San Marcos Flooding Evacuation Analysts Geo-Referenced Locations for Geo-Referenced Locations and Events Project Manager Justine Williams Assistant Manager Joshua Bridges Web Master Alexander Nankervis GIS Analysts James David Smith Clayton Holbrook
Introduction
Data DOQQs DEMs 100 and 500 year FEMA flood planes TIGER
Methodology Locate Flooded Roads Find Underwater Road Segments Identify Areas Affected Modifications to Existing Roads Potential Alternative Routes
Implications Use Analysis to Save Lives Find Safe Routes Recommend Changes to Make Routes Safer
Budget Analysts GIS Analysts (3 analysts * $45.00 per hour * 100 hours total) $13,500.00 Management Project Manager ($65.00 per hour * 100 hours total) $6,500.00 Assistant Manager ($55.00 per hour * 100 hours total) $5,500.00 Equipment Costs Supplies ($150 per workstation * 5 workstations) $750.00 Maintenance ($200 per workstation * 5 workstations) $1,000.00 Workstations ($3000.00 / 24 mo. lifetime * 2.5 months * 5 workstations) $1,562.50 Software ($12000 / 24 mo. lifetime * 2.5 months * 5 workstations) $6,250.00 Total equipment costs $9,562.50 Total Costs $38,375.00
Timetable Week 4 5 6 7 8 9 10 11 12 13 Dates 9/25 - 10/1 10/2 - 10/8 10/9 - 10/15 10/16 - 10/22 10/23 - 10/29 10/30 - 11/5 11/6 - 11/12 11/13 - 11/19 11/20 - 11/26 11/27 - 12/3 Data Collection Processing Analysis Quality Assurance
Conclusion
Final Deliverables Report Poster Web Site CD