PROGRESS REPORT AS OF: END JULY 2017 CADANGAN TAMBAK LAUT SELUAS 66 EKAR UNTUK TUJUAN PEMBANGUNAN DI ATAS TANAH KERAJAAN KAWASAN BANDAR XL, DAERAH MELAKA TENGAH, MELAKA PHASE I – PLOT I AND E PHASE II – PLOT F, G, J, K, L PROGRESS REPORT AS OF: END JULY 2017
Executive Summary: Developer :- Egah Group Sdn Bhd Main Contractor :- Gold Palm Global Bhd Contract :- Execution & Completion Of Reclamation Works, Revetment Works & All Related Works Contract Period :- 15 September 2015 to 14 July 2016 (10 months) LAND RECLAMATION WORKS PLOT PLOT AREA (m2) AREA DONE (m2) PROGRESS (%) E 30351.495 29280.09 96.47% F 19587.289 18441.433 94.15% SL1 1505.735 0.00 0.0% G 13638.003 6918.559 50.73% I 96680.195 83908.741 86.79% SL2 12237.217 10229.089 83.59% SL3 3844.757 J 81343.413 SL4 16335.782 K 22581.171 L 2918 TOTAL 301023.057 m2 TOTAL AREA DONE 148777.912 m2 OVERALL RECLAMATION PROGRESS : 55.85% REVETMENT WORKS PLOT TOTAL LENGTH (m) ACTUAL DONE (m) PROGRESS (%) E 339.63 290 85.38% F 197.479 - SL1 14.628 G 155.348 I 780.446 633.976 81.23% SL2 20.319 100% SL3 30.676 J 461.233 SL4 31.089 K 322.249 TOTAL 2353.10 m TOTAL DONE 944.295 m OVERALL REVETMENT PROGRESS : 40.13%
Layout of 66 Acres
Work Progress
Mud Clearance using Longarm excavator at Plot I on 5/7/2017
Mobilizing Excavator to Plot I on 8/7/2017
Surveying Works for Revetment Repair at Plot I on 15/7/2017
Revetment Repair in progress at Plot I on 17/7/2017
Revetment Repair in progress at Plot I on 18/7/2017
Revetment Repair in progress at Plot I on 19/7/2017
Revetment Repair in progress at Plot I on 20/7/2017
Revetment Repair in progress at Plot I on 21/7/2017
Revetment Repair in progress at Plot I on 22/7/2017
Surveying Works for Revetment Repair at Plot E on 26/7/2017
Revetment Repair in progress at Plot I on 29/7/2017
Revetment Repair in progress at Plot I on 30/7/2017