Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Crab Cavities in IR1 and IR5 Some considerations on tunnel integration What will be the situation in the tunnel after the LHC IR Phase-1 Upgrade. What.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
New HV test specification for the LHC N. Catalan for the EI section.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
LHC Magnet Tests: A challenge for an OperationTeam V. Chohan G.H. Hemelsoet CernGeneva Always set the trail, never follow the path.
CRYOGENICS AND POWERING
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
MM planning for HiLumi-LHC L. Fiscarelli M. Buzio, O. Dunkel, T. Zickler 4 March 2015.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Readiness of test stations for design validation Marta Bajko on behalf of the TE-MSC TF team CERN, 11 th December 2014 QXF design review, CERN.
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
The integration of 420 m detectors into the LHC
TE-CRG Activities D. Delikaris, TE-CRG.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
Procedures for detecting vacuum leaks in the LHC LTC open action from /36. LTC Frank Zimmermann, LHCCWG 23 October 2007.
CERN –GSI/CEA MM preparation meeting, Magnetic Measurements WP.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
HL-LHC IT STRING and Series test of SC link
SLHC –PP WP6 LHC IR Upgrade - Phase I.
Roadmap for triplet cryostats
11T Magnet Test Plan Guram Chlachidze
Equipment simplified model SMR UR safety
Testing of SC Magnets Status - November 2010
Minimum Hardware Commissioning – Disclaimer
Installation of an Instrument on a CERN machine
The HL-LHC Circuits: Global View and Open Questions
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Status of cryostat integration and conceptual design
The LHC - Status Is COLD Is almost fully commissioned
M. Alcaide Leon, Paolo Fessia
Update on HW commissioning
Comparison between 1) HL-LHC BASELINE: Q5 at point 6 at 1
M. Alcaide Leon, Paolo Fessia
Hollow e- lens, Cryogenic aspects
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
XFEL Vacuum System Commissioning
Circuits description and requirements - Closed Session-
Overview & baseline of LS2 and roadmap for CRG
The 11T cryo-assembly: summary of design and integration aspects
UK RFD Pre-Series cryomodule
Superconducting Links and Cold Powering components for HL-LHC
TEST PLANS for HL LHC IT STRING
WP3 Meeting – December the 10th 2015 H. Prin
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
Cryostats Some ideas for the new Q1 to Q3 Hi-Lumi WP3 meeting
HiLumi P1/P5, Cryogenic interfaces for sc links, DFX 2nd review
HL-LHC Long term behaviour of magnets Test facility limitations
Summary post TCC#54_02Aug’18
Review of hardware commissioning
HL-LHC Engineering Change Request # REDUCTION OF Q1 BEAM SCREEN COOLING TUBE DIAMETER FROM Ø16 MM TO Ø10 MM N. Kos TE-VSC TCC #77,
Review Bloc 4 and SM18 facilities and upgrade
HL-LHC New MS optimisation WP9, Preliminary cost estimates
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16

Open technical issues under discussions Integartion With SLOPE or not ( no request from CRG nor from magnets and Vac) Tooling : for Sc link and DFX installation Which set up point 1 or 5? Paolo Integration? The most complex one String should validate installation and dismounting procedures Cryogenics: Need of a quench buffer, 10 g/s recovery line at warm, operational pressure 20 bars Which cooling ( point 1 or point 5) Do we have spare DFX or we use a standard one? VHe in a cold mass = 25 l/ m? Herve? Magnets Machine cycles…see with ABP Training till Inom? Iultimate? Provoked quenches with QHs to check propagation, QH delays Tracking test ( measurements during ramp?) Thermal cycle? Alignment Monitoring also during operation the position of the magnets (installation, cool down, warm up) Vacuum Beam screen? With dedicated instrumentation? Chaufrettes? De we have counted in the budget the beam screens? 700 kCHF extra cost?WP12?we would need for Q1 proto ( 166mm) and D1( 6mm dipole) proto , we have for the series but we need to instrument at least one ( 6 mm quad). Marta Bajko for the TCC 15th September 2016

Integration slide1 Integartion With SLOPE or not ( no request from CRG nor from magnets and Vac) Tooling : for Sc link and DFX installation Which set up point 1 or 5? Paolo Integration? The most complex one String should validate installation and dismounting procedures We have to choose between: P1 or P5 Where P1L = P5R, and P1R= P5L P5L is the most complicated and coherent set up with the Sm18 installations and the tunnel is the smallest . We plan to reproduce the space allowed in that place of the tunnel for the interventions Using the argument of the SM18 set-up the choice is: P5L or P1L Using the argument of complexity is : P5L QRX P5 D1 CP Q3 Q2b Q2a Q1 DFX Proximity of existing cryogenic installations Position of the cryo line between the wall and magnets Marta Bajko for the TCC 5th October 2017

