Amtrak Fleet Strategy Plan Update 2011 Ken Uznanski Amtrak Policy and Development AASHTO Standing Committee on Rail Transportation 2011 Annual Meeting.

Slides:



Advertisements
Similar presentations
Amtrak Fleet Strategy Plan Update 2011 Ken Uznanski Amtrak Policy and Development AASHTO Standing Committee on Rail Transportation 2011 Annual Meeting.
Advertisements

EPTTOLA: ETCS Perspective
OHIO & LAKE ERIE REGIONAL RAIL CLEVELAND HUB STUDY Ohio Rail Development Commission TMACOG Annual Transportation Summit September 29, 2003.
Section 209 Activity Report September 12, 2011 Federal Railroad Administration.
Commuter Rail Vehicle Technology Analysis | 1 May 2007 Commuter Rail Vehicle Technology Analysis May, 2007.
I-95 Corridor Coalition December 14, 2001 I-95 Corridor Coalition Mid-Atlantic Rail Operations Study — An Integrated Strategy to Eliminate Choke Points.
Standardization Working Group Report
An Action Plan for the Restructuring and Rationalization of the National Intercity Rail Passenger System Briefing by the Amtrak Reform Council February.
The BGA Apollo Clean Transportation Manufacturing Action Plan  Modern Transit  High Speed Rail  Clean Freight Movement  Make it in America!
Lessons Learned from World Bank Work on Assessment of Agricultural Lab Capacity Needs in Developing Countries John E. Lamb Agro-investment Strategy Advisor.
Globalization of Markets : - Some Trends and Implications for Norwegian Industry Arild Aspelund, PhD.
NGEC - SFTF Structure and Finance Task Force Eric Curtit, MODOT Section 6 Project Update.
Economic Impact of Medical Education Expansion in Nevada & Recommended Approach FUTURE 1.
Railroad 101 Equipment April 9, Next Generation Corridor Equipment Committee  Established by Section 305 of the Passenger Rail Investment and Improvement.
Randy Wade TRB Intercity Passenger Rail Committee Tuesday January 25, 2011 Washington, DC.
LOW CARBON TRANSIT OPERATIONS PROGRAM [SB 862 (2014)] DECEMBER 2014.
Siemens sans siemens sans bold siemens sans italic siemens sans italic bold siemens sans black siemens black italic Siemens Building Technologies.
Program Update Baltimore MPO November 25, Internal Draft AGENDA  Program Overview  Alternatives Development  Stakeholder and Public Outreach.
Public Transit Department Bus and Fuel Procurement Strategy AzTA/ADOT Transit Conference April 2013.
Section 305 Technical Subcommittee Progress Report: Buy America Survey.
Freight Bottleneck Study Update to the Intermodal, Freight, and Safety Subcommittee of the Regional Transportation Council September 12, 2002 North Central.
High-Speed Intercity Passenger Rail Program March 14, 2011 Federal Railroad Administration.
PRIIA Section 305 Next Generation Equipment Pool Committee Ken Uznanski Amtrak Policy and Development SCORT National Meeting September 21, 2010.
Intercity Rail Background/ Statewide Freight and Passenger Rail Plan Update Met Council TAC Meeting November 5, 2008.
September 19 & 20, 2007 Items 4.11a,b, & c Tabs 15, 16, & 17 Proposition 1B Intercity Rail Bond Program.
The Crescent Corridor Intermodal Freight Project Improving Lives and Livelihoods IN & AROUND DC Washington, DC December 16,
NEW STRATEGY FOR TRANSPORT GOVERNANCE IN MONTREAL March EMTA Meeting, Madrid.
Developing State-Amtrak Agreements Stephen Gardner Vice President, Policy and Development March 8, 2010.
Amtrak Government Affairs Update NGEC Annual Meeting Matt Kelly Sr. Director, Government Affairs February 21, 2014.
Metro’s Capital Improvement Needs Presented to the National Capital Region Transportation Planning Board By Tom Harrington, Director of Long Range Planning.
Gauteng Strategic Plan Update Public Transport GDS 2055 Summit Hishaam Emeran, General Manager: Strategic Network Planning 7 September 2012.
00 Metropolitan Transit System Transit Serving Point Loma September 23, 2008.
1 Presented to the Transportation Planning Board October 15, 2008 Item 9 Metrobus Priority Corridor Network.
1 Transit Capacity Constraint Presented to: TPB Technical Committee April 1, 2005 Lora Byala Washington Metropolitan Area Transit Authority Office of Business.
Unit 5 Operations Management Location. Learning Objectives To be able to explain the causes and consequences of location and relocation – domestically.
Nate Asplund Director – Public Private Partnerships September 20, 2009 SCORT 2009 IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII.
DEMAND FORCASTING. Introduction: Demand forecasting means expectation about the future course of the market demand for a product. Demand forecasting is.
Review of 2016–2021 Strategic Budget Plan Development Process and 2016 Budget Assumptions Financial Administration and Audit Committee April 14,
Beyond Oil Transforming Transportation: A National Demonstration Project Breakout Session: A New Paradigm - Future of Transportation, Funding, and Climate.
Multi Agency Exchange May 16, 2017.
Using Public-Private Partnerships to Move More People The Story of HOT Lanes in Northern Virginia January 30, 2017 Morteza Farajian, Ph.D.
Strategic Information Systems Planning
Los Angeles – San Diego – San Luis Obispo Rail Corridor Update
Porter’s Competitive Forces
Review of 2018–2023 Strategic Budget Plan Development Process and
Tourism Growth Partnership – Round 5
Changes and Benefits brought from Modern Procurement to Bridge the Infrastructure Gap Remo Bucci, P.Eng Infrastructure and Capital Projects October 27,
NGTA Halton Planning and Public Works Committee
Introduction First established as Federal Express, today’s FedEx Corporation is one of the most recognized brands for their express delivery system, FedEx.
Capital Metro Long-Range Financial Forecast ( )
JSC “UKRAINIAN RAILWAY” (UZ) DEVELOPMENT STRATEGY FOR
Internet Interconnection
Midwest Rolling Stock - Section 6 Plan
Focus40 Overview A long-range plan for how the MBTA can meet the needs of the region in 2040: A 20-year plan as required by MBTA enabling legislation A.
Improving Energy Reliability & Performance
Improving Energy Reliability & Performance
Operations Management Introduction to operations Management 1.
International Strategy
AGM
NGEC Executive Board Chairman’s Report
Stevenson 5 Capacity Planning.
Environment Committee November 29, 2016
I-81 Corridor Improvement Plan
Capital Improvement Plans
AGM
North Suburban Planning Council
Next Steps for the NGEC Specification Development
India Energy Congress 2013 Sustainable Sources of Energy February 2013.
Report of the Technical Subcommittee
Chicago to Council Bluffs-Omaha
Presentation transcript:

