At present SW18 houses a demineralised water station with a thermal capacity of 800 kW limiting the operation to two test stands Operational from April 2016 Ref. A. J. Broche Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

Test stand : HADLING upgarde To enable insertion of test objects into the HFM cryostat the operating height, must be increased to 6 m (presently 5.3 m). Cluster D, on the other hand, will be deeper than the existing vertical facilities. To handle the inserts the operation depth between the hook and the top of the cryostat must be increased to 9.3 m. Ref. R. Rinaldesi 25 T HANDELING CAPACITY WAS KEPT Operational from February 2016 Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities

New Control room Foreesen for Jul 2016 The motivation to build a new control room is driven by: Safety and Working conditions CONTROL ROOM AT THE PROXIMITY OF THE CRYOSTATS CONTROL ROOM WITH LARGER SPACE Foreesen for Jul 2016 Ref. M. Charrondier Marta Bajko for 1st International Workshop on Superconducting Magnet Test Facilities