BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016 PANDA Solenoid Magnet Status of work BINP, Sergey Pivovarov, Panda magnet meeting at GSl, June 07, 2016
Coil winding procedures; An agreement on the status of work at BINP was achieved and include the production of PANDA solenoid magnet, assemblies and tests: PANDA yoke; Cold mass; Cryostat; Coil winding procedures; Electrical, control and safety system (with CERN collaboration); Assembly procedures at BINP; Cold and magnet tests at BINP; Assembly at FAIR.
Yoke, Platform and Frame
BINP received the specification of Yoke, Platform and Frame of PANDA detector on May 2015. According this specification we began work with BINP design department, technology department, BINP workshop and Russian plants. The last 3D models from February 2016
3D model of the Yoke, Platform and Frame .
BINP prepared assembly drawings of the one octant of Yoke with all requirement for the first variant of yoke design and for the second one. BINP carried out a few meetings with technical specialists of Russian plants. Next step: preparation of documents for a call for tender in Russian Federation.
Assembly drawing of the octant of Yoke with 12 layers of muon chambers
Assembly drawing of the octant of Yoke with 12 layers of muon chambers
The last assembly with 11 layers of muon chambers BINP received the new sketch of Yoke of PANDA detector on February 2016.
The last assembly drawing with 11 layers of muon chambers
The last assembly drawing with 11 layers of muon chambers
According this drawings the cost of yoke with frames and platform was estimated. Schedule of manufacturing and delivery of Yoke: Start of works 10.2016 Design works till 04.2017 Purchase raw material and instruments from 01.2017 till 01.2018 Manufacturing from 04.2017 till 06.2018 Tests in Novosibirsk side 09.2018 – 09.2019 Delivery to GSI according to contract Assembly and tests in GSI side according to contract
Cryostat and Valve Box
3D model of the Cryostat and Valve Box.
Assembly drawing of the Cryostat
BINP work in the near future, 2016: Agreement of the Technical Specification of Cryostat, cold mass, coil winding procedures, assemblies and tests; Cryogenic scheme should be approved together with CERN; Instrumentation should be approved together with CERN; Preliminary assembling drawings of Cryostat with coil; Preliminary technologic work; Manufacture and tests of PANDA solenoid magnet will be made at BINP.
Conclusion Manufactured assembly drawings of one octant are ready; Preliminary discussions with plants to produce of yoke held; Costs of Yoke, cryostat and coil are estimated; It is needed to prepare Technical Specification for delivery of PANDA solenoid magnet; It is planned to sign of contract with FAIR to delivery of PANDA solenoid magnet at September 2016
Thank for you attention!