26.10.2016 EN-EL-FC Activity Jeremy Blanc, EN-EL-FC
Fibre Optics Activity SPS BPM Upgrade Phase 2 Installation of ducts, blowing of cables and termination. BA2 Surface and Shaft 650 m of ducts / 1875 m of optical cable 14 days BA3 Surface 50 m of ducts / 250 m of optical cable 7 days BA4 Surface 30 m of ducts / 150 m of optical cable TS4- 2525 m of ducts / 5414 m of optical cable 17 days 26.10.2016 Jeremy Blanc, EN-EL-FC
Fibre Optics Activity Replacement of Radiation Sensitive Optical Fibres Removal and blowing of cables. TI2 (from RA3830=BA7) 17 cables / 16.6 km 11 days TI8 (from RA1228=HCA442) 31 cables / 41.3 km 17 days TI2 TI8 26.10.2016 Jeremy Blanc, EN-EL-FC
Fibre Optics Activity Various Optical Fibres Installation Pulling/Blowing of cable. BA3 Surface 2 cables / 95 m 2 days BA4/BB4 Surface 1 cables / 150 m 1 day BA5 Surface 3 cables / 90 m 3 days 26.10.2016 Jeremy Blanc, EN-EL-FC
Fibre Optics Activity Crab Cavity Installation of ducts + Pulling/Blowing of cable. BA6 Surface 1 duct / 90 m 4 cables / 360 m 4 days TA6 Alcove 1 cable / 30 m 1 day LSS6- 2 cables / 175 m 3 days 26.10.2016 Jeremy Blanc, EN-EL-FC
Fibre Optics Activity New SPS Access System Pulling/Blowing of cable. ECA5 2 cables / 200 m 4 days BA6 Surface 1 cables / 100 m Pilot Installation 26.10.2016 Jeremy Blanc, EN-EL-FC
Fibre Optics Activity Planning & Constraints False floor need to be opened for installation in surface TI2 & TI8 will be blocked by drums during the cables removal (no coactivity) TS4- will be blocked during the duct installation (no coactivity) Support: Transport for moving OF cable drums Radioprotection for checking the OF cables removed from TI2 & TI8 26.10.2016 Jeremy Blanc, EN-EL-FC