MICE CM29 Magnets Summary

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
Magnet Measurement Device for MICE F. Garnier, P-A. Giudici, F.Bergsma CERN MICE Collaboration Meeting No July 2011 Oxford technical drawings by.
MUTAC Review, 9 April MuCOOL and MICE Coupling Magnet Status Michael A. Green Lawrence Berkeley Laboratory Berkeley CA
Magnet quench during a training run Magnet electrical circuit schematic PROGRESS ON THE MODELING AND MODIFICATION OF THE MICE SUPERCONDUCTING SPECTROMETER.
Spectrometer Solenoids MICO 146 Steve Virostek LBNL June 6, 2011.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
The 23 rd MICE Collaboration Meeting -1- ICST/HIT Jan.13 to 17, Harbin/China Large Prototype Coil Test and Plan Fengyu Xu Institute of Cryogenics.
-1- Wang, Li The 23rd MICE Collaboration Meeting to 17 HIT/CHINA WANG, Li Institute of Cryogenics and Superconductivity Technology.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Cooling Channel Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration.
Tracker Solenoid Module Design Update Steve VirostekStephanie Yang Mike GreenWing Lau Lawrence Berkeley National LabOxford Physics MICE Collaboration Meeting.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
1 Superconducting Magnets for the MICE Channel Michael A. Green Oxford University Physics Department Oxford OX1-3RH, UK.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
12 March 2006NFMCC Meeting, IIT, Chicago1 Progress on the MICE Cooling Channel and Tracker Magnets Michael A. Green Lawrence Berkeley Laboratory.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
MICE Magnets - Virostek 11 MICE Magnets Steve Virostek Engineering Division Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
RF Cavity / Coupling Coil Module
Progress on the MuCool and MICE Coupling Coils * L. Wang a, X. K Liu a, F. Y. Xu a, A. B. Chen a, H. Pan a, H. Wu a, X. L. Guo a, S. X Zheng a, D. Summers.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
Office of Science 3/8/ LBNL MICE Project Status Spectrometer Solenoids, Coupling Coils and RFCC Modules Steve Gourlay MICE Project Board March.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
Spectrometer Solenoid Test Plan Workshop: Spectrometer Solenoid Overview Steve Virostek - LBNL February 17, 2012.
Some Thoughts on Magnetic Measurements for MICE Michael A. Green Lawrence Berkeley Laboratory Berkeley CA 94720, USA.
F. Garnier, P-A. Giudici, F.Bergsma CERN MICE Collaboration Meeting No. 28 Absorber Systems & MICE Magnets Session 6 October 2010 technical drawings by.
Magnet Measurement Device for MICE F. Garnier, P-A. Giudici, F.Bergsma CERN MICE Collaboration Meeting No. 29 RAL technical drawings by O.Jamet.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Preliminary Design for the Coupling Coil Cryostat in MICE
Abstract: The Muon Ionization Cooling Experiment (MICE) is an international effort sited at Rutherford Appleton Laboratory, which will demonstrate ionization.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE Cooling Channel Magnets: Spectrometer Solenoid Procurement RF Module Coupling Coil Proposal Steve Virostek Lawrence Berkeley National Lab NFMCC 07.
Magnet vacuum vessel w/radiation shield and cold mass in place Magnet leads (left) and the three cryocoolers on the top of the spectrometer solenoid service.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Spectrometer Solenoid – Quench Analysis The LBNL version of the quench model has been further refined - Heng Pan is finishing various quench scenarios.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
MICE/MuCool Coupling Magnets to 22 ICST/HIT MICE/Muool Coupling Magnets Progress Li Wang for MICE Group Institute of Cryogenics.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
MICE RF Coupling Coil Magnets Update Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory October 6, 2010 Sofia, Bulgaria.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
MICE/MuCool Coupling Magnets ICST/HIT Progress and Schedule for the MICE/MuCool Coupling Coil Project HIT MICE CC Project Group.
Progress on MICE RFCC Module for the MICE Experiment * Allan DeMello, Nord Andresen, Michael Green, Derun Li, Heng Pan, Steve Virostek, Michael Zisman.
Status of MICE Coupling Coil Magnets D. Li and M. Zisman Center for Beam Physics Lawrence Berkeley National Laboratory February 16, 2011 MICE CM29-Rutherford.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
MICE Spectrometer Solenoid Recovery Review - December 3-4, Steve Virostek MICE Spectrometer Solenoid Design and Assembly.
MICE CC Magnet Cryostat Design Overview Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MICE CC Cryostat Design Review LBNL, February.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
S. Feher MICE Magnet Readiness Review RAL, June 28th, 2016
Overview of the RFCC Module and 201-MHz Cavity Design
Spectrometer Solenoid Update
Spectrometer Solenoid Fabrication Status and Schedule
MICE Coupling Coil Update
Spectrometer Solenoid Update
Presentation transcript:

MICE CM29 Magnets Summary Mike Courthold 18Feb11

AFC Update & Plans

Recent Progress Recent Issues –slow getting the winding started Reported last meeting that there was some concern over the loss of bobbin temper after application of insulation. This was completed but there was a delay with remake of G10 insulation. Some high voltage tests have been done on current insulation system Tests completed on splice – results obtained in the nano-ohm region. These are being repeated but first indications are excellent. Improved thermal contact at top of HTS leads to improve the temperature margin. Personnel changes at Tesla have led to a review of items prior to winding to check that issues have not been forgotten.

