DICKINSON AVENUE RECONSTRUCTION PUBLIC MEETING July 19, 2017 &
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT END PROJECT
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT 1.06 MILES END PROJECT
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT END PROJECT 1.09 MILES
DICKINSON AVENUE TOTAL 2.15 MILES PROJECT OVERVIEW BEGIN PROJECT END PROJECT
PROJECT OVERVIEW 10’ Concrete Multi-Use Path on east side of Dickinson No additional ROW required Approximate Construction Cost $9,300,000 Additional detention will be provided to account for additional pavement
DICKINSON AVENUE TYPICAL SECTIONS STORM SEWER SECTION
CURB & GUTTER / STORM SEWER SECTION – 50’ / 60’ ROW DICKINSON AVENUE CURB & GUTTER / STORM SEWER SECTION – 50’ / 60’ ROW EXISTING PROPOSED TRAVEL LANE TRAVEL LANE MULTI-USE TRAIL
DICKINSON AVENUE TYPICAL SECTIONS OPEN DITCH SECTION
OPEN DITCH SECTION – 70’ ROW DICKINSON AVENUE OPEN DITCH SECTION – 70’ ROW EXISTING PROPOSED TRAVEL LANE TRAVEL LANE MULTI-USE TRAIL
CONSTRUCTION / TRAFFIC CONTROL Bid separately as 2 projects Phase 1 – South Portion S.H. 96 to F.M. 646 – 12 months One- way detour phase – 4 months Phase 2 – North Portion E. Walker to S.H. 96 – 12 months One- way detour phase – 8 months Access to all properties will be maintained
DICKINSON AVENUE CONSTRUCTION TIME PHASE 2 – 12 MONTHS
SCHEDULE Public Meeting July 2017 70% Submittal July 2017 90% Submittal September 2017 Bid South Project (S.H. 96 to F.M. 646) October 2017 Construction South Project December 2017 – December 2018 (12 months) Bid North Project (E. Walker to S.H. 96) January 2019 Construction North Project March 2019– March 2020 (12 months)