LARP Phase II Secondary Collimator RC1

Slides:



Advertisements
Similar presentations
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Advertisements

RF Cavity Module G. Gosling Dept. of Mechanical Engineering Imperial College London.
Purpose Body Making module is designed for bending the laminated foil film in the shape of a tube, for welding the side seam and for cutting bodies with.
Coll Eng E Doyle 1/18 LARP Phase II Secondary Collimator RC1 Prototype Engineering Status 6/21/06 Jaw-hub-shaft concept - continued Permanent.
MP Prototype 2 1IWF-EXP/ÖAW GRAZ  Smaller Size  Outcome of the test results with MP-P1 was the need for a reduced cross section  Rectangular Shaped.
MICE RF Cavity Design and Fabrication Update Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
4m Undulator Design Concepts Amanda J Brummitt CCLRC RAL On behalf of the HeLiCal Collaboration.
Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
Progress on the MICE 201 MHz Cavity Design Steve Virostek Lawrence Berkeley National Lab RF Working Group Fermilab August 22, 2007  automatic.
Update on Be Wall Cavity Steve Virostek Lawrence Berkeley National Lab MTA RF Workshop November 15, 2010.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes now twist, under vacuum, as jaws turn, with R~1.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
LARP Rotatable Collimators for LHC Phase II Collimation 26 October 2006 LARP Collaboration Meeting – Port Jefferson, NY Tom Markiewicz/SLAC Representing.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes now twist, under vacuum, as jaws turn, with R~1.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
MECHANICAL DESIGN OF TCSP COLLIMATORS Secondary Collimators Embedding BPMs L. GENTINI, A. Dallocchio, A. Bertarelli, F. Carra, M. Garlasche.
LARP Rotatable Collimators for LHC Phase II Collimation 26 October 2006 LARP Collaboration Meeting – Port Jefferson, NY Tom Markiewicz/SLAC Representing.
LHC Phase II Collimator teleconference - 4 March 2008LHC Rotatable Phase II Collimators 1 beam LARP Phase II collimator Progress and Plans 4 March 2008.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 16 May 2006 No 1 /22 LARP Phase II Secondary Collimator RC1 Collimator Test Program Revised 5/15/06.
SLAC RC Status Report 30 August 2010 LHC Collimation Working Group Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
ZDC Remote Handling Tool Structure and Force Analysis P. Debbins University of Iowa December 10, 2009.
SLAC R&D Mtg November 2007LHC Rotatable Phase II CollimatorsSlide # / 17 beam LARP Rotatable Collimators for LHC Phase II Collimation 12 November.
LARP LHC PHASE II COLL RC1 - S. Lundgren 1 April 2009 No 1 /6n LARP Phase II Secondary Collimator RC-1 Mechanical Design Review 01/04/09.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
A. Bertarelli CERN TS – MME Group 1 CERN European Organization for Nuclear Research Actuating system of the LHC Collimators (Phase 1) Main Features.
LARP Rotatable Collimators for LHC Phase II Collimation 18 April 2007 LARP Collaboration Meeting – Fermilab Tom Markiewicz/SLAC Representing Gene Anzalone,
Mount structure concept FM1 & FM2 Mount structure design 1) Aluminum structure. 2) Structure design for holding Newport mirror mount because of its compact.
Jan. 28, 2014W. Bertl, PSI BPIX Cooling Status W. Bertl, PSI.
Task List for Phase II Rotatable Collimator Project at SLAC 30 January 2007 CERN/LARP Video Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Collimation Overview 28 October 2008 LARP CM11, Fermilab Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program 1)Short Status.
LARP LHC PHASE II SECONDARY COLLIMATOR CD1 REVIEW. - E. Doyle 15 Dec /25 LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 Prototype Engineering.
LHC Collimators Phase 2 - Visit to Plansee 28th August Materials for Phase II collimators.
LARP Rotatable Collimators for LHC Phase II Collimation 09 July 2007 SLAC R&D Status Meeting Gene Anzalone, Eric Doyle, Lew Keller, Steve Lundgren, & Tom.
LARP Rotatable Collimators 19 June 2006 ILC R&D Status Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 10 Dec 2007 No 1 /12 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 1/17 LARP Phase II Secondary Collimator RC-1 Collimator Development Status and Outlook Revised.
B [OT - Mechanics & Cooling] Stefan Gruenendahl February 2, 2016 S.Grünendahl, 2016 February 2 Director's Review -- OT: Mechanics &
PXIE RFQ Engineering Design Steve Virostek Engineering Division Lawrence Berkeley National Laboratory April 10, 2012 Project X Collaboration
1 SLAC RC Status Report 19 July 2010 LHC Collimation Working Group Meeting Jeff Smith/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
LARP Phase II Secondary Collimator Status Report SLAC ILC R&D Summary Meeting 24 April 2006 T. Markiewicz/SLAC.
LARP Phase II Secondary Collimator RC1, ETC - Status 4/10/06
Status of material tests
Complementary ISTC Projects #3888, 3889p
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 RC1 Construction and Test Plan LARP LHC PHASE II COLL REVIEW – RC1.
LARP Phase II Secondary Collimator RC-1
SLAC RC Status Report US LHC Accelerator Research Program
Recommendations of 12/16/05 review committee & SLAC response
23 April 2012 Tom Markiewicz/SLAC
LARP Phase II Secondary Collimator RC1
questions for cern – doyle rev 7/09/07 1/5
LARP Phase II Secondary Rotatable Collimator
LARP Phase II Secondary Rotatable Collimator
LARP Phase II Secondary Collimator RC-1
GEARS AND CAMS C H A P T E R S E V E N T E E N.
LARP Phase II Secondary Collimator RC-1
LARP Phase II Secondary Collimator RC-0 and RC-1
LARP Rotatable Collimators for LHC Phase II Collimation
LARP Phase II Secondary Collimator RC-1
Engineering Update E. Doyle 5/16/06
LARP Phase II Secondary Collimator RC-0 and RC-1
Presentation transcript:

