SE503 Advanced Project Management

Slides:



Advertisements
Similar presentations
Chapter 7 Project Management
Advertisements

Critical Chain Project Management in the Supply Chain Presented By Greg Sullivan APICS Nashville Chapter 19 Feb 2008 Sullivan Group Consulting, Inc.
Sponsor: Dr. K.C. Chang Tony Chen Ehsan Esmaeilzadeh Ali Jarvandi Ning Lin Ryan O’Neil Spring 2010.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Project Uncertainty Management.
Critical Path and Gantt
Project Scheduling Basic Approach. projectA project is a collection of tasks that must be completed in minimum time or at minimal cost. activitiesIt is.
OPSM 639, C. Akkan1 Defining Risk Risk is –the undesirable events, their chances of occurring and their consequences. Some risk can be identified before.
Project Management March 9, 2001 Dr. Richard Chung Dept. Chemical & Materials Engineering San Jose State University.
OPER 576 Project Management Reducing Project Duration or Project Crashing Greg Magnan, Ph.D. May 20, 2004.
Dr. Godfried Williams1 Project Management – Topic 6 Lecture Content Planning Tools/Techniques Optimization Techniques Resource Planning & Allocation Linear.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Agile Principles: Leadership-Collaboration.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Chapter 10 Introduction to Simulation Modeling Monte Carlo Simulation.
Midterm Review SE503 Advanced Project Management.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
When Things Go Right Cornell’s PeopleSoft 8.9 Upgrade Lisa Stensland Manager, CIT Project Management Office May 15, 2008.
Critical Chain From “Theory of Constraints” Developed by Elihu Goldratt in 1984 Goldratt – Many of his key ideas were first explained via “business novels”
Quick Recap.
Time-Cost Tradeoffs Time-Cost Tradeoff Example Time-Cost Tradeoff Example (cont’d) Project Duration (weeks)Critical Path(s)Task(s) Reduced Total Direct.
IS 556 Enterprise Project Management 1IS 556 -Spring 2008 Lecture 2 Apr 7, 2008 //48.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
“WHY ARE PROJECTS ALWAYS LATE?” (“and what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations.
Presented by: Meysam rahimi
9-1 Chapter 9 Project Scheduling Chapter 9 Project Scheduling McGraw-Hill/Irwin Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Introduction.
VMcG 2/11/02 Critical Chain as an Extension to CPM Vincent McGevna, PMP February 11, 2002
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Project Management Software.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
SE503 Advanced Project Management
Project Planning with PERT and CPM Chapter 14
Change management control Sources of Change  Project scope changes  Implementation of contingency plans  Improvement changes ISE Ch. 6 1.
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
Project Time Management
Critical Chain Method These sides and note were prepared using 1. The book Streamlined: Building Lean Supply Chain Using the Theory of Constraints. Srinivasan.
1 Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources.
Critical Chain A Novel by Eliyahu Goldratt Copyright 1997.
SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Critical Chain Project Management.
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
IT-301 Project Management I: Unit 4: Cost Management.
Project Management Jukka A. Miettinen September 4, 2006
Chapter 16 – Project Management
Project Management Chapter 8.
SE503 Advanced Project Management
Project Management Chapter Topics
Project Management: PERT/CPM
Chapter 4: Project Management
Chapter 17 Project Management McGraw-Hill/Irwin
Chapter 6 Scheduling
Software Project Management
Critical Chain Project Scheduling
Class 27: Project Management Part II
ECE2799 Project Management
Projects: Critical Paths
Software Project Management
SE Tasks for a Concept Development Project
Risk Analysis & Success Driven Project Management
Project Management Operations -- Prof. Juran.
SE503 Advanced Project Management
Manajemen Industri Teknologi informasi
Project Management CPM/PERT Professor Ahmadi.
Project Management Dr. Michael Busing
Reducing Project Duration
Setting up a project file
Chapter 6 Scheduling
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Theory of Constraints Part II: TOC Concepts
Presentation transcript:

SE503 Advanced Project Management Dr. Ahmed Sameh, Ph.D. Professor, CS & IS Project Management Issues

History 1960’s 1980’s 1990’s 2000 Agile PM PERT, CPM, Monte Carlo simulation 1980’s Personal computers, PM software Teams, TQM, Concurrent Engineering 1990’s Widespread use of MS-Project Critical Chain PM Fuzzy Critical Path Method 2000 Agile PM Nothing has happened in 40 years?

Some PM Issues From “Critical Chain” Chapters 1-10 Will serve as a set of problems that we need to solve Will explore tools to solve these

Project Management is Relevant Much of what we do at work (or home) are projects Most projects fail to meet: Scope expectations Budget expectations Schedule expectations How do we define project success?

The Schedule is a Worthy Goal Finishing on time (or early) can be worth a large amount of money Economic benefits Market entry (new product) Finishing late can dramatically reduce project economic benefits Is schedule the most important aspect?

Uncertainty is the Culprit Uncertainty leads to overestimation Tasks expand to consume the available time/money Student’s syndrome Parkinson’s law Are tasks really overestimated by 50-100%? Can we improve behavior?

Gaussian Model Does Not Fit PM Normal curve is symmetrical Project variables are usually skewed Normal curve is infinite Most project variables have a practical minimum Most project variables have a practical maximum

Better Choices Beta distribution (PERT) Triangle distribution (approximation) How do we estimate the parameters?

Focusing on Cost is not Enough Cost cutting often comes at the expense of schedule or quality Reducing cost can damage the overall economic performance of a project How does this happen?

Early Start or Late Start? Early start (Push) Start all tasks as soon as possible Protects against delays Traditional method Late Start (JIT) Start all tasks as late as possible Improves focus on tasks Maximizes return on investment Minimizes damage, loss, effects of change Which is best?

Progress Reporting is Flawed Progress is often non-linear (80/20) Reports should focus on what remains, not what has been done (time, not %) Progress reporting causes people to lose focus on the overall goal Is this true? Why does it happen?

Summary Most projects fail to meet objectives Traditional project management is flawed Estimating Focus on cost Progress reporting Human behavior Uncertainty cannot be ignored