Recent Progress Conductor tails - These now exit the coil in a copper half tube which provides good thermal sinking and mechanical support. Analysis suggests that this is a good solution and is required. These are slightly old drawings – the copper channels extend directly into the coil Cover removed for clarity

Recent Progress Assembly sequence still being refined Still need Mississippi to scrap a safety window to act as test piece. Quench protection heater sizing is ongoing. Test cryostat, for checking that the crycoolers meet specification before installation, now at Tesla, waiting for a window of opportunity to start tests. The recent leaving of Tom Frame (lead engineer), and a frank discussion with TESLA senior management re lack of progress, has precipitated a change of personnel and a reorganisation at TESLA.

Test Plan at RAL Outline test plan for the AFC when at RAL was presented Assumes delivery in early July Special conditions of testing without the lattice means that a support structure will be required for operation of the magnet in the MICE Hall The same/similar support will be required for transport. Assume that the tests will first be done with hydrogen and the absorber. It may be that the absorber will have to be taken out at the end of the tests to fit a solid one.

Status of MICE Coupling Coil Magnets D. Li and M. Zisman Center for Beam Physics Lawrence Berkeley National Laboratory

Current Status of the CC Magnets 1st coil winding complete in Dec. 2010 Coil winding at Qi Huan: last layer of SC wire (left) and finished Al banding (right) Latest cryostat design with 3 cryocoolers Status of MICE CC magnets, D. Li and M. Zisman, LBNL, Feb. 15-18, 2011

Summary of the Cryostat Design Updated design significantly improves performance Three cryocoolers More robust structure More spacing for MLI shielding and assembly Improved cooling circuit Easier assembly Easier access for repair and adjustment (if needed) Direct method to reference cold mass position to outside survey fiducial Status of MICE CC magnets, D. Li and M. Zisman, LBNL, Feb. 15-18, 2011

Summary of the HIT Tests Cryogenic system modified and rebuilt successfully new transfer lines and good vacuum Upgraded system able to cool dummy load to 4.2 K produced LHe accumulation (25% of the volume) Both current leads tested from 0 to 500 A very stable during 1 hour test period All cryogenic components tested successfully transfer lines, bayonets, cryogenic valve, insulators, feed-through and current leads all can be used for testing the large test coil and CC magnets Status of MICE CC magnets, D. Li and M. Zisman, LBNL, Feb. 15-18, 2011

Summary MICE CC magnet fabrication plan under way Slow to start, but has been progressing during past year Organization and responsibilities redefined LBNL has overall responsibility for MICE CC magnets Coil winding status indicated 1st MuCool coil winding complete at Qi Huan Corp. in Beijing, China Mandrels & cover plates for coils 2 & 3 fabricated MICE CC Cryostat design reviews completed at SINAP (Shanghai INstitute of Applied Physics) Two design reviews held in Sept. and Dec. 2010, respectively Three cryocoolers, improved cryostat and cooling circuit design 3D and 2D drawings to be completed at end of March 2011 Status of HIT (Harbin Institute of Technology) activities presented Update of ICST test system complete and initial tests done Preparations for welding of cold-mass cover plate in progress Updated plans to provide CCs being developed as part of MAP Status of MICE CC magnets, D. Li and M. Zisman, LBNL, Feb. 15-18, 2011

Spectrometer Solenoid Plans Steve Virostek Lawrence Berkeley National Lab

Technical Review and Recommendations MICE technical review held on 10/27/10 Final report w/recommendations issued 12/14/10 LBNL has reviewed the recommendations and prepared preliminary responses The committee recommended implementation of an active quench and lead protection system LBNL is conducting analyses to determine if an active system is necessary Other recommendations are related to the heat load calculations

Design Modification Plan A preliminary design modification plan has been developed by LBNL. The plan includes the following: - reduction of heat leaks to the cold mass - the addition of more cryo cooling power - assessment of the suitability of the passive quench protection system - modification of the LTS leads to prevent burn-out The plan has been detailed in a separate document The plan will be finalized once the quench analysis and design modification (if necessary) are complete

Preliminary Work A series of tasks to start immediately were proposed and have been approved by MICE management: Modify Shield 1 to match previous mods to Shield 2 Generate design layout of the 5 + 1 cooler arrangement and provide a spec to Wang NMR Develop a procedure for improved MLI bore wrapping Install a new 4” vacuum port on the cryostats After the 5+1 design layout is complete: modify the vacuum vessels and tower plates for the 5 + 1 design, add cryocooler holes in cold mass #2

