Highway 110 Project Update Molly Kline, Project Manager
Highway 110 Project Overview Project Location: From Highway 13/55 to 494 Estimate: $7.7 Million Construction: Summer of 2017
Construction Impacts Directional closures of Highway 110 between 35E NB ramps and 494 Anticipate 6 weeks in each direction Detour route will utilize 35E and 494
Municipal Consent Obtained April 19th Dakota Drive Access Drainage Easements
Corridor Wide Safety Improvements Turn Lane Extensions 35E, Hwy 149/Dodd Rd., Delaware, Church/Daycare, Charlton, and Mendota Road Reduced Conflict Intersection (RCI’s) Crown Point neighborhood Church and Daycare Redesign Charlton intersection and remove 2 median accesses creating 2 right-in, right-out accesses
Mendota Heights RCI Safety Improvements Daycare and Church Carmen Lane
Public Outreach Crown Point Neighborhood Meeting Held June 15th Numerous items were discussed Business Meeting scheduled for June 29th Public Open House planned for August, date TBD.
Project Contact Information Project Manager Molly Kline, Molly.Kline@state.mn.us 651-234-7723 http://www.dot.state.mn.us/metro/projects/ hwy110mendotaheights/index.html
Corridor Improvements-Delaware Turn lane extensions ADA updates Left turn lane extensions and ADA improvements will occur at this intersection.
Corridor Improvements-Charlton Road This intersection will see extended left and right turn lanes, off-set left turn lanes to increase sight distance, as well as ADA updates. This intersection is currently functioning in this same manner—with no left turns or through movements from Charlton Rd., so there is no change in access—only change in looks.
Mendota Road Improvements Left turn lane extension for EB 110, adding a flashing yellow arrow and ADA updates.
Charlton Rd. to Mendota Rd.
Highway 110 Project Overview Project includes: Pavement update Safety improvements Signing replacement and repair Drainage improvements ADA updates County trail underpass