Cryoplant Installation Scope

Slides:



Advertisements
Similar presentations
ZONE 18 CRYOGENICS M. Sanmarti On behalf of AT-ACR-OP section.
Advertisements

ESS Cryogenic System Design
Current status Arkadiy Klebaner November 21, 2012
ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
12 GeV Upgrade of Cryogenics at Jefferson Laboratory (Jlab) Dana Arenius Engineering Division Cryogenic Systems ILC08 Nov This work is supported.
Engineering and Design Group Fermi National Accelerator Laboratory Cryogenic Department AAC Review, May , 2005 Jay Theilacker HPTFCRYOGENICS.
SOFT 2004 OVERVIEW OF CRYOGENIC TECHNOLOGY FOR THE THERMONUCLEAR FUSION P. DAUGUET, M. BONNETON, P. BRIEND, F. DELCAYRE, B. HILBERT, A. RAVEX Air Liquide.
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
April, 2009 ERL SRF CRYO MODULES AND CRYOGENIC SYSTEM.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
The ESS Cryogenics System J. G. Weisend II, P. Arnold, J Fydrych, W. Hees, J. Jurns, A. Lundmark, X. T. Su, X.L. Wang June 2015.
April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
TAC2 Alpi consolidation in Cryogenics and Cryomodules.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
NML Cryogenic System Arkadiy Klebaner Cryomodule One Commissioning June 3, 2011.
LCLS-II Cryoplant Overview
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
Project X Workshop - Cryogenics1 Project X CRYOGENICS Arkadiy Klebaner.
CRYOGENIC SYSTEM of RAON Chul Jin Choi, Ki Woong Lee Cryogenics and Control Team Accelerator Division 5/23/2013 Chul Jin Choi, Ki Woong Lee Cryogenics.
Thomas Jefferson National Accelerator Facility LCLS September 13, 2013 Dana Arenius Rao Ganni Jefferson Laboratory Sept 13, 2013 CRYOGENIC SYSTEMS.
Makara, Aug. 17, Cryo Dept. Shutdown Status.
Energy efficiency considerations in cryogenics Philipp Arnold Section Leader Cryogenics Proton Driver Efficiency Workshop.
1 Young-Ju Lee Vacuum & Cryogenic Engineering Team National Fusion Research Institute Young-Ju Lee Vacuum & Cryogenic Engineering Team National Fusion.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
Installation Package - Electrical
Hongyu Bai LCLS-II 2 K Cold Box PDR September 27, 2016
Cryoplant Installation Organization
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
Cryoplant Installation Cost and Schedule Installation PDR
Cryoplant Controls Installation
Study and Development of Large Cryogenic Systems in China
Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016
Process Requirements and Design Approach
2 K Coldbox Safety and ESH
2K Cold Box FDR Introduction
He Plant, LN2 Systems and Commissioing
Process Simulation for the LCLS-II Cryogenic Systems
2K Cold Box PDR Introduction
FRIB Cryogenic Support
Cryoplant Installation Overview
Online Helium Inventory Monitoring of JLab Cryogenic Systems
N. Hasan1, P. Knudsen2 and V. Ganni2
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
LCLS-II 2K Cold Box Controls Design Review
SPS cryogenic proximity equipment and SM18 validation
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Cryogenic System Operation and the Progress of SSRF II
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
Testing/Commissioning of 2 K Cold Box
2K Cold Box Process Design
2K Cold Box Mechanical Design
Mathew C. Wright October 2016
Cryogenic Plant Controls – Safety Switches
Pressure Piping Analysis
ILC Experimental Hall Cryogenics An Overview
LCLS-II Cryoplant Controls FDR Status of Past Reviews and Lessons Learned Dana Arenius Sept 13, 2017.
ESR 2 Presented to Joint Hall A/C Summer Meeting
Scope, Requirements Deliverables & Schedule
Overarching Commissioning Plan
Operator Training Requirements
SNS Cryoplant Commissioning Past Experiences
CryoPlant Commissioning
ESR2 Process Cycle Design
ESR2 Process Cycle Design
Presentation transcript:

Cryoplant Installation Scope Mike Bevins LCLS-II Cryoplant Installation PDR October 18, 2016