Current Status The electromagnetic and heat load analyses are under way and expected to be completed in the coming days The quench and lead protection issue presents a major uncertainty in the completion of the plan Upon finalizing the modification plan, the Spectrometer Solenoid team will present the plan to MAP and subsequently the MICE tech board LBNL has been meeting with the vendor to begin preliminary work (approved by MICE) and to ensure the project restarts promptly when the plan is complete

Spectrometer solenoid quench protection MICE Collaboration Meeting #29 Rutherford Appleton Laboratory Soren Prestemon Lawrence Berkeley National Lab

Review The review committee recommends: to continue the analysis of the quench protection system, including Coupled transient magnetic and thermal calculations, eddy currents in the Aluminium mandrel, external circuits with shunt resistors. Investigation of different quench scenarios and definition of the hotspot temperatures of coils, leads and shunts. Definition of peak voltages: to ground, and layer to layer. Definition of the optimal shunt resistor values for all coils to reduce risk. Definition of the allowable peak operating current to eliminate the risk of coil damage. Measurement of the leakage current to ground for each coil, to check the status of electrical insulation. Limitation of the test current to 200 A until all points above are verified and understood. Design of the magnet test procedure ensuring a minimal risk of cold mass damage.

Planned simulations Code validation: Comparison with Wilson code for single coil case Evaluate current fluctuations, decay, voltages, hot-spot temperature throughout circuit in: Test configuration Operating configuration Evaluate role of quench-back from mandrel: Temperature rise and distribution in mandrel during a coil quench

Goals of simulations Main questions to be answered by 3D simulations: What are the maximum turn-to-turn and coil-to-ground voltages seen during a quench? Are there scenarios where a subset of coils quench, but others remain superconducting, resulting in slow decay through bypass diodes and resistors? What dI/dt will be “certain” to generate quench-back? What modifications to the existing system should be incorporated to minimize/eliminate risk to the system in case of quench

General approach towards repair Address reviewer concerns essentially same as the project team’s Use simulations to guide final decision on protection system repairs Allow repair strategy to crystallize based on results Develop clear strategy for protection modifications Develop test and operational controls to support magnet protection

Magnetic Measurement Plans Pierrick Hanlet

Purpose Characterization of magnets Two Sets of Measurements ·At vendors: Determine magnets operate according to specifications ·In situ in MICE hall real configurations & real environment check field alignment check field uniformity check field consistent with Maxwell fringe fields

Purpose Additional reasons: ●Determine if simulation matches data ●Fringe fields ● Force models ●Nearby equipment (pumps, electronics, ...) ●Global tracking ●Relative and global alignment ●Scale with fixed hall probes

Tasks – before mapping What do we need to know? How do we quantify field error contributions to emittance? Uniformity, positions, magnitudes ·What can we do analytically? ·What simulations do we need? ·How to convert map to G4MICE map? Introduce conversion errors? What grid step size?

Magnet Measurement Device for MICE F. Garnier, P-A. Giudici, F.Bergsma CERN

Disk with 7 B-sensors calibrated at 4.5 Tesla Beam axis Tooth belt Magnet bore Rails ¼ pipe of aluminum Cradle

This flange cannot be removed and cannot be surpassed by rail support Extension disk for AFC 5m version for spectrometer solenoids 2m version for focus absorber solenoids. Extension disk to by-pass internal flange AFC Need to measure from both sides 2m version could be used to measure eventually coupling coils dismountable

Pin holes made by CNC machine

Strategy mechanics: 1 build 5 m version , test precision with laser tracker 2 if precision insufficient add encoder and rack and/or foresee laser tracker during measurements etc 3 build 2 m version DAQ: Build simple read-out for 7 B-sensors Anticipate to have interface outside high field region Accuracy: < 0.5 mm longitudinal +/- 0.5mm radial Theta +/- 1 mrad Bx,By,Bz +/- 2 mT Check in situ with NMR on service module

Status 6 m Alu pipe of 40 cm bore arrived, segment cut, principle seems to work Cradles: designed, will be produced outside CERN, rectified inside CERN Rails: ordered , will arrive in one month Chariot: designed, must be build Motion: standard BALDOR motion controller, drive and motor (available) Maybe encoder on rack (unlikely), encoder exist, rack must be ordered B-sensors ready and calibrated Read-out: basics exist ( used in calibrator with 4 cards), parts exist duplicate electronics board should be send to CERN ! Ready at August 2011 for AFC (small version)

Other Magnet Considerations Global hardware/software solutions where possible Coordinating magnet integration includes: Ability to move magnets between Steps Need to consider practicalities of performing field-mapping of individual magnes in the MICE Hall Mapping machine requires 0.5m minimum clearance at one end, and ~1m at the other