Amtrak Fleet Strategy Plan Update 2011 Ken Uznanski Amtrak Policy and Development AASHTO Standing Committee on Rail Transportation 2011 Annual Meeting Charlotte, NC September 12, 2011

Amtrak Fleet Strategy Plan Initially Published February 2010 Why a comprehensive fleet plan? Intercity Passenger Rail in United States has unprecedented opportunity that must be addressed Amtrak, as the nation’s passenger railroad, will play a vital role Amtrak’s fleet is and will be at the heart of its ability to deliver competitive service, impacting all aspects of Amtrak services History of underinvestment has constrained Amtrak’s ability to deliver modern and reliable services our customers deserve Average age of equipment in the existing Amtrak Fleet is approaching 25 years Essential need for recapitalization of the fleet to sustain and grow service Continuing, predictable equipment replacement plan is needed to rebuild and stabilize supplier base Fleet Strategy Plan Update 2011 Further refines and updates previous plan Addresses new developments Responds to feedback received from stakeholders

Fleet Strategy Plan Objectives Replace our aging fleet with modern equipment Buy equipment in a manner that will develop and support a viable manufacturing base and fleet Orders of sufficient size to attract, develop and sustain a robust car building industry Deliveries spread out over period of years, to allow for economical use of manufacturing plant, ease of incorporation into fleet Allows us to ‘debug’ issues on small batches of new equipment at the beginning of a production run Establish guidelines for the commercial life of new equipment Establish a foundation for continuing fleet plan update Determinations of demand so that we can estimate costs, capacities, and fleet size Numbers aren’t chiseled in stone – will change as the plan develops in response to changing economic and technical conditions Why is this such an urgent need?

