Injector De-cabling Project

Slides:



Advertisements
Similar presentations
Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
Advertisements

Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Fibres & copper Cabling activities LIU meeting 27/09/2013 F Duval 27/09/2013 F Duval Cabling acxtivities LIU 1.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Injector De-cabling Project Project Team Meeting #
Injector De-cabling Project Enlarged meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
TS, Length of YETS EYETS LIU & CONS Project
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Status Report – Injection Working Group Working group to find strategy for more efficient start-up of injectors and associated facilities after long stops.
Injector De-cabling Project Enlarged meeting # E. HARROUCH, EN-MEF, on behalf of the Injector De-cabling Project Team.
Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure.
Consolidation and Upgrade of the SPS Electrical Networks Current Status JP. Sferruzza, on behalf of EN/EL.
ECRs and ES for the LHC Last presentation on the 26 th of August 2015 (LMC 232) S. Chemli for EN-MEF-DC LMC xxx.
Injector De-cabling Project Enlarged project meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
On behalf on EN-EL October 1 st, 2015 YETS Works EN-EL [ CF excluded ]
Booster identification/disconnections Follow-up Enlarged project meeting, E. HARROUCH, EN-MEF, on behalf of the Injector De-cabling Project.
Injector De-cabling Project Project meeting # 7, S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.
28 th January LHC Performance Workshop Session 8: (E)YETS and Long Shutdown 2 Strategy and Preparation. Long.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
Dr. José Miguel JIMENEZ LS2 Project Leader, CERN 1 LS2 Days 30 th September2015.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
Planned activities during (E)YETS… up to LS2 for PSB-PS equipment Etienne CARLIER On behalf of TE/ABT/EC.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
Electrical Group Inputs for LIU-Ions J. Devine, on behalf of EN/EL.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Forecasts for waste and radioactive material storage A. Funken, L. Kobzeva LIU-Ions Coordination Meeting, 27/04/2016.
Electrial Safety LS2 days November 2016 AP
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
Magnet activities in SPS during EYETS
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
V4.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
ABT-EC EYETS Activities 2nd reports
East Area Renovation Project Team meeting # 2 – EDMS News
Framework Schedule from EYETS 2016 to LS2
CONS and HL-LHC day Analysis of needs from BE-CO
Update on the Critical Path of the PS Booster Schedule for the EYETS
PSB Lock Out Test, Follow-Up AP. Bernardes-/EN-STI, K
EYETS Works EN-EL [ FC excluded ]
YETS & LS2 Works EN-El on LHC / Power distribution
BE-ICS Activities during the LS2 Period (15 min)
East Hall under construction
EC Activities Status for the LIU
Buffer Zones - Status Report
Unifying for all accelerators and projects
De-cabling strategy during YETS
LHC-TS3 Coordination meeting #3
Installations, modifications, consolidation in 2005:
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS Planning for the EYETS Meeting 8 (07/12/2016)
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
Survey on “Chargés de Consignation” Follow-up
SPS activities during LS2 TE-EPC (Power Converter Group)
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
Short LHC-TS week 38 Confirmed by LMC on 16th August
GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (SMB/SE) Olivier Barrière.
YETS & LS2 Works EN-EL / Power distribution
Overview & baseline of LS2 and roadmap for CRG
TE-MSC activities in SPS during YETS
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
ABP/RTL Main RTL Activities for 2007/8:-
Presentation transcript:

Injector De-cabling Project Coordination Meeting for the PSB and PS & TT2 Facilities YETS 2015-2016 01.10.2015 S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team

Contents Scope of the project Status by machine YETS activities @ Booster Identified issues Project Information Sharing

Scope of the Project To identify and remove obsolete cables within the injector complex, until end of LS2. First  priority:  Identification of obsolete cables in the  Booster and SPS BA5  Partial / total removal must be decided by end September 15’ Triggered by LIU needs (room in cable containment) Second priority: SPS (BA3) Third  priority:  Identification of obsolete cables in the PS, TT2, LINACs   RUN 2015 YETS 2015-2016 RUN 2016 EYETS 2016-2017 RUN 2017 YETS 2017-2018 RUN 2018 LS2 BOOSTER Cable identification IDENTIFICATION Cable labelling LABELLING Cable disconnection DISCONNECTION Cable removal REMOVAL SPS BA5 LEFT REMOVAL BA5 LEFT REMOVAL BA5 RIGHT & BA3 REMOVAL PS, TT2 & Linacs TO BE DEFINED

Status by machine BOOSTER: Machine/area Total number of signal and control cables Identified obsolete cables on Sept. 21st Booster 12’000 3’000 (25%) SPS – BA5 ~ 6’500 3’250 (50%) SPS – BA3 ~ 8’000 PS – CENTRE RING ~7’000 963 (14%) TT2 ~3’000 72 (2.5%) BOOSTER: 3000 obsolete cables to be removed (consolidation budget) before LS2 2800 used cables to be removed and replaced during LS2 for LIU (LIU budget) 2 big cable campaigns for EN-EL (EYETS16-17 + YETS17-18 / LS2) Strong commitment from all the equipment groups during identification and disconnection stages  resources to be secured for YETS15-16

YETS activities @ Booster YETS 2015/2016 = 7-8 weeks to complete: Circuit lockout Cable identification Cable disconnection System tests Current proposal: Circuit lockout: 1-2 days (depending on equipment group decision) Cable identification and disconnection for separate systems . 2 weeks in 2 shifts Check of separate systems: 2 weeks in 2 shifts Cable identification and disconnection for communication system: 2 weeks in 2 shifts Check communication system : 1-2 week in 2 shifts Schedule being prepared Operators might help.

YETS activities @ Booster Access 6.00 am to 22.00 pm Booster Mon 07/12/15 Fri 19/02/16 @ 12.00 PS Wed 16/12/15 Fri 12/02/16 @ 12.00 TT2 Tue 15/12/15 Access Control transfer CCC  CSA Mon 04/01/16 @ 06.00 Fri 12/02/16 @ 06.00 Draft Planning YETS 2015-2016: PS&TT2 EDMS 1510007 PSB soon Simon Mataguez EDMS 1549666

Identified issues: re-commissioning Re-commissioning after disconnection/removal – Common procedure  a dedicated sub-WG has been launched Will address the following topics: List of tests to be achieved after disconnection Procedure for already disconnected cable Procedure for not yet disconnected cable Procedure for orphan cable

Identified issues: Lock-out Lock-out of all services during identification and cable disconnection in conflict with some systems Identification and cable disconnection (YETS 2015) under the responsibility of the equipment group  Up to the equipment group to decide for the lock-out of its equipment Removal of the obsolete cables (EYETS 2016-2017) under the responsibility of EN-EL  general lock-out is mandatory.

Project Information Sharing E-groups InjectorDe-CablingProjectMembers (members of the Injector De-Cabling Project (equipment group)) InjectorDe-cablingProjectTeam (Project team for de-cabling activities in the injectors) Indico https://indico.cern.ch/category/6591/ Sharepoint site https://espace2013.cern.ch/Injector-De-Cabling-Project/_layouts/15/start.aspx#/

THANKS FOR YOUR ATTENTION !