CE Status: Activities executed until 03/08 and ongoing

Slides:



Advertisements
Similar presentations
Durra Eco-Form Cabins Build your own home and move in within a week Fast, Simple and Affordable.
Advertisements

CENF – Civil Engineering Extension B887 CERN: An accelerator complex unique in the world -Prevessin site complex- -EHN1 Extension Area- EHN1 Extension.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
19 February Summary: Updating on the activities completed (Done) since the last meeting List activities on going (Next steps) and related Actions.
Visit Gangway FromLHBIEP__0181 by Andre Coin ~ 2600 GANGWAY POSITION.
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 What is Precast Concrete? Precast concrete consists of a mixture of cement, water, aggregates and admixtures. This mixture is cast into a specific shape.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
EHN1 Extension overhead crane coverage Keith Kershaw CERN EN-HE.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
1 CV4902- Construction Methods Dr David Chew. 2 Construction Considerations Site layout plan Outline of entire construction process Details of temporary.
Transport and handling at CERN for FAIR
Status of AMS02 Integration Area in Building 867 January 10, 2007.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
2 IMPACT - THE FIRE PERMIT = Hot Work Permit 3 Welcome ! This course is linked to the use of IMPACT, so it is assumed that: You know how to use IMPACT.
Baby MIND coil modules assembly the aluminium folded strip solution 1 Alexey, Philippe, Gabriella, Helder, Herman Baby Mind Magnet CERN June.
Building 867 Project TE/MPE workshop status and schedule Presented by Tony Fowler, TE-ABT on behalf of the Project Team 28/09/2010Building 867 Project:
CENF – Civil Engineering Extension B887 Status – 02 October 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
The New Steel Erection Rule Developed by S teel E rection N egotiated R ulemaking A dvisory C ommittee (SENRAC) in 2001 Occupational Safety and Health.
Bidders’ conference IT-4123 Supply, Replacement and Repair of Crane Rails Technical Specification Handling Engineering Group.
22 October Summary: Updating of the activities carried out on-site (Done) in SEPTEMBER List activities on going (Next steps) and scheduled for OCTOBER.
CENF – Civil Engineering Extension B887 Status – 18 September 2014 Done: (1/2) Preliminary civil engineering drawing and Functional specification approved.
Contributions from BE -ABP -ASR -BI -CO DG -RP EN -CV -EL -MEF -STI GS -SEM -ASE IT -CSPH -CMXTE -CRG -EPC -MPE Follow.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
WA 104 : TOOLS FOR WORK ORGANIZATION IN THE CLEAN ROOM Erwan Bertrand Olga Beltramello.
EHN1 – EN/EL Progress update J. Devine G. Gross 11/02/16.
EHN1 – EN/EL Planning Lighting _ Containment_ Cabling J. Devine G. Gross 11/02/16.
19 February Extension of Building Neutrino Platform General Meetings N.Lopez – M.Manfredi EHN1 civil engineering project status Summary: Updating.
Work by contractors And Safety Coordination CONTRACTORS ’ ACTIVITIES What is the role of TSOs when contractors are working in their area? HSE Unit - Olivier.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
Status of AWAKE Installation and Integration Presented 9/3/2016 at the AWAKE Collaboration Meeting Ans Pardons, for the AWAKE CP4 team.
… getting there … 112/02/2014A. Fabich, EN-MEF-LE.
21 January Summary: Updating of the activities carried out on-site (Done) in DEC + ½JAN List activities on going (Next steps) and scheduled till.
10 December Summary: Updating of the activities carried out on-site (Done) in NOVEMBER List activities on going (Next steps) and scheduled for DECEMBER.
Museum of Islamic Art Project Package # 3 Site Logistics and Progress Presentation.
Schedule Access to the hall b508. Magdalena Kowalska.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
SPS Personnel Protection System Renovation Project
EHN1 Cryogenics Integration
Neutrino Platform Proximity Cryogenics 72th EHN1 Cryogenics Integration TE-CRG
Safety in the Neutrino Platform Hall
NP Hall Visits Guides’ training
IT-4337/SMB – Bidders Conference
Francois and Lau EATM 17 July 2012
EHN1 Extension planning
EHN1 Extension North Side wall (Removal of Existing services & platforms) Michael Jeckel & Bastien Rae.
San Luis Potosi – New plant April 24th 2015
INSTALLATION SEQUENCE
Budget specification EHN1 Extension: Infrastructure (WG2)
EHN1: CE Integration process updating
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
SR1 cleanroom extension
EHN1 Neutrino Installation Plans
East Hall under construction
USA-15 Compressor displacement for maintenance
East Hall under construction
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
How Remodeling Your Home or Business Can Cause False Alarms
On the accuracy of port assembly at Wendelstein 7-X
Commercial Project Bidding Solution
Instruments Shielding Project Installation
Neutron guide Shielding Concept
East Hall under construction
Polarized 3He target installation
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

CE Status: Activities executed until 03/08 and ongoing 19/07/2016 03/08/2016 (1) INSIDE HALL: Removal of last cladding separation and columns towards EHN1 completed. Rainwater pipes deviation and crane connection are done on Saleve side. Same activities are ongoing and scheduled for next week on Jura side. Removal of concrete wall is ongoing (~15m of 50m are done). Activity is supposed to be completed next week. Finishing works inside pits ongoing. Priority is given to Pit_B whose access has been asked by EP from 15/08  Upcoming Tasks: Slab btw existing and extension ; Metallic platform connecting w/ existing one at Jura side ; Finishing works Pit_A ; Overall finishing works on the slab and painting on metallic structure ; Materials disposal using existing Saleve door ; Skydômes commissioning ; Smoke screens installation

