October 2004 Through September 2005

Slides:



Advertisements
Similar presentations
East Hampton High School July 2013 – July 2014 Design Phases.
Advertisements

Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
OUTSOURCING INDUSTRIAL WASTEWATER TREATMENT Jerzy Kołłajtis – Magda Trybuch –
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
CON 4003 CVE 4073/5073 The Estimating Process Prof. Ralph V. Locurcio, PE.
9/17/07 ILC Detectors 1 Conventional Utilities Tom Lackowski.
Alderman Road Residences Phase II Design Build. Extensive master planning preceded this phase 2003 – Dagit Saylor Master Plan Hanbury Evans Update.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
ESTIMATING By Laith Jacob.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
CONVENTIONAL ELECTRICAL TDR DESIGN Randy Wielgos March 22, 2012 ILC CFS Baseline Technical Review.
Module 6/7: DPR (Detailed Project Report) & EPC (Engineering Procurement Construction)
Process Engineer’s Role in Project Management Dr Abdullah Malik.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
Implementing and Managing a Maintenance Plan The Maintenance Plan Ken Henman.
© 2010 Chevron A Day in the Life of a Project Manager Presented by Nancy Grossman, Project Manager Presented to Chabot College Engineering Class September.
Report from GG5, Dec. 20, 2005 Report from ILC GG 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
BASICS IN IRRIGATION ENGINEERING 2.1. Planning Irrigation systems 2.2. soil-plant-water relation – over view 2.3. Crop water requirement 2.4. Base, delta.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
CON 4003 CVE 4073/5073 Construction Cost Estimating Class #2: The Estimating Process Prof. Ralph V. Locurcio, PE.
PROJECT PHASES ACT Objective To provide an understanding of the design & construction process and the roles of the different participants in this.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
STRUCTURAL ENGINEERING. What Does a Structural Engineer Do?
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
Unit 18: CADD in Construction Lesson Objective Be able to explain the use of Building Information Modelling in buildings.
Role of PM in Airport Projects.  What constitutes a Successful Airport Implementation Programme?  Should the Process of Design and Construction of Airports.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
3/20/11 ALCPG11 Global Design Effort 1 CFS Detector Hall Considerations Tom Lackowski.
April 5, 2005 PPD Informal FLARE Review T. Lackowski 1 FLARE Conventional Civil Construction.
Chapter 3 Facility Design and Construction. Chapter Objectives 1.Describe the process of facility design and construction 2.Demonstrate proficiency in.
Procurement of Professional Services.  Professional Services:  Architects, Engineers  Surveyors  Geotechnical engineers  Nonprofessional Services:
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
Construction Tender Process Tender steps between Client, Contractor and Subcontractor Dr A Kimmance.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
SWT Construction partnering
Container Freight Station, Utilities and Drainage at Bayport Container Terminal (RFQ-148) Brenda Trevino, P.E. Project Manager October 11, 2016.
U.S. Air Force Cooperative Agreement for Perfluorinated Compounds Response Activities Jayne Joy, P.E. February 9, 2017.
2016 SAME Small Business Conference - Atlanta
Conventional Facilities and Siting Global Group (ARCFS)
Light Rail Transit Project
BIM EXECUTION PLANNING PROCESS
Procurement Management
Change Management V.N.Bhaskar Rao Engineering & Construction Director Amec Foster Wheeler India Operations.
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
$150K Chicago/ANL seed funding for Braidwood site investigation
Case Road Sewer Joe Mouawad, P.E. October 27, 2016.
EDR HLRF Work Packages Draft Summary
ILC PROJECT ENGINEERING DESIGN REPORT CFS Europe – KICK OFF MEETING
The Life Cycle of a Project – START to FINISH
9/18/2018 Bids CONTRACTING Khamis…..
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Quality Management Systems – Requirements
How to Build a Great Team
BIM EXECUTION PLANNING PROCESS
Outsourcing: Managing Interorganizational Relations
1 Stadium Company Network. The Stadium Company Project Is a sports facility management company that manages a stadium. Stadium Company needs to upgrade.
Far Experimental Hall Hutches Civil Construction
Controlling Project Cost and Schedule
Far Experimental Hall Hutches Civil Construction
MULTISPORTS CENTRE PRESENTATION
Richland Creek Water Supply Program Program Update
JLEIC Accelerator R&D Meeting
Honoraria for Design Build Projects Methodology Assessment Matrix
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Post Point Treatment Plant Resource Recovery Project Update
Presentation transcript:

October 2004 Through September 2005 Order of Magnitude Scope and Cost Estimate for a Design-Build Contract Package for the Braidwood Theta 13 Experiment October 2004 Through September 2005

Background Proposed as an engineering scope needed to prepare a Design-Build bid package for tender in the Fall of ‘05 Order of magnitude estimate based on: Regional geologic data sets (no site-specific data) An allowance for Electrical/Mechanical finish-out Excludes studies of detector hoisting/transportation needs Excludes cost for additional site investigation work The overall process outlined is consistent with principles-of-practice set-out for Design-Build Contracting: US Design & Build Institute and US Guidebook “Design-Build Subsurface Projects” Redpath Engineering Handbook

Braidwood Design-Build Design Scope Underground Design Scope 2 Vertical Shafts 2 Sump Chambers 2 Detector Chambers and connector tunnels Surface Design Scope Utility Runs Fenced/Gated Platforms Industrial Assembly Buildings Note: Under Design-Build Delivery Format Layout, Requirements & “Baseline Design” by Owner-Designer Final Design-Build by Contractor

