Status of design and production of LEP connection cryostat

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

SPL Intercavity support Conceptual design review 04/11/ A. Vande Craen TE/MSC-CMI.
Vacuum Vessel Production Readiness Review
WA105 General Meeting at CERN 21 & 22-January-2014 Enrique Calvo Alamillo.
Integration of Cavities and Coupling Coil Modules Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting March 28 – April 1, 2004.
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
H. Prin, F. Savary, D. Duarte Ramos, L. Grand- Clement, C. Mucher, A. Temporal.
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
PETS EuCARD. Present status and precision assembly L. Sánchez, F. Aragón, J. Calero, J.L. Gutiérrez, E. Rodríguez, F. Toral, CIEMAT 26/10/2011.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Interconnection work for the the QRL cryogenic extensions Ivo Slits - AT/CRI
Cavity support scheme options Thomas Jones 25/06/15 1.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
The integration of 420 m detectors into the LHC
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
AT-VAC SPC Nicolaas KOS Beam Screens for Inner Triplet Magnets LHC Upgrade Phase 1 Nicolaas KOS  LHC Upgrade phase 1  Inner triplet BS Requirements.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Summary of Presentation 1. Tolerances i. Vertical tolerances on BPMs (rf-BPM: ± 0.2μm, user BPMs: ±0.1μm, and X-BPMs: ± 0.1μm) ii. Tolerances on magnets’
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
First Wall Panel - Overview
Design ideas for a cos(2q) magnet
Cryostats for superconducting magnets
SPL RF coupler: integration aspects
Cold mass design, assembly plans and QA/QC at CERN
Stress and cool-down analysis of the cryomodule
Roadmap for triplet cryostats
11 T Dipole Integration & Plans M. Karppinen
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
HFM Test Station Main Cryostat
LEP cryostat Procurement strategy and plans
Crab Cavity HOM Coupler Specification Drawings & Tolerances
Cryostat procurement, status and plan, QA/QC
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Manufacturing of the first FCC-hh beam screen prototype for ANKA
Cryo-assembly design D. Ramos, V. Parma, C. Mucher, H. Prin, M. Souchet, J. Hrivnak, M. Moretti, L. Mora, F. Savary, L. Gentini Review of the 11T Dipoles.
Challenges of vacuum chambers with adjustable gap for SC undulators
Preliminary Y-chamber specifications – First draft
Status of cryostat integration and conceptual design
Update of cryogenic activities
Cedric Garion, TE-VSC-DLM, WP12
Dump Core Studied Design Solutions
From Design to Installation courtesy R. Folch S. Atieh TS / MME
Far Detector Activities Late 2017 – Early 2018
Parts exchange for HL-LHC AUP Q1&Q3
The 11T cryo-assembly: summary of design and integration aspects
Design of Distribution Feedbox at LHC P7
Challenges for FCC-ee MDI mechanical design
Phase II Collimators : design status
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
Magnetic shielding and thermal shielding
Status of QQXF cryostat
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

Status of design and production of LEP connection cryostat A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN Status – 22 September 2017

Summary Introduction Design Production Conclusion A. Vande Craen

Reminder Connection cryostat To be used with “standard” cryo-bypass Guarantee continuity of the cryogenic and electrical distribution A. Vande Craen

Design finished and approved Introduction Build to print design Use of standard LHC components when possible New concepts to Ease assembly Limit welding work Avoid deformations during fabrication and life cycle Design finished and approved (Internal review of IR2 LEP cryostats– 17 May 2017) A. Vande Craen

LE requirements : LHC-LE-ES-0001 LHC equipment requirements for pressure, temperature and leak tightness LE requirements : LHC-LE-ES-0001 A. Vande Craen

Specific requirements Golden class magnet (most stringent) Tolerances distribution Source +/- Vertical [mm] +/- Horizontal Geometry (sag) 0.015 Geometry (straightness) 0.2 Play in V/V’ assembly Play in alignment system 0.1 0.35 Alignment tolerance 0.05 Stability over time Total 0.465 0.7 Maximum 0.5 0.8 A. Vande Craen

Concept Concept Cold bore in helium vessel Pipes in continuity of standard interconnection lines Shuffling module at LEN extremity Bolted supporting structure LEP-A mirror of LEP-B A. Vande Craen

LEP vs LE A. Vande Craen

Cold bore cooling Goal Solution Beam line heat load = 0.65 W/m (LHC-LE-ES-0001) Warmest point bellow 2.7 K Solution Addition of a V’ line around cold bores Filled with superfluid helium Connected to shuffling module Cooling by conduction through superfluid helium A. Vande Craen

Cold bore/V’ supporting Goal V’ for cooling of cold bore with helium Insure positioning of cold bore inside V’ lines (play ~ 0 mm) No deformation of cold bore Solution Local “Punching” of V’ line to make contact with cold bore 3 deformation at 120° A. Vande Craen

Solution validated V/V’ support Tooling : lathe chuck Development campaign to find correct procedure Zero gap between tubes No deformation of cold bore Solution validated A. Vande Craen

Cold bore alignment system Goal Align beam lines within tight tolerances Solution Sleeve on V’ (tack welded) to improve pipe geometry Brass/Stainless steel contact to avoid seizing X-Y table for positioning Source Requirement Result V’/support +/- 0.1 (V) +/- 0.35 (H) +/- 0.05 Play in alignment system < +/- 0.05 A. Vande Craen

H-beam Ease access during assembly No structural welds No deformation/stresses Mechanical assembly for cold mass alignment Tight tolerances easy to achieve Machined plates  flatness = 0.2 mm/m Stress relieving  no later deformation due to stress relaxation Light cold mass (~ 2 tons) Lower mechanical rigidity than closed profile A. Vande Craen

H-beam cooling Goal Solution Uniform cool-down of the cold mass (no hot spot, no deformation) Cooling of the cold mass from 300 to 80 K < 1 week (on test bench) Solution Copper clamps on M1 and M2 lines  vertical symmetry Copper plates on H-beam for heat distribution Copper braids to connect clamps to plates All bolted solution Cooling time 300  80 K ~6 days (conservative assumption) A. Vande Craen

Flexible M lines Tolerances and forces in interconnection Solution : reduce interconnection forces > 90% due to M lines bellows Negligible deformation of cold mass (<< 0.1 mm deformation due to weight) (See M. Moretti’s presentation) A. Vande Craen

Flexible line prototype Test : 5 mm vertical offset 25 bar (water) External radial excitation Results : Small line displacements V = 0.07 mm H = 0.1 mm No buckling Solution validated A. Vande Craen

Shuffling module Goal Solutions Create space for busbars lyras Transition between position of lines in standard interconnection and LEN House bayonet heat exchanger Solutions 2 welded stainless steel dished ends with nozzles 12 mm thick for deformations ~0.12 mm @ 20 bar A. Vande Craen

Procurement strategy Collaboration with EN-MME for machined components Busbars and associated components procured by TE-MSC-LMF TE-MSC-CMI specification and contract follow-up Welded pressure components (shuffling module, bellows); MLI; Vacuum vessel; Bottom tray; Standard components. A. Vande Craen

Production status Vacuum vessel and bottom tray Cold mass Being fabricated Delivery from December 2017 Cold mass Being manufactured Delivery of components starting from November 2017 A. Vande Craen

Design reviewed and approved Fabrication on going Conclusion Design reviewed and approved Fabrication on going Assembly of first unit starting from November A. Vande Craen

Thank you ! A. Vande Craen