Injector De-cabling Project Coordination Meeting for the PSB and PS & TT2 Facilities YETS 2015-2016 01.10.2015 S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team
Contents Scope of the project Status by machine YETS activities @ Booster Identified issues Project Information Sharing
Scope of the Project To identify and remove obsolete cables within the injector complex, until end of LS2. First priority: Identification of obsolete cables in the Booster and SPS BA5 Partial / total removal must be decided by end September 15’ Triggered by LIU needs (room in cable containment) Second priority: SPS (BA3) Third priority: Identification of obsolete cables in the PS, TT2, LINACs RUN 2015 YETS 2015-2016 RUN 2016 EYETS 2016-2017 RUN 2017 YETS 2017-2018 RUN 2018 LS2 BOOSTER Cable identification IDENTIFICATION Cable labelling LABELLING Cable disconnection DISCONNECTION Cable removal REMOVAL SPS BA5 LEFT REMOVAL BA5 LEFT REMOVAL BA5 RIGHT & BA3 REMOVAL PS, TT2 & Linacs TO BE DEFINED
Status by machine BOOSTER: Machine/area Total number of signal and control cables Identified obsolete cables on Sept. 21st Booster 12’000 3’000 (25%) SPS – BA5 ~ 6’500 3’250 (50%) SPS – BA3 ~ 8’000 PS – CENTRE RING ~7’000 963 (14%) TT2 ~3’000 72 (2.5%) BOOSTER: 3000 obsolete cables to be removed (consolidation budget) before LS2 2800 used cables to be removed and replaced during LS2 for LIU (LIU budget) 2 big cable campaigns for EN-EL (EYETS16-17 + YETS17-18 / LS2) Strong commitment from all the equipment groups during identification and disconnection stages resources to be secured for YETS15-16
YETS activities @ Booster YETS 2015/2016 = 7-8 weeks to complete: Circuit lockout Cable identification Cable disconnection System tests Current proposal: Circuit lockout: 1-2 days (depending on equipment group decision) Cable identification and disconnection for separate systems . 2 weeks in 2 shifts Check of separate systems: 2 weeks in 2 shifts Cable identification and disconnection for communication system: 2 weeks in 2 shifts Check communication system : 1-2 week in 2 shifts Schedule being prepared Operators might help.
YETS activities @ Booster Access 6.00 am to 22.00 pm Booster Mon 07/12/15 Fri 19/02/16 @ 12.00 PS Wed 16/12/15 Fri 12/02/16 @ 12.00 TT2 Tue 15/12/15 Access Control transfer CCC CSA Mon 04/01/16 @ 06.00 Fri 12/02/16 @ 06.00 Draft Planning YETS 2015-2016: PS&TT2 EDMS 1510007 PSB soon Simon Mataguez EDMS 1549666
Identified issues: re-commissioning Re-commissioning after disconnection/removal – Common procedure a dedicated sub-WG has been launched Will address the following topics: List of tests to be achieved after disconnection Procedure for already disconnected cable Procedure for not yet disconnected cable Procedure for orphan cable
Identified issues: Lock-out Lock-out of all services during identification and cable disconnection in conflict with some systems Identification and cable disconnection (YETS 2015) under the responsibility of the equipment group Up to the equipment group to decide for the lock-out of its equipment Removal of the obsolete cables (EYETS 2016-2017) under the responsibility of EN-EL general lock-out is mandatory.
Project Information Sharing E-groups InjectorDe-CablingProjectMembers (members of the Injector De-Cabling Project (equipment group)) InjectorDe-cablingProjectTeam (Project team for de-cabling activities in the injectors) Indico https://indico.cern.ch/category/6591/ Sharepoint site https://espace2013.cern.ch/Injector-De-Cabling-Project/_layouts/15/start.aspx#/