LHC schedule.

Slides:



Advertisements
Similar presentations
Extended LTC CERNMassimiliano Ferro-Luzzi 1 Experiments during HWC, beam tests and initial commissioning  What are the experiments going to do.
Advertisements

A. Bay Beijing October Accelerators We want to study submicroscopic structure of particles. Spatial resolution of a probe ~de Broglie wavelength.
LHC status and commissioning plans. LHC in 4 slides Lest we forget Progress to date Present schedules Consequent plan for 2008.
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
Luminosity expectations for the first years of CLIC operation CTC MJ.
R.Bailey, LHCCWG, January 2007 LHC Commissioning Working Group 2006 Presented to LTC in November and MAC in December Presented to LTC in November and MAC.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
Michel Della Negra/Karlsruhe May PbWO4 Crystals: Energy Resolution  m /m = 0.5 [  E1 /E 1   E2 /E 2  cot(  /2)  ] H   Simulation (100.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
P. 1K. Eggert – Early TOTEM Running with the  * =90m Optics Karsten Eggert on behalf of the TOTEM Collaboration Politecnico di Bari and Sezione INFN Bari,
Running scenario 2009/10 Run through components – and then synthesis.
Feb 1, 2010 Experimental Particle Physics 1 Elementary Particle Physics Experiment: The ATLAS experiment at the LHC University of Massachusetts, Amherst.
Bill Christie For the STAR Collaboration January 5, Outline Detector configuration for Run 16 Data set Goals Desired luminosity profile for Run.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
1 Machine Checkout and Setup Periods Jan Uythoven Thanks to: O.Aberle, R.Bailey, F.Bordry, O.Brunner, L.Bottura, E.Carlier, P.Charrue, E.Ciapala, S.Claudet,
AEM, Sept Frank Chlebana (Fermilab) Status of the LHC and CMS Frank Chlebana (Fermilab) All Experimenter’s Meeting Sept
Steve Playfer University of Edinburgh 15th Novemebr 2008 Large Hadron Collider at CERN.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
Joint LHC Machine-Experiments Workshop on Very Forward Detectors Summary D. Macina (CERN) Joint LHC Machine-Experiment Worshop on the Luminosity Monitoring.
Lucio Rossi The High Luminosity LHC Project Distinguished Lecturer 2013.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
An Idiot’s Guide to LHC Upgrades Bohr Lunch Seminar. 16/5/08 Terry Wyatt. University of Manchester.
CERN’s Large Hadron Collider
Luminosity monitor and LHC operation
LHC Status and Prospects
Beam Energy & Intensity: One bunch during full cycle
The CERN Physics Programme
LHC Commissioning with Beam
Minimum Hardware Commissioning – Disclaimer
Status of LHC installation & New Installation Schedule
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Installation of an Instrument on a CERN machine
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Powering the LHC Magnets
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
Summary of week 7 Hardware Commissioning:
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
The Status of the LHC machine
Machine plans - Alignment workshop
Status of the LHC December 2009
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Beam requirements and operational scenarios in 2010
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Summary of Week 16 G. Arduini, J. Wenninger
CSP Meeting CERN CERN Accelerators in th November 2010
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
LHC upadtes.
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
LHC status & 2009/2010 operations
LHC installation status
SLHC-PP kick-off meeting, CERN 9 April 2008
Lecture II.
Luminosity and time estimates
Summary for LPC (March 7th, Ralph Assmann)
Beam commissioning plans, 2007 and 2008
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
LHC Machine Advisory Committee, CERN 12th June 2008
Presentation transcript:

LHC schedule

Installation activities in a sector QRL installation QRL consolidation after pressure test Cryo-magnet transport Interconnection phase 1 LSS installation End of 1st interconnect activity Pressure test Cryostat closure – Interconnect consolidation Insulation // Interconnect phase 1 Beam pipes & bake-out ELQA at warm Cool-down Power tests Machine check-out Beam at 450 GeV/C

Press release June 23 First collisions in the Large Hadron Collider (LHC) will happen in November 2007, said LHC project leader Lyn Evans at the 137th meeting of the CERN[1] Council held in Geneva today. A two month run in 2007, with beams colliding at an energy of 0.9 TeV will allow the LHC accelerator and detector teams to run-in their equipment ready for a full 14 TeV energy run to start in Spring 2008. The schedule announced today ensures the fastest route to a high-energy physics run with substantial quantities of data in 2008, while optimising the commissioning schedules for both the accelerator and the detectors that will study its particle collisions. It foresees closing the LHC’s 27 km ring in August 2007 for equipment commissioning. Two months of running, starting in November 2007, will allow the accelerator and detector teams to test their equipment with low-energy beams. After a winter shutdown in which commissioning will continue without beam, the high-energy run will begin. Data collection will continue until a pre-determined amount of data has been accumulated, allowing the experimental collaborations to announce their first results.

Operations Activity

Machine checkout and later Oct Operations testing Minimum HWC Nov Full Machine Checkout (TI8 & TI2, Access, Vacuum, Equipment Tests, Cycle and Set, BIC and INB) Beam Commissioning to 450GeV 16days estimated, 60%efficiency assumed Dec Engineering run (Collisions at 450GeV + Ramp Commissioning) Minimum HWC

Hardware Commissioning Calibration run in 2007 Installation Hardware Commissioning 450GeV Engineering Run Shutdown Machine checkout 450GeV Beam commissioning Calibration run 450GeV Kb 43 156 ib (1010) 2 4 10 * (m) 18 6 intensity per beam 8.6 1011 1.7 1012 6.2 1012 1.6 1013 beam energy (MJ) .06 .12 .45 1.1 luminosity 1028 1.3 1029 4.8 1029 3 1030 event rate 1 (kHz) 0.4 5 19 120 W rate 2 (per 24h) 0.5 21 130 Z rate 3 (per 24h) 0.05 0.6 13 Assuming 450GeV inelastic cross section 40mb Assuming 450GeV cross section W → lν 0.5nb Assuming 450GeV cross section Z → ll 50pb

Staged commissioning plan for protons@7TeV 2008 Stage I II III Hardware commissioning 7TeV Machine checkout Beam commissioning 43 bunch operation 75ns ops 25ns ops I Shutdown No beam Beam 2009 III Shutdown Machine checkout 7TeV Beam setup 25ns ops I Install Phase II and MKB No beam Beam

Issues LTC on July 5th will deal with Anything else ? Optics (Stephane) Dynamic aperture (Massimo) Collimators (Ralph) Beam dump (Brennan) Operation (Mike) Anything else ? Detecting collisions How long is 450GeV collisions useful for the experiments? Assuming we make the 2007 run, what about 2008? What if we don’t make the 2007 run?