Configuration Management and Layout Database ELENA Project

Slides:



Advertisements
Similar presentations
02/06/20141 WHAT ITEM IS COMPOSED OF ? INTEGRATION MODEL DETAIL MODEL SKELETON 3D ENVELOP PART 1 PART 2 PART XXX… EQUIPMENT ITEM INTEGRATION OFFICE RESPONSIBILITY.
Advertisements

Overview of Data Management solutions for the Control and Operation of the CERN Accelerators Database Futures Workshop, CERN June 2011 Zory Zaharieva,
360 Panoramic Photographs Capture, Processing, Layout Database T. Birtwistle EN-MEF-DC.
14 December 2006 CO3 Data Management section Controls group Accelerator & Beams department Limits of Responsibilities in our Domains of Activities Ronny.
CERN Accelerators Topology Configuration and Change Management Engineering Department Thomas Birtwistle, Samy Chemli – EN/MEF/DC.
HL-LHC Configuration Management Keywords : HW Baseline, Naming, Parameters, Layout DB, Change Control The HiLumi LHC Design Study (a sub-system of HL-LHC)
CLIC Project breakdown structure: organization, documentation and cost estimate Beam Instrumentation Workshop, June 2-3, 2009 CLIC Project breakdown structure:
LHC Hardware Commissioning Review May 2005, CERN, 1211 Geneva 23 1 LHC Hardware Commissioning Review Contribution ID: 20 – Quality assurance and.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
1 1. Some recent views ( ) 2 Linac tunnel
ANKITHA CHOWDARY GARAPATI
Margarita Saifoulina BE/RF/SR. Outline Data Management EDMS & MTF for RF structures Future prospects for EDMS/MTF solution Data Management EDMS & MTF.
Samy Chemli – Configuration Management - S. Chemli EN-MEF – Contents Configuration Management Hardware Baseline Change Management.
MTF – Manufacturing and Test Folder Large Scale Deployment of MTF Sonia Mallón Amérigo Elena Manola-Poggioli on behalf of the EDMS Team, TS-CSE.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
Rack Wizard LECC 2003 Frank Glege. LECC Frank Glege - CERN2/12 Content CMS databases - overview The equipment database The Rack Wizard.
Application of a CAMMS to CERN’s cryogenic installation park G. Perinić and S. Knoops, CERN.
ELENA Hardware Baseline Current Document Status T. Birtwistle EN-MEF-DC.
ELENA EXTRACTION LINES W. Bartmann, D. Barna, M. Fraser, J. Jentzsch, R. Ostojic ELENA Commissioning discussion, 23th November, 2015.
Equipment Management Folder / MTF Travellers. Product Data Management A huge amount of product and engineering data stored in CERN databases – Design.
Review of the processes released in the framework of the MMP Goran Perinić.
Philip Schwarz TE-MSC-MNC 1 Engineering Specifications for ELENA ring and TL magnets Philip Schwarz on behalf of WP 2.2 ELENA IIC meeting 5 th December.
ELENA Documentation and Data Management Items, Assets, Functional Positions T. Birtwistle EN-ACE-CL With input from T. Krastev EN-ACE-EDM.
Database - How to keep BI information up to date? Samy Chemli on behalf of EN-MEF-DC.
Quality Assurance for LHC Gas Systems Stefan Haider / EP-TA1.
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
Product Lifecycle Management with the CERN EDMS David Widegren CERN, TS/CSE 8 Nov 2005EDMS:
ELENA Layout Naming Convention F. Butin / ELENA collaboration.
Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
ELENA installation progress F. Butin / ELENA collaboration.
Breakdown Work Structure Applying Management Tools to a Project.
Vacuum System P. Chiggiato TE-VSC
Accelerator Readiness Review October 31, 2006
Linac4-PSB 160 MeV connection readiness review
Software Project Configuration Management
A monitoring system for the beam-based feedbacks in the LHC
East Area Renovation Project Team meeting # 2 – EDMS News
Beam Interlock System SPS CIBU Connection Review
Chapter 11 Designing Inputs, Outputs, and Controls.
FCT and CERN Portuguese Trainee Programme Report
R. Denz, A. Gomez Alonso, AT-MEL-PM
Chapter 6: Database Project Management
CLIC module working group
ELENA installation and commissioning status
The HL-LHC Circuits: Global View and Open Questions
Document Plan & Milestones WP7
Configuration Management and Prince2
Layout Drawings and Mechanical Assembly Drawings
The MTF adjusted system to meet Vacuum Group needs
SPS CC: Final plan for interlocking of crab cavities in SPS
Software Developer for Vacuum Control System (BE3528)
East Hall under construction
HL-LHC Safety Assessment Process
Update on the PSB Transfer Lines
GIS Portal Racks Project
HMSWeb – Handover Management System
Programmable Logic Controllers (PLCs) An Overview.
Course: Module: Lesson # & Name Instructional Material 1 of 32 Lesson Delivery Mode: Lesson Duration: Document Name: 1. Professional Diploma in ERP Systems.
COMP 208/214/215/216 – Lecture 7 Documenting Design.
This presentation document has been prepared by Vault Intelligence Limited (“Vault") and is intended for off line demonstration, presentation and educational.
Metadata The metadata contains
Final Design Authorization
Configuration Management
PSS0 Configuration Management,
Introduction of PTM (Planning Tracking & Management) Tool - developed by Meridian Technology 29/05/2019.
East Hall under construction
HL-LHC Quality management
Presentation transcript:

