Process Air Compressor Knockout Replacement

Slides:



Advertisements
Similar presentations
The second generation of IGCC Power Plants. Problems and solutions.
Advertisements

Commissioning Approach Integrated Service Solutions
Refrigeration Systems
Fundamentals of Pressure Relief Devices
Setup/Installation/Operation of an Environmental Control Unit (ECU)
What is a centrifugal pump?
3.4.6 Student Book © 2004 Propane Education & Research CouncilPage Maintaining Bulk Plant Compressors Knowledge of the processes involved in maintaining.
Gas Transmission Pipelines
HEATING AND AIR-CONDITIONING
Objective : To understand the fabrication, design, installation welding, inspection and testing for new construction in oil and gas industry After followed.
2013 NATEF Task Area A-7 Heating, Ventilation, and A/C A. A/C System Diagnosis & Repair B. Refrigeration System Component D & R C. Heating, Ventilation.
MOST RELIABLE COMBINATION MASTER VALVE, WATER METER AND FLOW SENSOR
Where We Go Wrong - With Compressors Dick Hawrelak Presented to ES-317y in 1999 at UWO.
Section 1 Dr.Hoda’s part Sheet 1: Calculating equipment cost Eng. Reda Zein.
Clark Reliance Corporation Strongsville, OH. Fuel Gas Treatment.
Forging new generations of engineers. Basic Pneumatics.
Propylene Production from
January 4, 2007 RHIC II Project Internal Cost Review Gary McIntyre RHIC Ring Modifications January 4, 2007 Project Overview.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Done by: Esraá Hajjeyah Supervised by: Prof. M.Fahim Eng. Yusuf Ismail.
Introduction to Energy Management
CENTRIFUGAL PUMPS:- DESIGN & PERFORMANCE Ir. N. Jayaseelan 2012.
L.J.INSTITUTE OF ENGINEERING AND TECHNOLOGY compressors Shah Aadishkumar Aileshbhai (enrollment no ) (div A roll no. 55) Guided by Mr.hemangsir.
7 A/C System Components, Operation, and Service.
Government Engineering College Bharuch(014). Sub: Instrumentation And Process Control. Topic: Displacement float,Pneumatic balance and Magnetic level.
Production Engineering II
Fluid Mechanics for Chemical Engineers Arif Hussain (Lecturer)
ARÇELİK TİCARİ KLİMA EĞİTİM DÖKÜMANI APPENDIX.
REFRIGERATION SYSTEMS Er. Gagandeep kaur Associate Prof., Electrical Engg. PTU Giani Zail Singh Campus, Bathinda. Id:
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
CHE441 Lecture: Tank & Vessel. Introduction of Vessel Applications of Vessels:  (1) as a liquid surge drum for liquid storage  (2) as a vapor/liquid.
Automotive Heating And Air Conditioning
GROUND SERVICING OF VARIOUS SUB SYSTEMS
Advisor: Dr. Shangchao Lin
Introduction to Mechanical Engineering
GROUND SERVICING OF VARIOUS SUB SYSTEMS
2K Cold Box FDR Introduction
Advanced Post Graduate Program in Piping Design & Engineering with PDMS & CAESAR-II
Automotive Engines Theory and Servicing
PHOTO GALLERY Study Guide in PowerPoint to accompany Thermodynamics: An Engineering Approach, 7th edition by Yunus A. Çengel and Michael A. Boles.
System Diagrams Symbol Library – Black Background David Sellers
IT-4189 Supply and installation of a cryogenic distribution system
GOVERNMENT ENGINEERING COLLEGE, BHAVNAGAR TOPIC : INTRODUCTION TO PRESSURE VESSELS Prepared By :- 1.Aal Akash Ansari Aarif.
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Chemical Engineering Drawing
Overview of Mechanical Design
Heating Ventilating and Air Conditioning
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Piyush Modi Assist.Prof
Cooling technology Main components and equipments
Parul Institute of Technology
The Basic Direct Expansion Refrigeration Cycle
Subsea 100 Global Services Products Presentation
Process Equipment Design and Heuristics – Process Vessels
Mass Transfer In Chemical Engineering
Introduction of fuel feed system
BASIC PNEUMATICS.
LEGEND High press Low press Liquid vapour mixture
ILC Experimental Hall Cryogenics An Overview
By: JAGDEEP SANGWAN Refrigeration Basics 101.
Piping and Instrumentation for Process Industries
Chapter 5-3 Using Thermal Energy.
Automotive Engines Theory and Servicing
SC1R Cold Box PDR Assembly Sequence
Overview of the TARGET Monolith Rough Vacuum
Gas Transmission Pipelines
INTRODUCTION ALAQUA is a US corporation. We manufacture process equipment. Our engineers have over 20 years experience in the engineering of sanitary and.
Presentation transcript:

