ELCITA Update May 2016.

Slides:



Advertisements
Similar presentations
Unit 12 Construction Surveying
Advertisements

Omega & Associates Engineering Ltd. Chilliwack Providing professional services to our clients with quality, cost effective AND innovative engineering solutions.
CDOT WATER QUALITY PROGRAM
Stuck in the SWMP Storm Water Management Programs: New challenges for the Transportation Community.
Legal Descriptions and Site Plan Requirements
What do Civil Engineers do? Design Civil Infrastructure Roadworks Earthworks Stormwater Management.(Including Detention & Quality Measures) Sewer Water.
MODERN VENTURES (Pty)Ltd t/a NORTHERN GATEWAY CITY PORTION 2 OF 36-NQ
Architect Drawing of New Entrance. Location Location of Phase II Construction Project – Old tennis courts west of the existing building.
LAYOUT OF COMMERCIAL BUILDINGS
21 st Sep Election Process July & August
Brighton King's Avenue London Palmeira St. Marina Drive Victoria St. P
TCC Budget Highlights Capital Budget - $190.43M Operating Budget - $384.9M Total Budget – $575.33M.
ELCITA Update 25 th August Update – Estate Management E – Toilets 8 e-toilets operational and work order placed for 4 more e-toilets Under Ground.
October E – Toilets 8 e-toilets operational and work order placed for 4 more e-toilets. Under Ground Drainage System Completed & Tender Published.
Greetings from Spa Eco City & the creators of Frangipani Country Estates!! Greetings from Spa Eco City & the creators of Frangipani Country Estates!! 1.
MACHINERY AND EQUIPMENT OWNED  HOT MIX PLANT 40/60 TPH ELECTRONICALLY CONTROLLED :12 Nos ELECTRONICALLY CONTROLLED :12 Nos AS PER MOST (III REVISION)
Water Quality Demonstration & Educational Program for Main Street Little Rock.
February Skywalk Contract Awarded to M/s mayaPRAXIS to provide Architectural & Structural feasibility report of Skywalk system for Electronics.
November E – Toilets 8 e-toilets operational and 4 more e- toilets work in progress. Under Ground Drainage System Completed & Tender Published.
Civil Engineering Surveying Roy Frank. Basic Route Survey and Design 1.Concept for Route 2.Reconnaissance Study 1.Small scale mapping of region (1”-500’
June Skywalk M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E.
PORT OF TACOMA Lincoln Avenue Grade Separation Lincoln Avenue Improvements Project Update.
Resolution No , Authorize the city attorney to bring condemnation action for the purpose of obtaining street right of way and easements for construction.
Chapter 2 Reading Site Plans. Chapter Overview Introduction to Reading Site Plans Understanding Legal Descriptions Site Plan Fundamentals Topography Reading.
We would like to list below an update on the Progress of the Project.
ELCITA UPDATE April 2017.
ELCITA UPDATE February 2017.
ELCITA UPDATE March 2017.
ELCITA UPDATE JULY 2017.
ELCITA Update December 2015.
City of Whitehorse 2017 Capital Projects & Service Requirements Peter O’Blenes, P. Eng February 21,2017.
ELCITA UPDATE January 2017.
Environmental Assessment
ELCITA UPDATE AUGUST 2017.
ELCITA UPDATE November 2016.
General Road Construction Information
Construction Activity
AR-315 BUILDING CODES & BYE LAWS
ELCITA Update April 2016.
SKYWARDS TECH PARK.
We would like to list below an update on the Progress of the Project.
ELCITA UPDATE SEPTEMBER 2017.
ELCITA UPDATE October 2016.
Construction Report March 25, 2010.
ELCITA UPDATE August 2016.
Architectural Drafting
ELCITA UPDATE November 2017.
Electronics City Industrial Township Authority
Atal Mission for Rejuvenation and Urban Transformation (AMRUT)
ELCITA Update March 2016.
Organics Waste Processing Facility Construction Progress Update December 15, 2010
ELCITA UPDATE March 2018.
ELCITA UPDATE April 2018.
We would like to list below an update on the Progress of the Project.
Light Regional Council
Chapter 15 Site Plan Layout.
ELCITA UPDATE July 2016.
ELCITA UPDATE December 2016.
OVERVIEW & PROGRESS Presentation before the Sub Collector cum Sub Divisional Magistrate, Cuddalore.
Site Plan Requirements
ELCITA Update January 2016.
ELCITA UPDATE September 2016.
URBAN TRAIL PROJECT UPDATES
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
ELCITA UPDATE June 2019.
Full Service Plumbing Columbus, Ohio. plumbing The art and science of creating and maintaining sanitary conditions in a building used by humans. It is.
ELCITA UPDATE August 2019.
ELCITA UPDATE July 2019.
ELCITA UPDATE April
Presentation transcript:

ELCITA Update May 2016

Estate Management Skywalk E – Toilets M/s mayaPRAXIS had submitted the draft preliminary feasibility study Report on Skywalk system for Electronics city phase 1. E – Toilets 15 e-toilets operational, e-toilets installation work in progress. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries - completed. Soft copy of base map drawing of Phase 1 has been submitted for ELCITA review - Completed. GIS Web Application Software work verification in progress.

Estate Management Permanent Works - Under Progress WIPRO Neeladri Road Cdot Dmart Road

Estate Management Maintenance – Under Progress Laying Pavers in Front of Lemon Tree Hotel Drain work At KSSIDC Complex

Estate Management Maintenance – Under progress Drain work in Canara Bank/ Fire station junction Shoulder Drain work at Various location

Estate Management Maintenance – Under progress Construction of Drain, Cover slabs along HP Avenue Road Laying Pavers Along HP Avenue Road

Estate Management Maintenance – Completed Cover Slab work at BESCOM Drain work Along Gollahalli Road

Estate Management Maintenance – Under progress Re Fixing of Kerbstone and providing pavers along Velankani Road Re fixing Drain cover slab in front of Lord Plaza

RMU yard at Wipro Gate no 5 Estate Management Maintenance – Completed RMU yard at Wipro Gate no 5 Drain Cleaning Work

Cross Drainage work at Gollahalli Junction Estate Management Maintenance – Completed Drain work adjacent to RajKamal Industries Cross Drainage work at Gollahalli Junction

Estate Management Maintenance – Completed Drain work in front of BETL Footpath work in front of KFC

Estate Management Maintenance – Completed Providing & Laying Sewer line, Electronics City Phase 2 Construction of Drain from JJ glastronics to existing drain

Estate Management Sustainability Works – Completed Supply & Erection of Shed for Organic waste processing plant & Shredding Area at KIADB Land – Ecity Phase 2

Estate Management Maintenance – Completed Construction of Compound Wall at Wipro Gate No 5 Construction of Compound Wall at Wipro Gate No 12 A

Drain from 300KLD STP to Outside Estate Management Maintenance – Under Progress WMM Road from MSME Building to Exit Gate Drain from 300KLD STP to Outside

Doddanagamangala Village Concrete Road Estate Management Road Works - Under Progress WIPRO Neeladri Road Doddanagamangala Village Concrete Road

Canara Bank to Firestation Road Estate Management Road Works – Under Progress HP Avenue Road Canara Bank to Firestation Road

Bhavani Industries Road Estate Management Road Works - Completed Quasitum Road Bhavani Industries Road

Estate Management RWH works – Under Progress SI.NO DESCRIPTION NO OF PITS STATUS 1 RAIN WATER HATVESTINH PIT 38 COMPLETED 2 12 TO BE AWARDED

Estate Management Contract Awarded Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road C-DOT to D-Mart Road Junction

Estate Management Contracts on Anvil Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2