Marta Bajko for the TCC 5th October 2017 Integration slide 2 Integartion With SLOPE or not ( no request from CRG nor from magnets and Vac) Tooling : for Sc link and DFX installation Which set up point 1 or 5? Paolo Integration? The most complex one String should validate installation and dismounting procedures P5L is the most complicated and coherent set up with the Sm18 installations and the tunnel is the smallest . We plan to reproduce the space allowed in that place of the tunnel for the interventions QRX P5 D1 CP Q3 Q2b Q2a Q1 DFX Consultation results OK Not relevant Not relevant There is no clear show stopper in SM18 to simulate the SLOPE but we did not get till today REQUEST for doing it. OK Not relevant OK Not relevant OK OK Not relevant Not relevant OK OK OK OK TODAY we do not consider to implement a SLOP for the IT STRING. Marta Bajko for the TCC 5th October 2017

Marta Bajko for the TCC 5th October 2017 Integration slide 3 Integartion With SLOPE or not ( no request from CRG nor from magnets and Vac) Tooling : for Sc link and DFX installation Which set up point 1 or 5? Paolo Integration? The most complex one String should validate installation and dismounting procedures Magnets ordered by arrival option 1 Q2a prototype 1st-3rd Q 2019 Q2b series 2nd Q 2020 Q1 prototype 2nd Q 2020 CP series 2nd Q 2020 D1 prototype 1st Q 2021 Q3 series 2nd Q 2021 P5 QRX DFX D1 CP Q3 Q2b Q2a Q1 In principle more difficult the installation and have more interest for the WP15 and for Vac as allows instrumenting the Beam screen of Q1 ( the tick version) CP Q1 Q3 Q2a Q2b D1 HL LHC IT STRING 3rd Q 2019 2020 3rd Q 2021 2021 Marta Bajko for the TCC 5th October 2017

Marta Bajko for the TCC 5th October 2017 Integration slide 4 Integartion With SLOPE or not ( no request from CRG nor from magnets and Vac) Tooling : for Sc link and DFX installation Which set up point 1 or 5? Paolo Integration? The most complex one String should validate installation and dismounting procedures Magnets ordered by arrival option 2 Q2a prototype 1st-3rd Q 2019 Q2b series 2nd Q 2020 Q3 prototype 2nd Q 2020 CP series 2nd Q 2020 D1 prototype 1st Q 2021 Q1 series 2nd Q 2021 P5 QRX DFX D1 CP Q3 Q2b Q2a Q1 CP Q3 Q1 Q2a Q2b D1 HL LHC IT STRING 3rd Q 2019 2020 3rd Q 2021 2021 Marta Bajko for the TCC 5th October 2017

Marta Bajko for the TCC 15th September 2016 Cryogenics Cryogenics: Need of a quench buffer, 10 g/s recovery line at warm, operational pressure 20 bars Which cooling ( point 1 or point 5) Do we have spare DFX or we use a standard one? VHe in a cold mass = 25 l/ m? Herve? P5L is the most complicated and coherent set up with the Sm18 installations and the tunnel is the smallest . We plan to reproduce the space allowed in that place of the tunnel for the interventions Antonio Perin is working on the cryogenics. Together with MSC-TF and P. Gayet we are evaluating the pumping capacity for SM18 . The last conclusion made by L. Serio ( with SM18 UPG) was that no need of additional pumping. Marta Bajko for the TCC 15th September 2016

Magnets Inom is what we have considered thill now. 1 TC is planned In the phase of HWC of the STRING 120 quenches were estimated to be done till I nom. An other 50 quenches are planned to do with the goal of “special test” not done in the shadow of the HWC. Magnets Machine cycles…see with ABP Training till Inom? Iultimate? Provoked quenches with QHs to check propagation, QH delays Tracking test ( measurements during ramp?) Thermal cycle? Hardware Commissioning Special Tests Hardware Commissioning Special Tests The Current level has a non-negligible consequence on the energy deposition into the cold mass + extraction and so on the pumping capacity affecting finally also the planning 1 TC is planned Marta Bajko for the TCC 15th September 2016

Vacuum Beam Screens will be installed Beam screen? With dedicated instrumentation? Chaufrettes? De we have counted in the budget the beam screens? 700 kCHF extra cost?WP12?we would need for Q1 proto ( 166mm) and D1( 6mm dipole) proto , we have for the series but we need to instrument at least one ( 6 mm quad). Beam Screens will be installed Following the magnets availability and the needs in testing all type of beam screens we have: 3 instrumented: Q1 proto, D1 proto and Q2a or Q2b proto Marta Bajko for the TCC 15th September 2016

Planning ( Draft version) Marta Bajko for the TCC 15th September 2016

We plan to make 1 TC and approximately 200 quenches up to a Summary Today we do NOT consider to implement a SLOP for the IT STRING. P5L is the most complicated and coherent set up with the Sm18 installations We plan to make 1 TC and approximately 200 quenches up to a maximum of I nominal