Configuration Management and Layout Database ELENA Project T. Birtwistle (EN/MEF/DC) – 21st May 2015

Contents Configuration and Layout Overview Basics of the Layout Database Current status of ELENA in the database Future layout updates Product Breakdown Structure (PBS) data

Configuration and Layout Overview Consistency between information sources Survey Integration Optics (MADX) Layout Hardware Baseline (PBS) Items and Assets

Layout Database Basics Stores the sequence (layout) of accelerator and transfer line components: Equipment types and details Functional positions for mechanical and electrical layouts Asset names – layout can display information from MTF Updated as a result of ECRs Accessible to all CERN users https://cern.ch/layout

Navigator tree with functional position names – logically ordered Position relative to a defined origin Equipment type and description from naming service Equipment dimensions Links to other information databases Drawing and documentation links

Current status of ELENA in the Database Currently only the main optics elements in the ring are registered: Equipment types and functional positions Middle points along the beam line (checked against layout drawings) Some links to drawings and EDMS items (magnets)

Future updates Start and end points along the beam path to be added for each component (mechanical lengths) – information from integration models and drawings. Vacuum information to be added with the assistance of TE-VSC: Chambers with start/end points. Location of interface points for instrumentation and pumps. Aperture information. *example from LHC

Future updates Functional positions to be added for supports (?). Electrical circuit information to be added, when well defined, with the help of TE-MSC and TE-EPC: Creates a link between magnets and power converters. Converters are extracted from the TE-EPC database, and linked to the relevant magnets using appropriately named circuits. Linking of drawings to equipment types for easy navigation to be completed. Transfer line information to be added where well enough defined (LNI, LNS, LNE).

Future updates A baseline to be set for the ELENA Ring (v.1.0 of the layout). Containing electrical circuits (~1 month) Vacuum detailed layout (~ weeks) Transfer lines to come later. Mechanical layouts (AD_LM___%) will have to be handled in parallel to the database. At the same time. After base-lining, any changes must be handled with ECRs (to ensure full impact analysis).

Additional information Various reports can be extracted from the Layout Database if needed. Optics data once the layout is fully complete – functionality needs to be set up with BE-CO and BE-ABP. Survey target point positions can be added if needed (?). *example from PSB

Product Breakdown Structure Data PBS (Hardware Baseline) structure exists in EDMS and is well populated with documents. Need to create ‘Items’ for all equipment and link them to the PBS. After this, ‘Assets’ can be created for each occurrence of a particular equipment type. See TE-MSC items as an example. Non conformities and test reports should be linked to assets, derived from items. Other document types (e.g. Hardware Commissioning procedures, operational procedures, maintenance procedures etc…) can be linked to the PBS, either in items or assets (?).

Thank-you for your attention Questions?