Cryoplant Installation Scope Outline Introduction of cryogenic cryoplants Cryoplants layout Equipment list Cryoplant Installation Scope Cryoplant installation and commissioning sequence CP1 installation Phase I and II CP2 installation Phase I and II LCLS-II Director’s Review, 30 August-1 September, 2016

2 Cryogenic Plants for Normal Beam Operations Equivalent capacity ~ 18 kW@4.5K each Cryoplants (JLAB) U-tube Jumper for 1st light CDS (FNAL) CM (FNAL&JLAB) Upstream string Downstream string

Equipment List Common subsystems for CP1 and CP2 30,000 Gallon Gas Helium storage tanks (6) 30,000 Gallon LN2 storage dewar Purification system – dual beds Recover compressor – 18 g/s (2) Guard vacuum system Oil Processor Instrument air system (2) Control UPS and Emergency Generator Subsystems for each CP Warm helium compressor and MCC(6) Gas distribution system Oil Removal System 4.5 K Coldbox: Upper CBX and Lower CBX Ambient heat exchangers 10,000 liter LHe dewar 2 K coldbox, cold compressors (6) Cryogenic transfer lines Interface box Control system

Cryoplant Building 2 CDS Transfer lines Cold Box Room Compressor Room 1 Compressor Room 2 Cold Box Room 2 CDS Transfer lines

Layout of Cryoplants LN2 storage GHe storage Cryoplant 1 Interface box 6

Installation Phases of 2 cryoplants CP1 Installation Phase 1 CP2 Installation Phase 1 CP2 Installation Phase 2 CP1 Installation Phase 2 Upstream string Downstream string

Cryoplant commissioning 1/2018 CP1 Installation Phase I Comm. Of GHe, LN2, He purifier 3/2018 Comm. of WHC system CP1 Completed 2/2019 7/2018 Comm. of CP1 4.5K CBX 9/2018 CP1 Installation Phase II Comm. of CP1 2K CBX 1/2019 CP1 Full system Comm. 4/2019 CP2 Installation Phase I Comm. of WHC system CP2 Completed 11/2019 5/2019 Comm. of CP2 4.5K CBX 6/2019 CP2 Installation Phase II Comm. of CP2 2K CBX 10/2019 CP2 Full system Comm.

CP1 Installation Phase 1 GHe vessels LN2 vessels LN2 transfer line Recovery compressor Purifier Instrument air compressor CP1 WHC (6) CP1 MCC Gas management panel CP1 ORS Oil processor skid CP1 WHC piping Cooling water piping Control 9

CP1 Installation Phase 1 (cont’d) - Sample pictures 30,000 Gallon LN2 Dewar 78’(L)*11’(W)*12’(H) 103,000 lbs (E) 6 * 30,000 Gallon GHe Tank 47’(L)*11’(W)*13’(H) 50,000 lbs Purifier (60g/s) Motor Skid Cooler Skid 6 Warm helium compressors MCC ORS Vessels

CP1 Installation Phase 2 CP1 4.5K coldbox CP1 LHe dewar CP1 CC CP1 cryogenic transfer lines & piping 2K CBX control Guard vacuum pump CP1 Interface box CP1 Control 11

CP1 Installation Phase 2 (cont’d) - 4.5K Cold Box Vendor Integration Turbines Instrument panel Cabinet and wiring Control valves Transfer line

CP1 Installation Phase 2 (cont’d) - Other equipment Transfer lines and U-tubes 10,000 LHe dewar Ambient Heat exchangers LCLS-II 2K CBX (Φ12’*12’H) Magnetic Bearing and VFD Cabinets

Interface boxes to CDS 4.5K CBX 2K CBX 4.5K CBX 2K CBX The transfer line will be delivered in 4 sections which are to be welded together at SLAC. Welded to Surface TL In CDS CDS

CP2 Installation Installation Phase 2 Installation Phase 1 Phase I CP2 WHC (6) CP2 MCC Gas management panel CP2 ORS CP2 WHC piping Cooling water piping Control Instrument air compressor Phase II CP2 4.5K coldbox CP2 LHe dewar CP2 CC CP2 2K coldbox CP2 cryogenic transfer lines & piping 2K CBX control CP2 Control Installation Phase 1 15