MICE Partial Return Yoke Mechanical Design

Slides:



Advertisements
Similar presentations
Tagger and Vacuum Chamber Assembly Procedure. Outline. Assembly procedure for tagger and vacuum chamber. Support stands. Alignment.
Advertisements

SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Heavy Concrete Construction Formwork
CMS ZDC Crane Emergency Payload Removal Procedures This document proposes the viability of using a portable hydraulic actuator Hand crane (Davit crane)
Vacuum Vessel Production Readiness Review
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
CM30 University of Oxford Engineering session Peter Ford Tim Hayler Eddie Holtom Roy Preece Jason Tarrant Steve Virostek.
Chapter 7 Metals.
MICE Collaboration Meeting at Frascati, Jun 26~29, 2005 Iron Shield Mounting Design Stephanie Yang.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE RF and Coupling Coil Module Integration Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Module Vessel Connection Concept Steve Virostek Lawrence Berkeley National Laboratory AFC Module Meeting April 23, 2004.
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Progress on the Coupling Coil & Focus Coil Interface Engineering
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
EBD existing crane details and future bridge crane upgrade Alev Ibrahimov June
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE Integration Engineering Jason Tarrant - STFC l Contents »Device Interfaces – General »AFC »Spectrometer Solenoids »RFCC »EMR / KL »South Mezzanine.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Moment Connection Requires Bolts Outside the Flanges
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
PRY Implementation - Contents l Fit with Experimental Devices (& services connections) l Fit with Tracker Cryo l Fit with Floor & Trench l Fit with Mezzanine.
Step IV Construction North Side Walls and End Walls May 2015 Stephen Plate, Brookhaven National Laboratory.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
ORKA support - status report Scope of conceptual design task Develop a conceptual design for how to support the ORKA detector inside the CDF detector Develop.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
TPC Support Installation 26 Apr 2016Dan Wenman Mechanical Engineer1 Overview Installation of the support rails Details of the rail from the SAS to the.
Integration of the Spectrometer Solenoid Magnets
Roller/rail - System for PANDA
ProtoDUNE – DSS Installation, Alignment and QA
Outcome of the Review and Response to Recommendations
PANDA Yoke of the Magnet
Step IV PRY Preparation - Contents
Endcap shielding senarios:
PANDA Collaboration Meeting , BINP Sergey Pivovarov.
SiD Muon Yoke Structure - Deformation Studies -
Spectrometer Solenoid Fabrication Status and Schedule
Introduction Jason Tarrant – Integration Engineering Step IV Removal
SHMS Downstream Beamline Large SHMS/HMS Angles (Config-1)
Additional Upstream Coil Shielding
COLUMNS SLIDE SHOW.
Additional Upstream Coil Shielding
Senad Kudumovic Design engineer
Bunker Wall Design Wall ESS
Presentation transcript:

MICE Partial Return Yoke Mechanical Design 23 September 2013 Stephen R. Plate Brookhaven National Laboratory 9/23/2013

Outline Mechanical Requirements and Features Assembly Technique Obstructions Engineering Calculations Cost Estimate – Outside Fabrication 9/23/2013

Mechanical Requirements and Features Minimize impact on existing structures and equipment Magnets, Detectors False floor Mezzanine Service-way cabling to ISIS Sliding platforms Comply with crane lift limit of 8 tonnes Bolted connections Maximize reconfiguration possibilities for later phases of project Eliminate possibility of changes in magnetic properties due to welding Provide greater fit-up allowances during installation Access to solenoids and AFC Increased access through yoke using very recent 6-piece design 9/23/2013

PRY SHIELDING CONSTRUCTION OVERVIEW (Mezzanine placeholder) Load-sharing cross bars (4 of 8 shown) 5700 kg at 120mm thk (one backer + one plate section) PRY SHIELDING CONSTRUCTION OVERVIEW Steel framework False Floor downstream Splice joints (will become flanged) Avoid service-ways Location templates (temp tooling) 9/23/2013