CE Status: Some photos_03/08/2016

CE Status: Some photos_03/08/2016

CE Status: Activities executed until 03/08 and ongoing (2) OUTSIDE HALL: Insulation package installation (Saleve+Jura side) completed. North side starts week 32. Cryo slab (Jura side) completed. Installation EU and Incendie networks ongoing.  Upcoming Tasks: EL slab ; External stairs and crinoline installation, Windows + Doors (supplied by CERN) installation ; Finishing works on cladding and roofing; Road and Networks completion; External arrangement

Next steps: Activities scheduled until 15/08 and after CERN activities has been reviewed after 15/08, following access requested by EP Permanent barriers installation (EN/ACE) delayed after CE handover ; Final light installation (EN/EL) delayed after CE handover ; EP needs to get access on Pit_B from 15/08 onwards Agreed date delayed EP activities in Pit_B delayed Pit_B handover to CERN before the 15/08 if possible! + Flatness works on the slab are still needed to reach EP needs 04/08 15/08 05/09 See MoM held on 02/08 btw SMB/EN/EP, URGENT ACTIONS TO EP Only CE contractors on site CE activities w/ EN-HE and EP teams

Next steps: Activities scheduled until 15/08 and after TABLE OF OVERALL ACTIVITIES W33 W33 SMB 1) Concreting process of slab #6 2) Finishing works (small modifications, cleaning, painting, etc..) EP 1) Technicians team access pit; 2) Installation + service supply ; 3) Bring equipm ; 4) Survey implantation control ; 5) Handling concrete blocks HE 1) Cable connection Saleve side 2) Crane commissioning on 19/08 condition - No crane - No slab risks - Difficulty to access extension for material and/or workers - EN/HE nacelle blocks passage - Crane commissioning Agreed date delayed EP activities in Pit_B delayed 04/08 15/08 05/09 Only CE contractors on site CE activities w/ EN-HE and EP teams

Next steps: Activities scheduled until 15/08 and after TABLE OF OVERALL ACTIVITIES W34 W33 W34 SMB 1) Concreting process of slab #6 2) Finishing works (small modifications, cleaning, painting, etc..) 1) Temporary barrier removal in Pit_A; 2) Skydome commissioning; 3) Smoke screens installation 4) Finishing works 5) Material disposal w/ crane EP 1) Technicians team access pit; 2) Installation + service supply ; 3) Bring equipm ; 4) Survey implantation control ; 5) Handling concrete blocks 1) Supports installation floor level ; 2) Final survey before floor installation 3) Unload 2 trucks of material in Pit_B 4) Check delivered pieces HE 1) Cable connection Saleve side 2) Crane commissioning on 19/08 - condition - No crane - No slab Crane_OK Slab_(?) risks - Difficulty to access extension for material and/or workers - EN/HE nacelle block passage - Crane commissioning - Skydomes commissioning - Smoke screen installation - Finishing woks in the entire hall Agreed date delayed EP activities in pit_B delayed 04/08 15/08 05/09 Only CE contractors on site CE activities w/ EN-HE and EP teams

Next steps: Activities scheduled until 15/08 and after TABLE OF OVERALL ACTIVITIES W35 W33 W34 W35 SMB 1) Concreting process of slab #6 2) Finishing works (small modifications, cleaning, painting, etc..) 1) Temporary barrier removal in Pit_A; 2) Skydome commissioning; 3) Smoke screens installation 4) Finishing works 5) Material disposal w/ crane 1) Pit_A finishing; 2) Decking platform Jura; EP 1) Technicians team access pit; 2) Installation + service supply ; 3) Bring equipm ; 4) Survey implantation control ; 5) Handling concrete blocks 1) Supports installation floor level ; 2) Final survey before floor installation 3) Unload 2 trucks of material in Pit_B 4) Check delivered pieces 1) Pieces installation on the blocks 2) Bolts and welded connection 3) Lift assembled system on support 4) Survey control HE 1) Cable connection Saleve side 2) Crane commissioning on 19/08 - condition - No crane - No slab Crane_OK Slab_(?) Slab_OK risks - Difficulty to access extension for material and/or workers - EN/HE nacelle block passage - Crane commissioning - Skydomes commissioning - Smoke screen installation - Finishing woks in the entire hall Agreed date delayed EP activities in pit_B delayed 04/08 15/08 05/09 Only CE contractors on site CE activities w/ EN-HE and EP teams

Conclusions: ACTIVITIES AFTER 15/08: All CERN activities scheduled after 15/08 inside the worksite area need to respect Safety Conditions imposed by a worksite of Category 1 EP and EN/HE must submit their procedures and the PPSPS to SOCOTEC for approval before works start EP and EN/HE reference persons must participate at the VIC, scheduled for the 09/08 at 15:30, with SOCOTEC, MOE and SMB SMB activities have the PRIORITY during this period. Claims generated by conflicts due of CERN activities must be avoided. The common goal of “Final CE Handover” for 05/09 has to be pursued REMIND: To access the CE worksite area, particular safety rules need to be respected, therefore for any visit, intervention, work, etc.., everyone is invited to taking contact w/ SMB reference person (Estelle FONTAINE or Martin MANFREDI).

New platform connecting existing one -> ISSUES 1) Implantation of 4 columns are inside “Supervised Area” OPTIONS: Either modify barrier position or we allow local intervention of SMB contractor beyond “declassified zone” ? 2) Two beams HEB200 will be placed btw axis 25 and 25b and connected to the side concrete wall. Conflict with existing services are detected. SOLUTION: Is it possible to temporarily or permanently remove them ?