Amtrak’s Diesel Locomotive Utilization Average annual miles 162,000 146,000 91,000 66,000 63,000 42,000 44,000 45,000

Amtrak Electric Locomotive Utilization Average annual miles

Amtrak’s Average Annual Car Miles – Highest in US Passenger Rail Operate 24x7, turnaround in 4 to 6 hours Commuters: Maintained nights, weekends, off-peak Average annual miles (in thousands) Amtrak

2011 Fleet Composition – Road Locomotives Equip Type In Service Build Year Age in 2011 Average Mileage Acela Power Cars 40 1999-2000 10-12 years 1.2 million AEM-7 49 1980-1988 23-31 years 3.5 million HHP-8 15 1999-2001 750,000 P-32 DM 18 1995-1998 13-16 years 1.4 million P32 1991 20 years 1.9 million P40 0* 1993 18 years 1.8 million P42 207 1996-2001 11-15 years F-59PHI 21 1998 13 years 1.3 million Electric Diesel *15 are being returned to service with ARRA funding 7

2011 Fleet Composition - Cars Equip Type In Service Build Year Age in 2011 Service Average Mileage Acela 120 1999-2000 11-12 years NEC 1.2 million Talgo 29 1999 12 years SD 1.7 million Amfleet I 412† 1974-1977 34-37 years NEC/SD 3.8 million Amfleet II 144‡ 1980-1981 30-32 years LD/SD 5.1 million Superliner I 249§ 1979-1981 20-32 years LD 5.5 million Superliner II 184+ 1994-1996 15-17 years 2.9 million Viewliner 50± 1995-1996 15-16 years 2.5 million Horizon 97 1989-1990 21-22 years 2.4 million Metroliner 17 1967 44 years Unknown* Heritage 92 1948-1956 55-63 years †55 will be returned to service with ARRA funding ‡5 will be returned to service with ARRA funding §14 will be returned to service with ARRA funding +6 will be returned to service with ARRA funding ±1 will be returned to service with ARRA funding *Mileage for equipment that predates Amtrak is unknown – but in some cases includes 20+ years of daily revenue service

Major Fleet Issues Age of equipment is at an all-time high: Average Amtrak car is now older than the average car we inherited in 1971 Heritage equipment is pushing (and in some cases past) sixty years Lack of homogeneity (multiple classes of equipment for short and long distance and corridor service) complicates maintenance Complete standardization will never be possible – but we need to reduce the number of classes and mechanically distinct variants Sizes of equipment classes vary widely, and mass obsolescence is a problem Supply base is limited – lack of market demand led to market exit Transit and commuter rail have taken attention of remaining manufacturers Amtrak needs to take a lead, or: Market will offer equipment not optimized for intercity service Limited range of choices may lead to increased cost and risks Industry may continue to atrophy

Major components of the 2010 Fleet Plan Set limits on maximum equipment age (“lifing”) Need to retire 60 year old equipment Need to determine useful life and commercial life Useful life is the maximum period we want to have equipment in service – 30 years for engines, 40 years for passenger cars Commercial life is the period when the equipment is maintainable, technically viable and commercially attractive for its designed service Estimate ridership demand in future years Develop assumptions for costs and production/purchase rates Include associated costs (acquisition, maintenance, etc.) Create demand for every type of equipment, and provide potential economies of scale and consistency for suppliers and state partners 10

Major components of the 2010 Fleet Plan (cont’d) Commercial life of equipment is set in plan; from 20-30 years (depending on equipment type) Plan designed for 2% ridership growth on existing services – but procurement model allows us to easily expand order sizes based on Requirements of new corridors (Sec 305 committee) Large-scale growth beyond conservative levels Average cost is about $743 million per year Total anticipated cost in 2009 dollars will be $11 billion through 2023 $23 billion through 2040 These costs include associated improvements to maintenance facilities, provision of spare parts, and provision of fleet overhaul services for the period Total fleet procurement over a 30 year period will include more than 2,500 cars and 700 locomotives, independent of needs for projected state-supported corridors and new services

Fleet Plan—Equipment Life Policy Amtrak defined equipment life policy Careful analysis of needs throughout the organization was performed Marketing/Customer focus Mechanical Financial considerations Commercial life goals for each fleet type developed for fleet recapitalization Commercial life goals: Electric Locomotives - 25 years Diesel Locomotives - 20 years Single Level Coach - 30 years Bi-Level Coach - 30 years Tier I Trainset - 25 years Tier II Trainset - 20 years Actual life of equipment will depend on tactical requirements

Amtrak Fleet Acquisition Plan Provides for a smoothed acquisition of high volume vehicle types Grouped acquisition of lower volume vehicle types Steady state procurement Approximately 65 single level cars per year Approximately 35 bi-level cars per year 70 electric locomotives under present procurement Begin acquisition of 265 diesel locomotives at rate of 25 per year Replace switcher fleet at rate of 10 per year Actual batch sizes and composition will be determined as necessary Coordination with PRIIA Section 305 Baseline that is scalable to accommodate state needs

A snapshot of the present Florida-bound Silver Star at Seabrook, Maryland Heritage diner (1948-1958) Heritage baggage car (1946-1976) AEM-7 DC electric locomotive (1980) Viewliner sleeping cars (1995-1996) Amfleet II coaches and lounge car (1981-1983) Bob Pickering photo