Assembly Technique – major operations Locate/drill holes using footprint template Assemble south side framework in place under mezzanine Install shield sections #1 and #2, and new middle access section #5 with backing plates Install shield sections #3 and #4, and new middle access section #6 with backing plates ... (See following illustrations - NORTH side shown for convenience) 9/23/2013

Clearance to back of channel Hoist ring Install Section 1 Clearance to back of channel Machined surfaces on channel mate to pink bar Hoist ring spacer provides correct tilt Section 2 is similarly installed 9/23/2013

Install Section 3 (and 4) Lower hoist rings removed; guide blocks installed (also shown on isometric, Slide #4) Plate guided into engagement during lowering 9/23/2013

Install Restraint Bars All beam-to-channel connections will also be bolted 9/23/2013

(Assembly Technique – continued) … Install Virostek plate extensions Install spectrometer solenoids and AFC Build and install shielding on north side, same technique as south side Install north/south load-sharing cross bars 9/23/2013

Obstructions/Interferences Identification has been on-going several months Identified all now: spectrometer solenoid tie-downs, mezzanine and its column supports, vacuum ports, AFC access, etc. Work continues with input from J. Tarrant to modify the shielding and/or add required apertures to model as required. Magnetic analysis is done for each modification (H. Witte) as appropriate Construction drawings to follow 9/23/2013

DESIGN CHANGE Access to AFC SOLENOID SOLENOID AFC 9/23/2013

Engineering Calculations Magnetic forces vector ~8660 N, each of 4 shield sections North side in trench shown Dead weight 25,810 kg total 9/23/2013 Overturning moment

Moment Reaction, worst location 9/23/2013

Need Reaction Moment Overturning moment = 29.7x103 N-m [263x103 in-lb] Must be self-supporting before cross bars are attached To counteract safely, maintain compression of vertical beam legs with floor. Determine force required to do this; check with ANSYS Workbench RESULT 4 anchor bolts/leg, spaced 234 mm [9.21 in] apart, embedded 240 mm [9.5 in] RAL must provide adequate strength surface (5000 psi concrete floor or grouted support plates anchored to floor) 9/23/2013

Deflection under loads of gravity and magnetic forces, with cross bars attached 9/23/2013

(Play video) 9/23/2013

Cost Quotes / Estimates Shield plates, machined, 1008 steel From American Alloy Steel, Syracuse, NY, USA Material cost = $5600, each of eight plates Machining cost = $2850, each of eight plates Backing plates (4-pc design), mat’l only = $625 each of eight plates TOTAL = $72,600 Delivery: 12-14 weeks Shield plates, machined??, 1006 steel From JFE, Kurashiki, Japan Material + machining(??) cost = $6800, each of eight plates TOTAL = (6800+625 est)*8 = $59,400 Delivery: 16 weeks Shield plates, machined, 1006 steel From Tesla Engineering, UK TOTAL = £74,227 Delivery: 21 weeks Framework, both sides – estimate only (unburdened) Labor 580 hrs @ $110/hr = $63,800 Material = $17,000 (steel + aluminum + hardware) TOTAL = $80,800 9/23/2013

Work to complete Finalize modifications to shielding plates to avoid interferences, etc. Reposition legs Reposition drilled/tapped holes Insert in Virostek plate extension for slide-out of spectrometer solenoids (allow rise of solenoid by 50 mm) Slot(s) for tracker waveguides 6-piece design change for AFC access Structural Framework Shorten framework legs for installation of surveyed and grouted floor plates (accommodate uneven floor) Reposition/shorten restraint bars on South side (interference with mezzanine) Begin and complete manufacturing drawings in CY13 Shorten legs for installation of surveyed and grouted floor plates (accommodate uneven floor) 9/23/2013

BACK-UP INFORMATION 9/23/2013

9/23/2013

Floor bolting calculations, Page 1 9/23/2013

Floor bolting calculations, Page 2 9/23/2013

Floor bolting calculations, Page 3 9/23/2013

Floor bolting calculations, Page 4 9/23/2013

Floor bolting calculations, Page 5 9/23/2013

Floor bolting calculations, Page 6 9/23/2013

9/23/2013

9/23/2013

9/23/2013

9/23/2013