Building H0209A (G007) (GAP Thorsten Ziglasch, Ina Schurig) Current Status Activities Communication
Overview Building Cable Planning CPS and UPS Air- and Water Cooling Radiation Shielding Other Building Aspects Organization Aspects
3D model Building H0209A
E20 (3D)
E20 with Racks
E20 including racks (2D)
E10 (3D)
E10 including racks (3D)
E10 including racks (2D)
Building H0209A
Cable Planning All data is specified by the WPLs includes starting point (component) ending point (power rack) cable type and cable class connectors electrical current and voltage thermal energy many other special requirements
Cable Database
Cable Database
Cable Database
Cable Database
Cuts for cable trays & surveying
External Cable Planning
Internal Cable Planning
CPS and UPS WPLs provided their requirements for CPS and uninterrupted power supplies UPS All data ist collected to be able to combine the requested modules with the aim to limit the amount of CPS and UPS units process is still ongoing
Air- and Water Cooling
Radiation Protection E10
The Balcony
Cut Through The Balcony
Radiation Protection E20
Other Building Aspects
Other Building Aspects
Organizational Aspects WPLs define: Change Requests for all relevant changes No direct communication with the external planners – communication is done via FAIR S&B or Marianna Frech (Drees & Sommer) every 2nd week „Technik AG“ to discuss general issues concerning buildings & machines cables electrical power & heat loss data technical gases nomenclature of components # of IT-network plugs and telephones