Process Air Compressor Knockout Replacement Presented By: Saud Saleem Designation: App. Engineer(Mech)

Overview: Introduction Project Handling Cost estimation Problem Area

Introduction: Knockout? A knockout drum is used whenever a process requires droplets to be separated from a vapor stream. T1 Inter Cooler Condensate causing Corrosion Condensate Removed and Drained Out Main Suction T2 T3 Where T2 > T1 Where T3 < T2 Condensed Vapors Knockout Drum

Working Principle of Vane Pack: Flow Vane Pack

Introduction: Background: Existing knockouts were replaced in 1987. Upon inspection in TA-07, heavy corrosion and cracks was observed on impellers. PECO (Original Vendor) informed that knockouts are undersized

Project Handling: Steps taken sequentially Planning and Scheduling Engineering Procurement Execution

Project Handling: PLANNING & SCHEDULING:

Percentage scope of each section: Project Handling: Percentage scope of each section:

Cost Estimation: Rs. 60.4 MM Rs.17.0 MM Rs. 1.54 MM Rs. 1.39 MM Cost Basis 30-Sep-2007 Foreign Component Cost of Internals € 90,178 Cost of Instrumentation € 100,000 Local Component Cost of Vessels Rs. 60.4 MM Cost of piping+ Civil works Rs.17.0 MM Custom Duty @ 5% Rs. 1.54 MM Sales Tax Rs. 1.39 MM Cost of Construction Rs. 12.75 MM Total Local Component Rs. 93.1 MM (€ 1.1 MM) Contingency @ 10% € 0.13 MM Total Cost In Euro € 1.43 MM

Project Handling: Engineering: Process Design Mechanical Design Civil Design

Project Handling: Procurement: Mechanical equipments: Instrumentation: Knockout vessels Internals Glass Level Gauges Flexibility bellows Hanger supports Instrumentation: Level transmitter Level Controller Control valves

Mechanical Equipment: Upstream Gas Distribution Plate & YORKMESHTM Agglomerater FLEXICHEVRON Vane Pack Tower Attachements Knockout Vessel

Comparison of total procurement by each section:

Project Handling: Procurement Status: Material procured Internals Material under procurement Knockout vessels Pending materials Expansion bellows Control valves Glass Level Gauges Spring hanger support

Project Handling: Execution: Mechanical Installation of New Interconnecting Piping Re-routing of existing piping Erection of KO vessel Installation of Internals Installation Of Glass Level Gauges

C-111A C-109A AVAILABLE SPACE FOR C-111A NEW C-111A NEW C-108A NOZZLE SIZE INCREASED NEW PIPING Ø 12” C-109A

Project Handling: Execution: E&I Installation Of Control Valves Installation Of Level Transmitters Installation Of Switches

Project Handling: Execution: Civil Structure Foundation

Problem Areas: Procurement of knock out vessels. Procurement of control valves. Procurement of Flexible bellows. Project time line.

Thank You

Questions?