A vision for the future Double the existing fleet by 2040 Maintenance of a “younger” fleet thereafter Acquisition and maintenance policies that support the projected age profile Work with states on equipment pool committee (Sec 305 of PRIIA) for additional acquisition needs A thriving railcar industry that supports our equipment needs

Current Amtrak Equipment Aquisitions Long Distance Single Level Program 130 car procurement awarded to CAF, USA in June 2010 Will replace Heritage cars and bolster capacity of fleet Deliveries begin October 2012 Electric Locomotives Contract awarded to Siemens Transportation for 70 new electric locomotives in September 2010 Replaces all electric locomotives on NEC with single type First locomotive for testing to be delivered December 2012

Fleet Strategy Plan Update Fleet Strategy Plan is to be updated on an annual basis Previous plan was issued in February 2010 The update is an evolutionary rather than revolutionary one Much of the plan is unchanged Updates are provided where circumstances have moved on External feedback has been added to internal updates The new plan brings all of this together

Summary of the 2010 Fleet Strategy Plan Assumed growth of 2% per annum across the fleet Long term acquisition of approximately 65 single level cars per year Long term acquisition of approximately 35 bi-level cars per year Expansion of the electric locomotive order to 70 locomotives Commencement of acquisition of diesel locomotives Review the proposed expansion options for Acela Long term plan for acquisition of Acela replacement Funding requirements include equipment, project management (5%), spares and maintenance infrastructure upgrades 30 year time horizon for the fleet strategy plan

Feedback from the 2010 Fleet Strategy Plan Briefings were provided to industry groups and political staffers External interests provided comments directly OIG Review Comments received included: The 2% growth assumptions are not sufficient Bi-level vehicle introduction would be cost beneficial Life assumptions are too short Demand level is too small for industry to be competitive Where will the funding come from?

What has Changed for 2011? Aligned the plan to fiscal rather than calendar years Address LDSL and electric locomotive orders that have been placed Update the funding requirements based on actual costs incurred Acela Include the 40 additional cars for the Acela fleet (2 per trainset) Add the additional Acela II trainsets proposed for service doubling in 2017 in parallel with the planned growth of NEC Regional service Replacement of Acela pushed out 1-3 years based on financing constraints and to gain maximum benefit of the planned investments Re-profiled the delivery schedules based on Section 305 NGEC specification developments with the states Realigned the Amfleet II and Amfleet I replacements Provided for the potential introduction of bi-level corridor cars in the Midwest

How Do the Changes Address Feedback from 2010? The baseline assumptions have not changed 2% is well below recent growth levels It is hard to argue with the base case as being too ambitious The fleet plan is scalable once it is implemented Higher levels of demand are not justified by the current projections Bi-Level car types are introduced as a potential for the Midwest. NEC is less likely but will be reviewed further Life assumptions are unchanged. Analysis of life cycle costs suggests they are actually conservative. Amtrak’s demand is insufficient to sustain the domestic car building industry alone and this cannot change that situation Funding is assumed in this plan. If funding is not available, the plan will not be implemented

Fleet Strategy Plan Update Equipment Requirements Years 1 to 15 904 single level cars 420 bi-level cars 70 electric locomotives 280 diesel locomotives 40 high speed trainsets and 40 additional cars for the existing trainsets Total acquisition cost (FY11 values) $12.3bn Years 16-30 592 single level cars 511 bi-level cars 300 diesel locomotives 40 high speed trainsets Total acquisition cost (FY11) values $12.7bn

What is not in the 2011 Plan Update? Very high speed equipment for the minimum operating segment between NYC and PHL is discussed but not quantified State equipment needs funded through HSIPR grants Any infrastructure issues outside maintenance facilities, e.g. stations, track condition, power supplies, catenary. Upgrades necessary to improve performance of the existing equipment Enhancements necessary to accommodate a growth in the service from additional equipment New maintenance facilities or significant expansion of facilities for additional capacity are not included Upgrade to the current facilities for new equipment is included Infrastructure upgrades are not optional when acquiring equipment Capacity growth above the 2% projection. Actual growth is above 2% and has average that for a number of years Additional equipment to meet that growth can be accommodated through scaling of the core plan but will require additional capital funding

Future Fleet Strategy Plan Updates Future Fleet Strategy Plan Updates will likely include: Further Refinement of Assumptions and Costs Traditional Single Car consists and merits of Integrated (fixed consist) Trainsets Opportunities provided by state/multi-state procurements Integration of PRIIA Section 305 Specifications and potential partnerships Refinement of Maintenance Facility needs Very High Speed Rail Development