Why Design-Build? Faster and potentially cheaper. However, Key that owner requirements be defined early in process: Owner commitment needed to avoid after-bid scope growth (build margin into scope to cover scope creep / experiment uncertainties) Early focus on development of a well-defined set of requirements that gives bidding contractors maximum design flexibility…. Leave detailed design and construction to Contractor Contractor knows best how to manage/use local labor, methods, means and materials most cost-effectively Additional Onus on Owner to select a good contractor and oversee the work (design reviews/approvals, QA inspections etc..) Greater potential for owner and contractor to work together (longer-term, less adversarial relationship with fewer intermediaries) but great reliance on contractor competence

Proposed 2004-2005 Activities Rough timeline for accomplishment of the main engineering and procurement tasks: October - February Selection/Tasking of Design Contractor(s) Fix Experimental Design Requirements for D-B Contract Start Engineering and Procurement Tasks… January - June Engineering Activities: Geology/Geotechnical, Civil/ Structural, Electrical, Mechanical (Budget/Schedule Input) Budget/Schedule Baseline Developed Procurement Activities: Pre-Qualification, Bid Package Preparations

Geology & Geotechnical Engineering Tasks ~ $75k Geologic/Geotechnical Characterization of: Ground units Ground water tables and unit permeabilities Viable options identified, baseline design developed Excavation Methods Rock Support Systems (Bolts, Shotcrete..) Water Control Systems (Grouting, Drain Systems..) Layout Optimization Develop Outline Specifications Meetings, reporting, reviews, contract documentation etc..

Civil/Structural Engineering ~ $50k Surface Platform Requirements and Baseline Design Work Platforms & Buildings Utility Runs and Access Roads Etc.. Underground Shaft Lining Requirements and baseline Design Soil and Rock Units Equipment Mountings.. Invert/Floor Requirements and baseline Design Drains, Rails, Equipment Mountings.. Outline Specifications Meetings, reporting, reviews, contract documentation etc..

Electrical Engineering ~ $25k Power and Communications Electrical services Enclosure normal/emergency lighting, outlets, cable trays, sump systems, grounding, include technical space needs for electronics (DAQ) Distribution system requirements (transformers, distribution panels, underground ducts, grounding, and raceways) Fire detection systems Emergency generator system(s) Outline specifications Meetings, reporting, reviews, contract documentation etc..

Mechanical Engineering ~ $25k HVAC Load calculations Fire Protection code review, system parameter selection and associated diagrams Groundwater Pumping Drain, sump, pump system layouts and associated diagrams Other Utilities water, gas, sanitary, as required Spatial layout of (equipment/ducting/piping..) Outline Specifications Meetings, reporting, reviews, contract documentation etc..

Drafting ~ $75k General Design Criteria (scale-approximate “schematics”) Title Sheet, Location Plan, Notes and Legend Design Criteria (Near & Far Sites) Surface Layout and, Shaft, Tunnels and Chambers Design Drawings (scale-accurate) General Existing conditions and road/utility runs for Near Site & Far Site Underground Space Envelopes and Elec/Mech Finish-Out Surface Platform/Road Footprints, Utility runs, Building Envelopes and Elec/Mech Finish-Out Electrical/Mechanical Drawings (line diagrams) HVAC and electrical systems Meetings, reporting, reviews, contract documentation etc..

Schedule/Cost ~ $25k To Support the Construction Proposal and Project Planning Cost Estimate Methodology Cost Estimate/Schedule Quantity Take-Offs Equipment Selection Crew Sizes/Make-ups Production Rates Schedule Risk Analysis Etc.. Contingency Setting

Other Costs ~ $50k Environmental Safety and Health Land Survey Initial evaluation and findings/recommendations Contract ES&H requirements and permitting Contractual ES&H instruments to ensure compliance Additional site investigation needs and monitoring Land Survey Site layout Access routes Meetings, reporting, reviews, contract documentation etc..

Project Management & Contract Administration ~ $75k Inter-Agency Coordination Plant Owner, Funding agency(ies), Owner’s Representative Management agreement(s) Coordination of Engineering Reviews Constructability and Value Engineering Reviews Work-in-Progress and Proposal Reviews Contract Administration Procurement & Execution Plans (ref. other projects, DBI format) Contract Development/Formatting/Assembly Contractor Selection - Pre-qualification Project Controls Establishment (Cost, Schedule, Risk.. Tracking) Meetings, reporting, reviews, contract documentation etc..

Cost Summary ~ $500k (with 25% Contingency) $25k increments - don’t want to give the impression that this is anything but an order of magnitude estimate ($25k represents ~1 senior engineering-month, or ~2 junior engineering-months) $75k Geology/Geotechnical $50k Civil/Structural $25k Electrical $25k Mechanical $75k Drafting $25k Schedule/Cost $50k Other Costs $75k Management/Administration/Bid Package Preparation (Design shown in basis of estimate is straightforward - there should be design duplication between near/far site so costs could go down but at this point in time think the above numbers provide a reasonable starting point) Contingency ~ 25%

Summary It is assumed that the work will get us to a point where the contract can be approved and bid: Adequate up-front engineering ($500k ~ a 25% design level) Ensure that bidding contractors know what is required Support funding decisions Upfront engineering by a “design contractor” with firsthand tunneling experience (builder-led with access to PE/SE). Design progress should be documented/reviewed by other qualified bidders so that “design contractor” does not get a bidding advantage. Final permit/design work will be done by Design-Build Contractor. Additional tasks may be required to comply with agency requirements (e.g. added documentation, planning and/or review cycles etc..). The budget may need significant adjustment depending on the disposition of partners. Suggest that we discuss internally and with our partners before writing a formal proposal.