Teleconference ACS – FREIA 10th May 2017

Slides:



Advertisements
Similar presentations
1.  Preparation of larger parts in a Clean room Class (ISO7)  Preparation of smaller parts in a “baldaquin” annex  Assembly in a clean-room Class.
Advertisements

Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
WUT Experience in Measurements of the Heat Transfer Thought SC Cable Electrical Insulation Jaroslaw Polinski*, Maciej Chorowski*, Michal Strychalski*,
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
2 Technical seminar - 5 th June 2014 Vincent Roger - TE-MSC-TF.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Assembly Organisation and Duration. Work Site Organisation STORAGE SMA18 UNLOADING CLEAN ROOM CERN-SITE CLEANING MANUFACTURE DIRTY TRIAL ASSEMBLY ISO7.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
1 HIGH ENERGY ACCELERATOR RESEARCH ORGANIZATION KEKB Review Committee/ NAKAI Hirotaka KEK Crab Cavity - Cryogenics - KEKB Crab Cavity Group - presented.
Agenda – Basics of cavity integration into CAST Introduction (M Davenport) Information exchange 2016 – Vacuum in cold bore – 2 cavities Cooling RF Cavities.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
EuCARD WP 7 – High Field Magnets Task – Radiation certification Status report EuCARD WP 7 – High Field Magnets Task 2 – Support studies Task
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
RESEARCH AND DEVELOPMENT FOR FUTURE LHC SUPERCONDUCTING MAGNETS POINT SUR LA STATION D’ESSAIS préparé par Jean-Marc Gheller Steering committee –September.
17-18 December 2013 LARP VTF Workshop BNL Proposal 1 A.Marone
Overview of On-going Cryogenic Work At the MTA Barry Norris AD/Cryo February 14, 2005.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S A Griffiths CM42 June 2015 Electrical & Control.
Final Design Cryogenic and mechanical configurations
Teleconf ACS – FREIA 28th March 2017
Teleconference ACS – FREIA 31th May 2017
Teleconf ACS – FREIA 13th March 2017
Mechanical and cryogenic configurations
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973
UPPSALA UNIVERSITY GERSEMI
Ti/SS transitions A.Basti INFN-PISA*
HFM Test Station Main Cryostat
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Teleconference ACS – FREIA 18th April 2017
News about the WA104 Programme
Cryostat design Mechanical design: Thermal screens: Specifications:
Teleconference ACS – FREIA 17th October 2017
Teleconference ACS – FREIA 31st October 2017
Diffuser status October 2017
From Design to Installation courtesy R. Folch S. Atieh TS / MME
(vertical cryostat, Gersemi)
Parts exchange for HL-LHC AUP Q1&Q3
Test box for ProtoDUNE SP – Integration Test
Cryostat design Mechanical design: Thermal screens: Specifications:
MICE Coupling Coil Update
Status of the PANDA Solenoid Magnet Production in BINP
FRESCA Cryostats Outer cryostat during pressure test at the manufacturer Top plate and lambda plate for the outer cryostat Inner cryostat during reception.
Teleconference ACS – FREIA 20th February 2018
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
Schematic diagram of the cryogenic system
Prototype cryomodule development
PANDA The conceptual design of the control Dewar
Double-Spoke Cavities
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
(vertical cryostat, Gersemi)
SNS PPU Cryomodule Instrumentation
SC1R Cold Box PDR Assembly Sequence
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Teleconference ACS – FREIA 10th May 2017 Agenda: Manufacturing follow-up Control and command Simulator – MicroGersemi Planning

Manufacturing follow-up Cryostat SOMINEX finished the vacuum vessel. Delivery expected middle of week 19. ACS has been invited by CD for the receiving tests at SOMINEX: Dimensional control, OK Cleaning control, OK helium leak control, OK Test installation for the vacuum vessel at SOMINEX Teleconf ACS - FREIA 10th May 2017

Manufacturing follow-up Dimensional validation using the 3D model Cryostat ACS measure the dimensions of the vacuum vessel to check with the pit Teleconf ACS - FREIA 10th May 2017

Manufacturing follow-up Dimensional validation using the 3D model Cryostat Distances between beams(roof) and components of the liquid insert Teleconf ACS - FREIA 10th May 2017

Manufacturing follow-up Cryostat The lambda seat has been re-machined to obtain the flatness Lambda seat installation on the machine tool Teleconf ACS - FREIA 10th May 2017

Manufacturing follow-up Cryostat CD performed the welding of the pressure vessel tubes X-ray test will be performed in week 19 CD expects the delivery of all parts soon to finish the welding of the pressure vessel, in week 20 Welding of the pressure vessel tubes Teleconf ACS - FREIA 10th May 2017

Teleconf ACS - FREIA 10th May 2017 Control and Command Connection boxes There will be 4 connection boxes placed on the systems: 1 for cryostat 1 for valve box 1 for magnet insert 1 for liquid insert Those boxes collect only the equipment operating at room temperature Schematic diagram of a connection box inside Sample of feedthrough for incoming wire Teleconf ACS - FREIA 10th May 2017

Teleconf ACS - FREIA 10th May 2017 Control and Command Connection boxes A 5th connection box will be placed in the pit and dedicated for the instrumentation of the inserts, Instrumentation of insert will be connected to the 5th box in which all insert instrumentation cables will be connected at the electrical cabinet The quotation is ongoing by ISII-Tech. Teleconf ACS - FREIA 10th May 2017

Teleconf ACS - FREIA 10th May 2017 Control and Command CB_INSERT CB_VB CB_VB CB_CRYOSTAT CB_INSERT Electrical cabinet IB CB_CRYOSTAT IB Electrical cabinet CB: connection box IB: instrumentation box (dimensions under estimated) Attempt to install the junction boxes and instrumentation box Due to a lack of space, welded supports seems require to maintain boxes as part of the cryostat and the insert while keeping access to the top lid and plate Teleconf ACS - FREIA 10th May 2017

Teleconf ACS - FREIA 10th May 2017 Control and Command Programming Sequences send to ISII-tech expected in week 21, Delay of programming: around 1 month Teleconf ACS - FREIA 10th May 2017

Simulator – MicroGersemi ACS and CD reviewed the design according to CD standards and workshop capacities Philippe Bujard is completing the manufacturing drawings Manufacturing drawings for externally proceed parts, (7 flanges over Ø150) expected week 19 Next weeks, the cryogenic scheme will be updated Teleconf ACS - FREIA 10th May 2017 Teleconf ACS - FREIA 18th April 2017

Planning An updated planning is under review at CD, expected week 19 Teleconf ACS - FREIA 10th May 2017 Teleconf ACS - FREIA 18th April 2017