LARP Phase II Secondary Collimator RC1 Collimator Test Program Status Revised 8/22/06 LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 1 /22

Jaw/Cooling Tube Joint Development Model of Coil Winding Test piece 200mm long x 86mm diameter LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 2 /22

Jaw/Cooling Tube Joint Development Section view of test Mandrel brazed to Jaw sections Jaw Mandrel 136mm dia 200mm LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 3 /22

Aluminum Mandrel for Coil Winding Test Cooling Tube aligner 200mm LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 4 /22

Jaw/Mandrel/Cooling Tube Next Step Copper Mandrel in fabrication Stake coil to mandrel during winding to prevent spring back Fully annealed tubing wound into groove Braze assembly together Machine od to eliminate distortions & add wire groove Braze together with Jaw halves (wire & foil) Cut into sections for braze joint inspection Document results with photos and write-up of process LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 5 /22

Single Jaw Thermal Test Hardware Progress Molybdenum Shaft has order out to bid: Is long lead (6-8 weeks) and may hold up timely progress So …. Stainless Steel Shaft may be used instead (for this test only) Mandrel fabrication drawing will be completed this week And released to shop soon after Jaw fabrication drawing complete except final dimensions of I.D. Not released to shop yet LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 6 /22

Single Jaw Heater Test Shaft Model of Shaft showing 1mm raised shoulder (Hub) at center LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 7 /22

Molybdenum Shaft end detail Relief on O.D is for stiffening sleeve and worm gear mounting Slots for tubing extend past bearing and are 180 deg offset Relief on I.D. is for roller bearing LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 8 /22

Single Jaw Thermal Test Hardware Jaw Sections ~450 mm long Jaw sections are manufactured as quarter cylinders for fabrication accuracy and ease of braze assembly Only 4 or 5 flats are planned for the test and for measurement purposes LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 9 /22

Single Jaw Thermal Test Setup Progress Instrumentation is mounted in Rack Data Acquisition and Control Module 32-Channel Isothermal Terminal Block 32-Channel Amplifier Instrumentation has been tested With vendor provided TC Will also test displacement sensor functioning Example System Schematic has been generated More work needed to complete the entire system schematic LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 10 /22

Single Jaw Thermal Test Hardware Test Lab Setup Block Diagram Bldg Power fuse Heater #1 Controller Jaw Heater #1 fuse 100 Amp Tap Over Temperature Control fuse Jaw Heater #2 Heater #2 Controller fuse PC with LabView Software Jaw Internal Cooling Line Jaw deflection sensors Capacitec Signal Amplifier Chiller DAC & Signal Processor Jaw thermocouples Bldg Power LCW Water (Supply) LCW Water (Return) LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 11 /22

Development/Test Lab Layout Item availability Chiller & LCW Next to Clean Tent Vacuum equip’t SLAC misc? Heater Power supplies In Clean Tent Gantry In Bldg Granite table Instrumentation Power to CR Work proceeding LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 12 /22

Granite surface plate in Clean Tent LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 13 /22

16.5 kW Chiller adjacent to Clean Tent LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 14 /22

Power Supplies staged for installation in rack LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 15 /22

Instrumentation rack and computer workstation LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 16 /22

No fabrication drawings have been done as yet RC1 Design Progress Models and assemblies of the various Collimator Mounting Stands are complete An enlarged vacuum tank has been modeled and some CERN support stand modifications have been identified No fabrication drawings have been done as yet Layouts, calculations and models of two Jaw mounting as well as a rotation scheme have been explored…. LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 17 /22

Plug and Play Concept for Jaw mounting LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 18 /22

Another View LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 19 /22

Some important Jaw mounting details Draws on features from CERN Phase 1 Collimator Top and Bottom RF springs (not shown) are identical To CERN part Positioning and Guiding Plates are similar to CERN Design CERN Contact RF Assy can be used Modified CERN Pivot Tensioning Plate LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 20 /22

Spring Return Ratchet Actuator Press here to rotate the worm/ratchet shaft 2 leaf springs produce linear motion LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 21 /22

Ratchet, Worm and Worm Gear Shaft and Jaw mount details not shown for clarity 100 Tooth Worm Gear (mounts to shaft) Single turn Worm 20 Tooth ratchet Bearing 2X LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 22 /22

RC1 Mechanical Prototype FY07 RC1 consists of jaws, tank & actuators - evaluated for horizontal (shown), vertical (90o) and skew (+/- 45o) orientations. FY08, RC2 LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 August 2006 No 23 /22